Seven reasons why your RCA is not getting results

Root Cause Analysis (RCA) can be a very powerful tool for eliminating defects and increasing efficiency and profits. Below are seven reasons why your RCA might not be working for you.

09/15/2017


Root Cause Analysis (RCA) can be a very powerful tool for eliminating defects and increasing efficiency and profits. I have noticed seven common pitfalls that prevent practitioners from getting maximum value from their RCA efforts. Below is a brief look at each of them. Image Courtesy: Helloquence on Unsplash

1. Not digging deep enough into the problem.

This manifest itself as either getting stuck on the physical causes which leads to replacing a lot of parts and solving the symptoms but not the true problem or even worse the human cause where it becomes an exercise in blame analysis. A gentleman by the name of Deming addressed this when he said "Blame the system not the people" The system or systemic cause allows for many if not all of the human mistakes to exist. 

2. Too many root cause investigations per month because the process triggers that kick off an investigation are too low.

The triggers can be set up to work off of a certain amount of downtime or cost or lost production or safety etc. or a combination of multiple elements but they should be set up to change as you mature into RCA. If you have the triggers set too low or if you are relying on management to ask for the investigation then you could have too many RCA investigations and reports to complete each month. It is also important not to forget that for every RCA there is multiple action items that must be assigned, completed, and verified. Can your systems and resources support that if you are busy generating RCA reports every time the wind blows?

3. Too much time spent on the report and not enough time spent on the implementation and follow up.

I am sure very few of you work for company that make RCA reports as a product. My guess is your  company probably makes wigits and walumps and in the end a three pound final report does not add anything to the bottom line or any more margin on your widgets. Please remember the company is not paid by the pound of report, we are paid by the solution and the return on investment we generates.

4. Lack of solid well understood and applicable tools and process.

Many sites have one side of this coin or the other and it is a major distraction. One site I visited in Brazil had great processes for problem identification and prioritization but the reliability engineers were using five whys as their only tool and were really missing the returns that they could have had.  Another site had a great selection of tools to help understand the causes of the problem but their "corporate" RCA process had not been accepted and implemented. This lead to great findings and solutions but no way to ensure that they were ever implemented or if they truly solved the problem.

5. Don't ask the right question and you will miss major causal chains.

To help to mitigate this one use some thing like design and application review and follow up with change analysis to perfect your questions before you start your in-depth investigation and interviews. If you do this correctly you reduce the amount of time you will spend stopping and gather additional data during the analysis phase.

6. Findings and solutions are not verified to ensure that they effectively eliminated the original problem.

When this step is done correctly the site uses quantifiable metrics to measure the solutions that were identified and they are done at intervals that verify a sustainable long term solution.

7. Neglect to put focus on ensuring the best return on investment.

If you use the correct tools and you dig down into the problem you should be left with multiple possibilities for resolution of the problem. Once you have this identified you can evaluate the cost to implement and the effectiveness of the solution to see which action or combination of actions gives you the best overall return on the problem. In the end we change our thinking on analysis and it becomes less about finding "root cause" and more about finding the most effective and lowest cost mitigation or elimination strategy.

After reading through these seven common causes of "root cause failure" I hope you recognized a few and can eliminate them from taking the profits out of your process.

Shon Isenhour, content marketing, Eruditio LLC. This article originally appeared on Eruditio's website. Eruditio is a CFE Media content partner.



Top Plant
The Top Plant program honors outstanding manufacturing facilities in North America.
Product of the Year
The Product of the Year program recognizes products newly released in the manufacturing industries.
System Integrator of the Year
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
October 2018
Tools vs. sensors, functional safety, compressor rental, an operational network of maintenance and safety
September 2018
2018 Engineering Leaders under 40, Women in Engineering, Six ways to reduce waste in manufacturing, and Four robot implementation challenges.
July/Aug
GAMS preview, 2018 Mid-Year Report, EAM and Safety
October 2018
2018 Product of the Year; Subsurface data methodologies; Digital twins; Well lifecycle data
August 2018
SCADA standardization, capital expenditures, data-driven drilling and execution
June 2018
Machine learning, produced water benefits, programming cavity pumps
Spring 2018
Burners for heat-treating furnaces, CHP, dryers, gas humidification, and more
October 2018
Complex upgrades for system integrators; Process control safety and compliance
September 2018
Effective process analytics; Four reasons why LTE networks are not IIoT ready

Annual Salary Survey

After two years of economic concerns, manufacturing leaders once again have homed in on the single biggest issue facing their operations:

It's the workers—or more specifically, the lack of workers.

The 2017 Plant Engineering Salary Survey looks at not just what plant managers make, but what they think. As they look across their plants today, plant managers say they don’t have the operational depth to take on the new technologies and new challenges of global manufacturing.

Read more: 2017 Salary Survey

The Maintenance and Reliability Coach's blog
Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
One Voice for Manufacturing
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Maintenance and Reliability Professionals Blog
The Society for Maintenance and Reliability Professionals an organization devoted...
Machine Safety
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
Research Analyst Blog
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Marshall on Maintenance
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
Lachance on CMMS
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
Material Handling
This digital report explains how everything from conveyors and robots to automatic picking systems and digital orders have evolved to keep pace with the speed of change in the supply chain.
Electrical Safety Update
This digital report explains how plant engineers need to take greater care when it comes to electrical safety incidents on the plant floor.
IIoT: Machines, Equipment, & Asset Management
Articles in this digital report highlight technologies that enable Industrial Internet of Things, IIoT-related products and strategies.
Randy Steele
Maintenance Manager; California Oils Corp.
Matthew J. Woo, PE, RCDD, LEED AP BD+C
Associate, Electrical Engineering; Wood Harbinger
Randy Oliver
Control Systems Engineer; Robert Bosch Corp.
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Design of Safe and Reliable Hydraulic Systems for Subsea Applications
This eGuide explains how the operation of hydraulic systems for subsea applications requires the user to consider additional aspects because of the unique conditions that apply to the setting
click me