Four common commissioning mistakes to avoid

A few simple steps can prevent countless expensive headaches.

10/02/2012


Commissioning is usually that undefined time between construction and plant start up. If commissioning doesn’t go smoothly, you can count on startup not going smoothly. I have commissioned dozens of plants over the past 27 years and have seen firsthand the difference between a good plan and a bad one. If you avoid these following mistakes I've witnessed over and over again, your efforts will be more trouble free with fewer self-induced headaches.

Mistake  1: Why do I need a plan? Let’s just go out there and start checking stuff out as soon as construction lands the wires. As crazy as this sounds, I’ve seen it many times. When you start energizing equipment while construction is still terminating wires, it will really slow things down. If you have to start before construction is complete, you will need a carefully thought out plan and daily meetings involving operations, safety, construction, and commissioning. Some equipment will require vendors on site and their schedules aren’t as flexible as you might need so plan wisely.

Mistake 2: Why do we need all these expensive people? We can avoid all those high wages, travel, and living expenses if we just use some of the construction crew and some of our own maintenance techs. This might sound good initially, because the construction guys know where everything is located and, besides that, they wired it up. I’m not trying to knock construction, but if they were knowledgeable and familiar with your collection of instrumentation, they would be technicians and not construction workers. As far as the plant maintenance crew, it’s okay to use them if they are guaranteed to be dedicated to the commissioning effort and without having to constantly run off to handle existing plant problems. It’s going to look like it costs more on paper, but in the long run you’ll recoup those charges with your great commissioning job.

Mistake 3: Just plug it in. The skid vendor said it would work right out of the box. Maybe the skid vendor promised plug-and-play, but some of these things don’t perform as easily as you may hope. As a matter of fact, you will be wiser to expect problems, because when east meets west, voltage levels, contact configuration, logic, signal types, and many other small details will have to be worked out. Many times you won’t be able to run the equipment until start up, and you don’t want to have to do that with a crowd of onlookers while you straighten out a few “minor details”. If the equipment is complicated, you might even consider source inspection at the vendor site before they ship.

Mistake 4: We’ll deal with documentation when we get caught up with things. Everything’s on the Internet anyway. Gather tech manuals, drawings, specs, and other documents before you start commissioning, because you won’t be able to find everything at the vendors’ websites. It will take longer than you think for redlines and as-built drawings to get back in the customer’s hands. They will need a set for operating, and you’ll need a set for your CAD department. Those tiny changes you made will add up to a big job. Keep your master set in one place, make updates daily, and don’t make any exceptions.

These common mistakes may sound just like common sense, and they probably are, but I’m amazed to see them happen again and again.

This post was written by Steve Cochran. Steve is a senior technician MAVERICK Technologies, a leading system integrator providing industrial automation, operational support and control systems engineering services in the manufacturing and process industries. MAVERICK delivers expertise and consulting in a wide variety of areas including industrial automation controls, distributed control systems, manufacturing execution systems, operational strategy, and business process optimization. The company provides a full range of automation and controls services – ranging from PID controller tuning and HMI programming to serving as a main automation contractor. Additionally MAVERICK offers industrial and technical staffing services, placing on-site automation, instrumentation and controls engineers.



The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
Pipe fabrication and IIoT; 2017 Product of the Year finalists
The future of electrical safety; Four keys to RPM success; Picking the right weld fume option
A new approach to the Skills Gap; Community colleges may hold the key for manufacturing; 2017 Engineering Leaders Under 40
Control room technology innovation; Practical approaches to corrosion protection; Pipeline regulator revises quality programs
The cloud, mobility, and remote operations; SCADA and contextual mobility; Custom UPS empowering a secure pipeline
Infrastructure for natural gas expansion; Artificial lift methods; Disruptive technology and fugitive gas emissions
Power system design for high-performance buildings; mitigating arc flash hazards
VFDs improving motion control applications; Powering automation and IIoT wirelessly; Connecting the dots
Natural gas engines; New applications for fuel cells; Large engines become more efficient; Extending boiler life

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
The maintenance journey has been a long, slow trek for most manufacturers and has gone from preventive maintenance to predictive maintenance.
This digital report explains how plant engineers and subject matter experts (SME) need support for time series data and its many challenges.
This digital report will explore several aspects of how IIoT will transform manufacturing in the coming years.
Maintenance Manager; California Oils Corp.
Associate, Electrical Engineering; Wood Harbinger
Control Systems Engineer; Robert Bosch Corp.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me