Letters

Commissioning on campus I enjoyed reading the article “Commissioning on Campus” (CSE 04/08, page 27). The real-life scenarios especially piqued my interest. The author is correct in pointing out how the contractor's version of the design drawings would disturb the flow to the cooling towers, but on careful examination of the photo in Figure 1, a problem of equal or greater import ...

06/01/2008


Commissioning on campus

I enjoyed reading the article “Commissioning on Campus” (CSE 04/08, page 27). The real-life scenarios especially piqued my interest.

The author is correct in pointing out how the contractor's version of the design drawings would disturb the flow to the cooling towers, but on careful examination of the photo in Figure 1, a problem of equal or greater import is evident.

If we assume that each tower is supplied by an 8-in. line and the combined flow to the towers requires a 12-in. main, then the tee installed as shown is the wrong size. The tee should have been installed as a 12x12x8-in. tee with the reducer on the downstream side of the run. At the point where the combined flow splits, the cross-sectional area needs to be able to support the flow of two towers. Otherwise, the turbulence and resultant pressure drop would cause significant additional imbalance to the flow. If the installed configuration were allowed to remain, the full flow for two towers would be squeezed into an 8-in. tee. This just adds credence to the fact that engineers need to be diligent when making field observations.

Anthony J. Curiale , CPD, LEED AP Associate Principal Buro Happold Consulting Engineers New York

Author responds:

Anthony Curiale's point is well taken, but in this particular instance, the lines are generously sized. Total flow is about 492 gpm, and each branch is designed for about 50% of that capacity, so the friction rates are pretty low. In the table that accompanies the article, I contrast the losses at the design flow rate with the limiting condition, which I arbitrarily chose as a flow rate that would create a friction rate in the range of 4-ft water column/100-in. in a 6-in. line.

The reality was that the designer specified and had installed towers with oversized outlets (8 in.) and the plan view drawings indicate that the entire return system should have been run at that size. A schematic shows the tower outlets reducing to 6-in. branches coming into an 8-in. tee with an increaser (or reducer, depending on whether you are an optimist or pessimist) on the run of the tee, but not the branch. So that would imply some sort of reducing tee. I suspect if we had to argue the case, we could have changed everything based on the drawings. But, because it was already there, and because the system could be made to work as installed, we focused on changes where there were more benefits to be realized. Still, it was frustrating to have it all laid out for the best of worlds and not installed that way—as opposed to having a set of documents where a nice arrangement is not so clearly defined.

At any rate, given the relatively low flow rate for the line size and due to space constraints on my article, I did not elaborate on the size of the tee. But, as Mr. Curiale points out, a better practice would have been for the installer to increase the line size and put the tee in at the size of the main leaving it rather than the branch entering it. The only reason it wasn't an issue was because of the generous sizing of the piping system. I suspect, knowing the designer, that the line sizes were based on some lifecycle cost factors, given the nature of the facility and the associated design life. Large line sizes translate to lower pumping energy requirements in a system that must run around-the-clock. In addition, they make the system more forgiving of field issues such as the one that is discussed in the article.

David Sellers , PESenior EngineerFacility Dynamics EngineeringPortland, Ore.

Clarification

In the Case Study department in the May ( CSE 05/08) issue, “Academic Center schools in electrical distribution” (page 64), CSE incorrectly identified Square D as a division of Schneider Electric North American Operating Division. Square D is a Schneider Electric brand of electrical distribution equipment.



Letters

Send your letters to Michael Ivanovich, editor-in-chief, Consulting-Specifying Engineer , 2000 Clearwater Drive, Oak Brook, IL 60523, or via e-mail tomichael.ivanovich@reedbusiness.com.

Letters should be no longer than 200 words, and may be edited for space, style, spelling, and grammar.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Strategic outsourcing delivers efficiency; Sleeve bearing clearance; Causes of water hammer; Improve air quality; Maintenance safety; GAMS preview
World-class maintenance: The three keys to success - Deploy people, process and technology; 2016 Lubrication Guide; Why hydraulic systems get hot
Your leaks start here: Take a disciplined approach with your hydraulic system; U.S. presence at Hannover Messe a rousing success
Flexible offshore fire protection; Big Data's impact on operations; Bridging the skills gap; Identifying security risks
The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Applying network redundancy; Overcoming loop tuning challenges; PID control and networks
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Package boilers; Natural gas infrared heating; Thermal treasure; Standby generation; Natural gas supports green efforts

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
This article collection contains several articles on the vital role that compressed air plays in manufacturing plants.
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
This article collection contains several articles on strategic maintenance and understanding all the parts of your plant.
click me