Stop corrective maintenance repairs on preventive maintenance work orders

There has been a lot of discussion as to why we are asking technicians to write corrective work orders for problems found on a PM instead of fixing the issue on the spot. If we consider the example of the four machines below, it becomes clear why this is the case.

03/24/2016


There has been a lot of discussion as to why we are asking technicians to write corrective work orders for problems found on a PM instead of fixing the issue on the spot. If we consider the example of the four machines below, it becomes clear why this isThere has been a lot of discussion as to why we are asking technicians to write corrective work orders for problems found during preventive maintenance (PM) instead of fixing the issues on the spot. If we consider the example of the four machines below, it becomes clear why this is the case.

A technician is assigned a two-hour PM for each of the machines below. As he checks No. 1, there are no issues found and the PM is completed with no corrective work order generated. As the inspection of No. 2 begins, he notices an issue. It is not very critical and could wait until next weekend, but he decides to fix it anyway. The repair takes another two hours. He moves on to machine No. 3. There are no issues that demand immediate attention. Since the PM of No. 2 and the corrective work order to fix the issue have taken a total of four hours, it is now time to go home and the PM for machine No. 4 does not get done.

The problem is, machine No. 4 has a failure in it that will shut the machine down in a day if not detected. The next shift coming in has its own list of things to do and will not get to the PM on machine No. 4 that the previous shift did not complete.

What we are trying to accomplish is to get as many failures detected as early on in the failure curve as possible. Some repairs need to happen as soon as the fault is detected, but most times this is not the case. We need to adopt an inspection mindset when doing a PM and provide a clearly written corrective work order when a failure is detected. When we plan for a repair, all of the parts can be ordered and the job will take less time. This is not the way things have been done in the past, but we cannot continue to do things the same way and expect better results. We must change the way we operate in order to improve.

—Rick Clonan is a reliability supervisor at Nissan Motor Corp. This article originally appeared on ReliabilityNOW. Eruditio is a CFE Media content partner. Edited by Erin Dunne, production coordinator, CFE Media, edunne@cfemedia.com



Top Plant
The Top Plant program honors outstanding manufacturing facilities in North America.
Product of the Year
The Product of the Year program recognizes products newly released in the manufacturing industries.
System Integrator of the Year
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
June 2018
2018 Lubrication Guide, Motor and maintenance management, Control system migration
May 2018
Electrical standards, robots and Lean manufacturing, and how an aluminum packaging plant is helping community growth.
April 2018
2017 Product of the Year winners, retrofitting a press, IMTS and Hannover Messe preview, natural refrigerants, testing steam traps
June 2018
Machine learning, produced water benefits, programming cavity pumps
April 2018
ROVs, rigs, and the real time; wellsite valve manifolds; AI on a chip; analytics use for pipelines
February 2018
Focus on power systems, process safety, electrical and power systems, edge computing in the oil & gas industry
Spring 2018
Burners for heat-treating furnaces, CHP, dryers, gas humidification, and more
April 2018
Implementing a DCS, stepper motors, intelligent motion control, remote monitoring of irrigation systems
February 2018
Setting internal automation standards

Annual Salary Survey

After two years of economic concerns, manufacturing leaders once again have homed in on the single biggest issue facing their operations:

It's the workers—or more specifically, the lack of workers.

The 2017 Plant Engineering Salary Survey looks at not just what plant managers make, but what they think. As they look across their plants today, plant managers say they don’t have the operational depth to take on the new technologies and new challenges of global manufacturing.

Read more: 2017 Salary Survey

The Maintenance and Reliability Coach's blog
Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
One Voice for Manufacturing
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Maintenance and Reliability Professionals Blog
The Society for Maintenance and Reliability Professionals an organization devoted...
Machine Safety
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
Research Analyst Blog
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Marshall on Maintenance
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
Lachance on CMMS
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
Electrical Safety Update
This digital report explains how plant engineers need to take greater care when it comes to electrical safety incidents on the plant floor.
Maintenance & Safety
The maintenance journey has been a long, slow trek for most manufacturers and has gone from preventive maintenance to predictive maintenance.
IIoT: Machines, Equipment, & Asset Management
Articles in this digital report highlight technologies that enable Industrial Internet of Things, IIoT-related products and strategies.
Randy Steele
Maintenance Manager; California Oils Corp.
Matthew J. Woo, PE, RCDD, LEED AP BD+C
Associate, Electrical Engineering; Wood Harbinger
Randy Oliver
Control Systems Engineer; Robert Bosch Corp.
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me