CSIA Best Practices offer project management planning guidance

The Control System Integrators Association Best Practices and Benchmarks covers the use of project plans, providing advice on project management, including the following tips.

03/27/2013


The Control System Integrators Association Best Practices and Benchmarks, now in its fourth edition, covers the use of project plans. Information below on project management was adapted from section 5.3 of the manual.

Develop a project management plan

The project management plan incorporates the output of other sales and planning processes, including:

  • Sales and client needs analysis
  • Proposal
  • Historical information related to project and client
  • Client’s and integrator’s organizational policies (e.g., required templates or forms)
  • Existence of client project execution methodologies and standards
  • Constraints and assumptions. 

Content should follow the integrator’s defined project planning methodology.

Review the project management plan with project members and then present the plan to the client.

Review the plan to ensure the execution process is understood and meets client expectations. The size and complexity of the project will determine the level and extent to which the plan will be reviewed. Ultimately, the review process allows for client buy-in and approval. Review and approval processes should follow those defined in the integrator’s project methodology. 

Hold a kick-off meeting with the client.

Review the plan

The integrator should review the project management plan with the client. If not already covered as part of the project plan review, be sure to address and agree upon:

  • Commercial issues
  • Scope of work and change order control method
  • Shipping requirements

Clarify expectations

During the kick-off meeting, clarify expectations by reviewing and addressing:

  • Project quality plan intentions
  • Project process intentions and client’s role
  • Items that require client’s signed approval
  • Configuration management requirements
  • Known project risks and a risk management plan
  • Format and content of physical deliverables
  • Roles and expectations during commissioning of the final product
  • Other general project execution issues.

Manage the project according to the project management plan.

Continuously manage and update the project baseline and other elements of the plan throughout the life of the project as status and requirements change. Any changes should be reflected in the project management plan. Monitor performance and take corrective actions based on the plan. 

Gain approvals along the way

Get formal approvals during project execution.

Some suggested key items for which to obtain approvals are:

  • Functionality and interfaces to be delivered (requirements and specifications)
  • Project technical risk plan and the associated contingencies
  • Project quality plan (including test plan)
  • Architecture and design reviews
  • User screen format, content, and navigation
  • Panel drawings for release to vendor
  • Resources, schedule, and scope changes.

Jeff Miller, PMP, is director of project management at Interstates Control Systems Inc., and chair of the CSIA Best Practices Committee.- Jeff Miller, PMP, is director of project management at Interstates Control Systems Inc., and chair of the CSIA Best Practices Committee. For more information about CSIA, visit www.controlsys.org. Edited by Mark T. Hoske, content manager, CFE Media, Control Engineering and Plant Engineering, mhoske(at)cfemedia.com.

Online Links

See related article on Collaboration, visibility key to successful project automation plan below.

www.controlsys.org 

www.interstates.com 



Sarah , , 11/25/13 03:40 AM:

great post! very informative. i've learned more about project planning strategies at http://pioneeripm.com/en/blog
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.