Case study: DCS migration challenges and obstacles for process manufacturer

An industrial utility service company in Kentucky needed to upgrade and migrate its distributed control system (DCS), which came with a few challenges.

By Josh Dalzell January 30, 2019

DTE Calvert City (DTECC) in Kentucky made the decision three years ago to upgrade its obsolete Process Suite HMI to APACS OS. For 15 years, the APACS distributed control system (DCS) had been a reliable and comfortable system used to maintain the operational functionality for a plant that generated power and utilities around the clock. However, now the APACS hardware lifespan was coming to an end due to a decrease in both new and used replacement components, and a lack of support for its human-machine interface (HMI) and hardware.

Cross Company, a certified PCS7 solution partner for Siemens, had built trust with DTECC by implementing the smooth transition to APACS OS. DTECC reviewed its needs, concerns, and questions and chose Cross Company to migrate the APACS DCS to a full Siemens PCS 7 system implementation.

Key upgrade challenges

With any change and upgrade, even to a modern system, there will be issues along the way. To begin with, there is the initial fear of the change itself. If we are not sure what will happen, good or bad, we may fear that it will be overwhelming, causing us to avoid that change and deny that there is a problem that requires the change. In the specific case of DTECC and its migration, the upgrade challenges included:

  • DTECC supplies industrial utility services to a number of chemical facilities in the area that include power via a gas turbine generator, softened water, steam, and compressed air. Its customers need a constant supply, so how could an upgrade take place with minimal downtime so as to minimize a loss of revenue for DTECC and its customers? APACS does not have a direct migration tool for moving to PCS 7.
  • APACS OS, while fundamentally using a Siemens WinCC supervisory control and data acquisition (SCADA) system, is configured with a third-party tool that write-protects the project database.
  • The initial PCS 7 version was 9.0 but had initial issues with the redundancy library, thus the project was migrated to version 9.0 SP1 during the implementation.
  • Following that, there were issues installing the Modbus (a method used for transmitting information over serial lines between electronic devices) library on PCS 7 V9.0 SP1.

The power of a systems integrator partnership

Braintrust is a powerful asset and Cross Company’s professional team has had experience with similar transitions. DTECC already had a positive working relationship with Cross and was able to discuss previous control system support and DCS upgrade projects. Additionally, Cross had personnel within a few hours of the site for continued support and improvements on a long-term basis. DTECC relied on its trusted relationship with Cross to discuss concerns and find reasonable and agreeable solutions.

Planning overcomes obstacles

Identifying key issues is an important part of the problem-solving process, but once those are determined, it is equally important to determine the next course of action. DTECC brainstormed with Cross engineers to mutually understand the goal of the process, review potential solutions or combinations of solutions, evaluate those options, and agree on contingencies and future review.

Things can be very different on paper than they are in the field, so Cross engineers used a mix of planning and situational problem solving to achieve their goal within the timeframe provided.

  • After discussing all possible options, a black plant (a plant that shuts down complete power) was scheduled for three days. To minimize issues or complications during the outage and speed up installation, Cross engineers planned the migration and rigged all necessary panels with more than roughly 2,500 input/output (I/O) points and used electronic marshaling which replaces manual cross-marshaling of field wiring with digital mapping.
  • The WinCC project was migrated by creating a new OS project, copying graphics, and using import/export functionality to move configurations for alarms, tags, scripts, etc., into the new OS project.
  • APACS logic was programmed manually for all initial implementations. Upon that successful completion, bulk engineering, copy/paste, and Process Object View were used to replicate code to all duplicate units.
  • Siemens tech support was able to provide a manual workaround for the version issue with the redundancy library until a permanent fix was developed through a software update.
  • The Modbus library installation issue was resolved after manual steps were completed.

Final thoughts

Change is an inevitable facet of our lives, but how we respond to change can determine the path that we take and where we end up. We can choose to ignore a problem in the hopes that it will go away, however, history shows us that this approach to change leaves us reacting to a situation (i.e., cleaning up a mess) instead of responding to it (i.e., proactive measures).

The migration to PCS 7 allowed DTECC to operate its facility on a current, state-of-the-art, well-supported system with a clear and reliable upgrade concept for future expansion. As time marches on, DTECC will continue to look to its trusted systems integration partners to maximize time management and improve production costs. APACS DCS was a reliable product, but those who have not yet migrated are encouraged to schedule a consultation to remain relevant in the industry, to stay within the production-possibility curve (PPC), and to understand the value that a modern system can offer.

DTE Calvert City is part of the DTE Energy P&I group of companies. The DTE Energy P&I Group focuses its products and services on energy-intensive industrial, commercial, and institutional customers across North America.

This article appears in the Applied Automation supplement for Control Engineering and Plant Engineering.

Original content can be found at Control Engineering.


Author Bio: Josh Dalzell is a systems integration engineer in the process control integration group at Cross Company, a CFE Media content partner.