Tips and tricks for commissioning, balancing buildings: Codes and standards

Building commissioning is one of the most important (and complex) types of projects an engineer can be tasked with. Codes and standard dictate many test, measurement, and verification techniques.

08/28/2013


Jerry Bauers, National director of commissioning, Sebesta Blomberg, Kansas City, Mo. Courtesy: Sebesta BlombergMichael P. Feyler, Co-director, building solutions group, RDK Engineers, Andover, Mass. Courtesy: RDK EngineersRobert J. Linder, PE, Senior project manager, Karges-Faulconbridge Inc., St. Paul, Minn. Courtesy: KFI EngineersJames Szel, Senior vice president, Syska Hennessy Group, New York City. Courtesy: Syska Hennessy GroupGeremy Wolff, Commissioning manager, McKinstry, Bellingham, Wash. Courtesy: McKinstryBarney York, Project manager, RMF Engineering, Baltimore. Courtesy: RMF Engineering

Participants


CSE: How have changing HVAC, fire protection, life safety, and/or electrical codes and standards affected your work in commissioning?

Wolff: NFPA requirements have changed the way we handle measurement on mechanical systems. It used to be pretty common for one of our engineers to open up the electrical panel on a rooftop unit to take amp/volt readings or install a data logger without thinking twice. Arc flash training has taught us this is something to be very careful with and there is a proper procedure to follow and personal protective equipment (PPE) that must be used. In Washington state, commissioning has been a requirement under the energy code since 1997. However, this code has been tough to enforce. The most recent version provides some additional compliance requirements with a compliance checklist that indicates the commissioning has been completed. We are now seeing inspectors looking for this document before they sign off on the final permits. One of the biggest challenges we face with regard to commissioning codes is one of education. There are a fair number of code officials that admittedly do not fully understand commissioning. We, the commissioning industry, have recently started to work closely with the International Code Council to provide educational programs to the AHJs on what commissioning is and, more importantly, what it is not.

Feyler: Building, mechanical, fire protection, life safety, and electrical codes change on a cycle, allowing for designers and CxAs to keep informed of changes as the codes update. Projects to be permitted after a code cycle change are the most difficult to perform design reviews of, so the CxA needs to become familiar with the adopted changes prior to the issuance of the new code. The CxA also needs to be familiar with the state the project is to be commissioned in, and be aware of what the adopted code is for that state and if the state has amendments to the adopted code. The CxA also needs to verify if the jurisdiction, city, town or county he or she is working in has the right to amend state adopted code or choose not to adopt portions or parts of state code. An example of this is Massachusetts; the state has the Stretch Energy Code, an addition to the building code. It provides a more energy efficient alternative to the standard energy provisions of the code. A municipality may choose to or chose not to adopt the addition.

York: I find more and more codes are now beginning to require that systems be commissioned as part of the acceptance process. The end result for CxAs is our scope of services has expanded, and we must find talented and highly skilled individuals to oversee and validate these systems. Building envelope, special inspections, and electrical testing are now becoming common request in requests for proposals (RFPs).

Szel: The changing codes are taken into consideration during the design process. We stay abreast of these codes to ensure the field installation is in compliance with the appropriate codes and standards. It is important for the design and commissioning teams to have full knowledge of all local codes and requirements, by the authority having jurisdiction (AHJ). The design and commissioning must be in compliance with those requirements. 

CSE: Which codes or standards prove to be most challenging in commissioning work?

York: The energy code has recently evolved as the most challenging. The local building codes have begun adapting the ASHRAE 90.1-2010 standard for energy performance and have increased the energy performance baseline dramatically. This increase in minimum energy performance has left designers with no choice but to design and implement more complex systems. These systems require CxAs to stay current with the latest technology and also knowledgeable enough to develop testing methods that verify equipment and system performance for systems not yet common in industry.

Szel: Challenging codes and standards are those related to energy and environmental issues, such as federal, state, and local standard and guidelines on air emissions, water, and wastewater disposal. Those are constantly changing. For critical facilities, such as data centers, meeting the guidelines or standards for high Tier level reliability requirements and high Tier level on emission requirements for emergency power generators can be challenging. The performance of system integrated testing or the final testing performed prior to turnover of the facility to the owner is challenging, but extremely beneficial. The performance testing is executed to demonstrate that the facility meets the facility basis of design basis (BOD), the applicable standards and guidelines, and the uptime facility reliability, integrated system performance testing is performed to demonstrate that the emergency power system (emergency generator, uninterruptible power supply (UPS) modules, battery systems, etc.) work on loss of utility or outside power supply. This test is done to validate that the design and installation are reliable with the required redundancy, to maintain the operation of all the supporting electrical and mechanical systems to support the continuous operation of the critical facility/data center equipment.

Wolff: Most commissioning standards or guidelines provide a very comprehensive process for commissioning, but the level of effort associated with each step isn’t clearly defined. This not only confuses owners when they are reviewing proposals, but doesn’t allow for a scalable program that meets the owner’s needs.

Feyler: Any time a project includes systems that are covered under the International Building Code Section 909: Smoke Control Systems, which inherently coincides with additional IBC code sections, applicable NPFA codes, and ASHRAE guidelines. The project becomes challenging to ensure that the design meets the applicable codes but also that the installations meet the design intent. Although the CxA is not normally acting as the special inspector, all the systems’ auxiliary equipment that forms the smoke control systems are commissioned by the CxA. The CxA looks at air handlers, exhaust systems, emergency generators, and fire alarm to ensure the installation requirements, control, and monitoring follow the applicable codes for the type of system designed.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Strategic outsourcing delivers efficiency; Sleeve bearing clearance; Causes of water hammer; Improve air quality; Maintenance safety; GAMS preview
World-class maintenance: The three keys to success - Deploy people, process and technology; 2016 Lubrication Guide; Why hydraulic systems get hot
Your leaks start here: Take a disciplined approach with your hydraulic system; U.S. presence at Hannover Messe a rousing success
Flexible offshore fire protection; Big Data's impact on operations; Bridging the skills gap; Identifying security risks
The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Applying network redundancy; Overcoming loop tuning challenges; PID control and networks
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Package boilers; Natural gas infrared heating; Thermal treasure; Standby generation; Natural gas supports green efforts

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
This article collection contains several articles on the vital role that compressed air plays in manufacturing plants.
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
This article collection contains several articles on strategic maintenance and understanding all the parts of your plant.
click me