Renovation Gold: Data crunch

12/01/2008


View the full story, including all images and figures, in our monthly digital edition

In the heart of Silicon Valley is a high-demand data center owned by Equinix. Equinix needed to rapidly expand and convert its existing data center (SV2 facility) in Santa Clara, Calif., to meet the growing number of customers who rent computer room space.

That meant the two-story, 160,000-sq-ft data center building needed a $50 million renovation. Less than a third of the 80,000-sq-ft second floor was already occupied by rentable space. The remaining 44,000 sq ft, which had been left as a gigantic empty room, needed to be converted into useable computer space as quickly as possible. The 80,000-sq-ft first floor included office space and a support equipment room. The half of that floor that contained electric and mechanical rooms needed renovation, too.

That's when San Jose-based Alfa Tech Cambridge Group (ATCG) stepped in. Equinix's target design time was 16 weeks. Instead, ATCG completed the design in less than 12 weeks by collaborating face-to-face with Equinix's technical staff.

Going green, saving big

“Data centers are known for being energy hogs,” said Tim Chadwick, who served as ATCG's project manager and has been with the company since 1994. “But we wanted to make it as energy-efficient as possible.”

To achieve its goal, ATCG considered using reclaimed water. The South Bay Water District was trying to find ways to use the water; if the non-saltwater ended up in the Bay, it would alter the Bay's delicate saltwater balance. To educate area residents, City Hall offered a class on recycled water. ATCG jumped on the idea, but then had to convince the city that it was in the city's best interest to dig up streets to add a branch line to ATCG's location in Santa Clara.

“We went on Google Earth and showed the city that the whole area around the job site was marked with data centers,” Chadwick said. “We convinced the city they could get a lot of users if they just built the line.”

Part of that approval resulted from ATCG's reminder that data centers draw water and power 24 hours a day, seven days a week, unlike a typical office building that experiences high demand only from 8 a.m. to 6 p.m. during the work week.

After it received the South Bay Water District's approval, ATCG had to convince an engineer in the Environmental Service Dept. that a reclaimed water line to the area was a good idea as well. Following that hurdle came a special meeting with the state health department.

“They were worried about cross connections and how the drinking water could be affected by the reclaimed water,” said Chadwick.

So ATCG submitted, on four different occasions, sets of drawings and site plans that showed how it would protect the water supplied—which included separating buried drinking water and reclaimed water pipes by 2 ft to make sure leaking water couldn't come near the drinking supply. An in-house team of four to five Equinix engineers assisted ATCG in the process.

The time-consuming process lasted from July 2007 until March 2008, but the end result was worth the trouble. Equinix needed only two water storage tanks—at 20,000 gal and 10,000 gal—saving it from adding a new 30,000-gal storage tank. This saved Equinix $300,000 in construction costs alone. The project also provided secondary savings since reclaimed water costs approximately 35% less than standard domestic water.

Another cost-savings concept came to light when ATCG added rooftop air handlers with an air-side economizer. Northern California's climate is ideal because temperature extremes are rare. Although adding an air-side economizer initially costs more, the annual savings of $318,000 per year meant in less than four years Equinix could recoup its costs and start saving money. The units also are equipped with atomizing humidifiers with RO water makeup that avoid the wasted energy associated with electric steam humidifiers and also provide the added benefit of free cooling when in use.

Because the data center required redundant air-handling systems to assure reliability in the event of a failure, ATCG was able to adjust the control sequence and added variable frequency drives (VFDs) to operate all air handlers at a reduced airflow rate. As a result, there was less of a pressure drop through each device and a net savings of 18% hp per fan, more than $51,000 a year in electrical savings.

Also for reliability reasons, redundant chilled water piping loops were installed. By using a control algorithm and VFDs, the system flow was split between each loop during normal operations, yielding an additional energy savings of $16,000 per year.

High-efficiency lighting sources were added to reduce lighting heat from fixtures in the hallways by 40%. Low-flow toilets were retrofitted in.

The existing 2,200-ton chiller plant was augmented to include 3,900 tons of capacity with the addition of two new variable-speed drive chillers. The most efficient chillers were staged to use first for optimal energy performance.

Challenges and solutions

Challenges included expanding and completing the construction without disrupting the existing 20,000 sq ft of live data center operations, and dealing with an inefficient existing infrastructure system that limited the overall building performance capabilities. (Think of the small business owners who would be furious when their Web sites went offline if the data center went down during the construction phase.)

To provide additional reliability, ATCG specified dramatic upgrades to the DDC system to provide redundant controllers for an all-new HVAC system, which provided control functionality in case a DDC ever failed.

“We consulted with several contractors who all said temporary generators were the only way to keep power going,” Chadwick said. “Instead we were able to save $100,000 by not using temporary generators.”

To do so, ATCG prepared detailed procedures for the changeover to eliminate the need for temporary generators. Stephanie Taylor, ATCG's lead electrical engineer for the project, said four pairs of paralleled, 2 MW, 12 kV generators were backed up by a ninth 2 MW, 12 kV “swing generator” that was held in reserve and could be used in the event of a breakdown.

The end result

ATCG hopes the project will be U.S. Green Building Council LEED certified in the near future. The former energy hog is now a highly efficient data center with a peak power usage effectiveness (PUE) of 1.66, well below the typical PUE average of 1.83 for data centers. That means for every 1 W of computer power, 0.66 W of power is being consumed by HVAC, lighting, etc.

Said Chadwick, “Peak PUE assumes the worst possible weather conditions and redundant equipment failures. With the redundant equipment and air-side economizer systems operating, an annualized PUE of 1.27 will be obtained.” Despite all the energy-efficient changes, which typically cost more up front, ATCG ended up 15% below the initial project budgets by implementing sustainable and cost-effective design strategies.

“Equinix told us this is the best project they've done in the last 10 years,” Chadwick said with a laugh. “It was a great project because we worked well together as a team.”





No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
World-class maintenance: The three keys to success - Deploy people, process and technology; 2016 Lubrication Guide; Why hydraulic systems get hot
Your leaks start here: Take a disciplined approach with your hydraulic system; U.S. presence at Hannover Messe a rousing success
Hannover Messe 2016: Taking hold of the future - Partner Country status spotlights U.S. manufacturing; Honoring manufacturing excellence: The 2015 Product of the Year Winners
The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Digital oilfields: Integrated HMI/SCADA systems enable smarter data acquisition; Real-world impact of simulation; Electric actuator technology prospers in production fields
Improving flowmeter calibration; Selecting flowmeters for natural gas; Case study: Streamlining assembly systems using PC-based control; CLPM: Improving process efficiency, throughput
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Warehouse winter comfort: The HTHV solution; Cooling with natural gas; Plastics industry booming

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
This article collection contains several articles on the vital role that compressed air plays in manufacturing plants.
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
This article collection contains several articles on strategic maintenance and understanding all the parts of your plant.
click me