How to eat a chocolate elephant: Step by step method to reduce lead time

To reduce lead time, the first step is to prioritize the operations which will yield the most results, then review transactional history to check actual performance.

03/26/2015


How do you eat a chocolate elephant? Well, the answer is easy and well-known – one bite at a time. The same is true when nibbling away at reducing lead time. Courtesy: Daniel Penn Associates, LLCHow do you eat a chocolate elephant? Well, the answer is easy and well-known – one bite at a time. The same is true when nibbling away at reducing lead time. A value stream map identifies opportunities through the build-up of work-in-process (WIP) which exists between operations in a process.

The first step is to prioritize the series of operations which will yield the most significant results. Nothing ensures continuous improvement like early success, and the bigger the success, the more momentum a team will gain in working to gain further improvements.

There are two ways to determine lead time.


The first is by checking actual 

performance, through reviewing transactional history from routers attached to the material. This should be done during the data gathering phase of the value stream mapping process. If routers aren’t used, then transactional history may be taken from the enterprise resource planning system’s material management module.

To reduce lead time, the first step is to prioritize the operations which will yield the most results, then review transactional history to check actual performance. Courtesy: Daniel Penn Associates, LLC

The second method, and perhaps even more revealing, is to calculate the lead time using Little’s Law. While on the data gathering walk of the VSM event, count the inventory at each operation. Then, use the simple formula. Little’s Law is simply expressed by dividing the amount of work-in-process by the daily requirement. The result yields the number of days of lead time.

(Hint: Don’t mix methods! Use the actual days from routers OR Little’s Law). Regardless of how the team arrives at the lead times, the work of the following kaizen events is to reduce lead times.

The kaizen team should regard every queue as the waste that it is. Work-in-process should not be arbitrarily reduced to 0. The technique is known as “Lean”, not “Anorexic”. The correct amount of work-in-process is calculated by dividing the operation’s total cycle time by takt time. This result yields standard work-in-process(SWIP).

Now, the team must consider the current limitations to reducing current WIP to SWIP. Daniel Penn Associates, LLC There may be a lengthy change-over that’s not a SMED (single minute exchange of dies), but more like a SHED (single hour exchange of dies). There may be staffing issues, which reveals the need for standard work combinations and effective cross-training. More complex an issue may be large equipment installations that preclude co-locating into a cell or process layout. Along with implementing improvements, visual controls must be put in place so there’s no ‘augmentation’ to the defined SWIP. And, any amounts of WIP in excess of WIP required by current process limitations remain targets for further kaizen.

Case study:

A company had identified opportunities through a value stream mapping event. They divided the process into four major VSM planning loops, with a fifth loop focused on administrative (planning, forecasting and order receipt) activities. They saw opportunities with the final sequence of operations – two inspection operations, an assembly kitting operation, and a final pack operation.

The material is lot-controlled, so the parts can maintain traceability through the entire product lifecycle, an important requirement in the industry they serve. Parts would pile up while inspectors were performing other duties – the symptom of large lot, batch method material movement. When orders became due, or overdue, then it was an all hands on deck call to hustle material through the operations and onto a plane to the customer. This approach chews up a lot of space, a potential quality issue with mixed lot materials, and the pressure to get stuff out the door almost at all costs.

How about air-freight and overtime costs? The team used the Little’s Law approach to calculate lead time – 10.5 days of WIP. The sum of all operations’ cycle times was 10 minutes, which is about one minute of work per day per piece (not a great example of material flow).

They calculated standard work-in-process, which worked out to be 2. They decided that each of two different products (size and number of pieces per assembly set), it would be best to establish two inspection cells, facilitating flow for each product. Then the SWIP was now 1 for each cell. As the parts were inspected, kitted (left and right for the large parts; left, right and center for the smaller parts, and bagged, they were placed on a cart bound for pack. When the SWIP was reached – indicated by the filling of the rack on the cart, it was wheeled out of the clean room to a packing station where the inspector would final pack the parts, print the label, and call for pick up from shipping. They would then return to the clean room to commence inspecting the next group of parts.

While it would be a perfect ending to say this ended the air freight, it did not, at least right away. When there was enough in the supply chain, the company was able to start shipping by truck, so that air freight is an occasional charge, not a daily expense.

The total cost of the improvements was about $500 – a cart, some racks, and some colored tape. Lead time was 10.5 days and is now 5 days. The team stays focused on further improvements to reduce the WIP to SWIP, which would result in a 2 day lead time.

Chocolate elephant? Not completely eaten, but it’s lost some weight!

Tom Voss is senior consultant at Daniel Penn Associates, LLC. He has developed and implemented Lean enterprise solutions for more than 15 years. Trained and mentored in Lean concepts by the founders of Shingijitsu Company, Ltd., renowned experts of the Toyota Production System. Daniel Penn Associates, LLC is a CFE Media content partner. Edited by Joy Chang, digital project manager, Plant Engineering.



Top Plant
The Top Plant program honors outstanding manufacturing facilities in North America.
Product of the Year
The Product of the Year program recognizes products newly released in the manufacturing industries.
System Integrator of the Year
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
October 2018
Tools vs. sensors, functional safety, compressor rental, an operational network of maintenance and safety
September 2018
2018 Engineering Leaders under 40, Women in Engineering, Six ways to reduce waste in manufacturing, and Four robot implementation challenges.
July/Aug
GAMS preview, 2018 Mid-Year Report, EAM and Safety
October 2018
2018 Product of the Year; Subsurface data methodologies; Digital twins; Well lifecycle data
August 2018
SCADA standardization, capital expenditures, data-driven drilling and execution
June 2018
Machine learning, produced water benefits, programming cavity pumps
Spring 2018
Burners for heat-treating furnaces, CHP, dryers, gas humidification, and more
October 2018
Complex upgrades for system integrators; Process control safety and compliance
September 2018
Effective process analytics; Four reasons why LTE networks are not IIoT ready

Annual Salary Survey

After two years of economic concerns, manufacturing leaders once again have homed in on the single biggest issue facing their operations:

It's the workers—or more specifically, the lack of workers.

The 2017 Plant Engineering Salary Survey looks at not just what plant managers make, but what they think. As they look across their plants today, plant managers say they don’t have the operational depth to take on the new technologies and new challenges of global manufacturing.

Read more: 2017 Salary Survey

The Maintenance and Reliability Coach's blog
Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
One Voice for Manufacturing
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Maintenance and Reliability Professionals Blog
The Society for Maintenance and Reliability Professionals an organization devoted...
Machine Safety
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
Research Analyst Blog
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Marshall on Maintenance
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
Lachance on CMMS
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
Material Handling
This digital report explains how everything from conveyors and robots to automatic picking systems and digital orders have evolved to keep pace with the speed of change in the supply chain.
Electrical Safety Update
This digital report explains how plant engineers need to take greater care when it comes to electrical safety incidents on the plant floor.
IIoT: Machines, Equipment, & Asset Management
Articles in this digital report highlight technologies that enable Industrial Internet of Things, IIoT-related products and strategies.
Randy Steele
Maintenance Manager; California Oils Corp.
Matthew J. Woo, PE, RCDD, LEED AP BD+C
Associate, Electrical Engineering; Wood Harbinger
Randy Oliver
Control Systems Engineer; Robert Bosch Corp.
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Design of Safe and Reliable Hydraulic Systems for Subsea Applications
This eGuide explains how the operation of hydraulic systems for subsea applications requires the user to consider additional aspects because of the unique conditions that apply to the setting
click me