Build a maintenance schedule in six steps

Manufacturers should build a weekly maintenance schedule that addresses potential conflicts and address overdue preventive maintenance (PM) tasks.

04/05/2017


Image courtesy: CFE MediaStruggling to put together a complete weekly schedule? It may surprise you, but you're not alone. Although the processes of work execution (preventive and predictive programs, planning, scheduling, coordination, storeroom and production partnerships) are foundational, many groups struggle to put it all together well. Without this foundation, more advanced concepts fizzle out quickly. Frustration ensues.

There are many pieces that need to be aligned to complete the entire work execution puzzle. To start, let's focus on developing the weekly maintenance schedule. There are six basic steps that you should address to move things forward.

1. Quantify the maintenance backlog

The backlog represents a comprehensive list of all work yet to be completed. It may include overdue preventive maintenance (PM) tasks, corrective actions, safety items and so on. Overdue PM tasks in the backlog highlight problems in your work processes. Determine if the work is complete. If the tasks and frequencies are valid and not done, then we can expect failures as well as a reactive state with equipment availability.

Backlogged work orders should not have birthdays of the annual sort. If it's been on the list for a year, most likely it is not important. Remove unnecessary work orders from the backlog. Now, place labor estimates on the work in the backlog. You need these hours to determine the how many crew weeks of backlog exist. The backlog metric should be trended at least monthly based on the hours, not the number of work orders.

2. Determine your ability to accomplish maintenance work

At the end of the day, the goal is to schedule more work. To do this you need to understand the available crew size for each week. Personally, I prefer the maintenance supervisor to work with the maintenance planner scheduler to provide those estimated available hours at least two weeks out.

Things may change—people take a vacation, get sick, have family emergencies—but you need a starting place. Maybe you're too reactive and don't believe you have the resources to schedule 100% of the available hours. So start with 60%. Just start.

3. Find windows for maintenance work

The planner scheduler role knows the maintenance backlog. As such, those individuals should be looking for and negotiating for maintenance work windows. This effort requires working with production or operations and planning in partnership. Some organizations have a production gatekeeper to help move things along. There are lots of windows for work that are often overlooked.

4. Build the draft maintenance schedule

Now we should understand the PMs that are triggering each week at least two weeks in advance. Future work has received some level of maintenance planning. We've identified the maintenance backlog. We know our estimated hours available for work. We understand the production windows. Time to build the schedule for next week.

Assuming a Sunday to Saturday schedule, this should be completed by Tuesday of the week prior. Ultimately, we want to get at least two weeks ahead, but start somewhere. Knowing available equipment windows, we can place that work on those days or windows. Once built, email the draft to the stakeholders, including production managers and supervisors. Ask for people to come with changes before the weekly scheduling meeting so those changes can be integrated early.

5. The weekly maintenance scheduling meeting

This meeting should be on late Thursday or early Friday so that the meeting time is close to the start of the schedule period. Fewer changes occur that way. Keep in mind it's not a planning meeting but a scheduling meeting to confirm next week's work as a minimum, along with any special coordination activities.

The planning part should have happened long before this meeting to ensure parts and time to plan. There are two main components for this meeting: next week's schedule and a review of the previous week's metrics. Part of the metrics review must include schedule breakers that prevented you from accomplishing the schedule. Keep it short and sweet.

6. What gets measured, gets done

While the metrics discussion is a longer subject in itself, make sure you have a progression plan using measures for continuous improvement.

Jeff Shiver, CMRP, is a founder of People and Processes, a consulting and training group.



Golden , Non-US/Not Applicable, Zimbabwe, 04/13/17 10:54 AM:

Quite interesting good article.
Chandranshu , Non-US/Not Applicable, India, 04/20/17 11:21 AM:

Very useful and practical points.
Paul , WV, United States, 04/20/17 01:47 PM:

Very quick and to the point article. Keeping up with the backlog is key.
Anonymous , 04/20/17 02:38 PM:

Good sound advice especially "Find windows for maintenance work". Too often planners and schedulers only observe large windows to perform maintenance work. Inspection PMs can usually done during short gaps in production but can lead to opportunities to identify issues that require parts and planning.
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Safer human-robot collaboration; 2017 Maintenance Survey; Digital Training; Converting your lighting system
IIoT grows up; Six ways to lower IIoT costs; Six mobile safety strategies; 2017 Salary Survey
2016 Top Plant; 2016 Best Practices on manufacturing progress, efficiency, safety
Mobility as the means to offshore innovation; Preventing another Deepwater Horizon; ROVs as subsea robots; SCADA and the radio spectrum
Future of oil and gas projects; Reservoir models; The importance of SCADA to oil and gas
Big Data and bigger solutions; Tablet technologies; SCADA developments
Automation modernization; Predictive analytics enable open connectivity; System integration success; Automation turns home brewer into brew house
Commissioning electrical systems; Designing emergency and standby generator systems; Paralleling switchgear generator systems
Natural gas for tomorrow's fleets; Colleges and universities moving to CHP; Power and steam and frozen foods

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
This digital report will explore several aspects of how IIoT will transform manufacturing in the coming years.
Motion control advances and solutions can help with machine control, automated control on assembly lines, integration of robotics and automation, and machine safety.
Compressed air plays a vital role in most manufacturing plants, and availability of compressed air is crucial to a wide variety of operations.
Maintenance Manager; California Oils Corp.
Associate, Electrical Engineering; Wood Harbinger
Control Systems Engineer; Robert Bosch Corp.
click me