ISS SourceAn equipment failure will lead to further delays at the Prairie State power plant in Marissa, Ill.

Mechanical delays have caused the start up to push back to the end of this year for the first of two 800 MW coal fired generators, said Coldwater Board of Public Utilities (CBPU) Director Paul Beckhusen, also a member of the American Municipal Power (AMP) board. CBPU partially owns the plant and AMP is supervising construction.

Beckhusen said it is possible the second unit could go online before the first. Now in a regulatory filing, AMP said one of the plant’s large fans suffered damage on March 27, 2012.

“The extent of damage and root cause analysis is under way,” the company reported. Because they don’t know why the fan failed, this latest delay could push the completion of the plant into late 2012. According to the filing this would be about a year later than original completion date of last December.

Because it remains uncertain why the fan failed, the second unit also shut down until officials complete the analysis. The fan is a key element for reducing air emissions which will make this coal plant one of the least polluting in operation.

The main contractor, Bechtel Corp., will need 10 to 12 weeks to obtain the critical parts for the repair. It will also require up to 30 weeks for other unique parts AMP stated in the filing. Repair time would add another six weeks, the report stated.

Estimates show the project is several billion dollars over budget but in AMP’s agreement with Bechtel, the contractor owes damages for each week the plant is late. There is also a cap on budget overruns that AMP must pay.

Coldwater has contracted for 9.8 MW of power from Prairie State which it expects online next summer. It does not need the capacity until the summer of 2015 when long-term power purchase contracts end. By then, its peak demand should increase to 59.4 MW of power.

The only other member of the Michigan South Central Power Agency (MSCPA) to purchase an interest in Prairie States is Marshall which agreed to take 1.99 MW.

While there are Midwest power companies who own interest in the plant, AMP purchased 23% for its members when it took over construction and operations. A number of Illinois municipalities and rural eclectic co-ops also are showing interest in the power.

Funds to pay off the bonds used for construction and operational costs will come from electric rates of those who own an interest or buy the output.



Top Plant
The Top Plant program honors outstanding manufacturing facilities in North America.
Product of the Year
The Product of the Year program recognizes products newly released in the manufacturing industries.
System Integrator of the Year
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
September 2018
2018 Engineering Leaders under 40, Women in Engineering, Six ways to reduce waste in manufacturing, and Four robot implementation challenges.
July/Aug
GAMS preview, 2018 Mid-Year Report, EAM and Safety
June 2018
2018 Lubrication Guide, Motor and maintenance management, Control system migration
August 2018
SCADA standardization, capital expenditures, data-driven drilling and execution
June 2018
Machine learning, produced water benefits, programming cavity pumps
April 2018
ROVs, rigs, and the real time; wellsite valve manifolds; AI on a chip; analytics use for pipelines
Spring 2018
Burners for heat-treating furnaces, CHP, dryers, gas humidification, and more
August 2018
Choosing an automation controller, Lean manufacturing
September 2018
Effective process analytics; Four reasons why LTE networks are not IIoT ready

Annual Salary Survey

After two years of economic concerns, manufacturing leaders once again have homed in on the single biggest issue facing their operations:

It's the workers—or more specifically, the lack of workers.

The 2017 Plant Engineering Salary Survey looks at not just what plant managers make, but what they think. As they look across their plants today, plant managers say they don’t have the operational depth to take on the new technologies and new challenges of global manufacturing.

Read more: 2017 Salary Survey

The Maintenance and Reliability Coach's blog
Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
One Voice for Manufacturing
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Maintenance and Reliability Professionals Blog
The Society for Maintenance and Reliability Professionals an organization devoted...
Machine Safety
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
Research Analyst Blog
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Marshall on Maintenance
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
Lachance on CMMS
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
Material Handling
This digital report explains how everything from conveyors and robots to automatic picking systems and digital orders have evolved to keep pace with the speed of change in the supply chain.
Electrical Safety Update
This digital report explains how plant engineers need to take greater care when it comes to electrical safety incidents on the plant floor.
IIoT: Machines, Equipment, & Asset Management
Articles in this digital report highlight technologies that enable Industrial Internet of Things, IIoT-related products and strategies.
Randy Steele
Maintenance Manager; California Oils Corp.
Matthew J. Woo, PE, RCDD, LEED AP BD+C
Associate, Electrical Engineering; Wood Harbinger
Randy Oliver
Control Systems Engineer; Robert Bosch Corp.
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Design of Safe and Reliable Hydraulic Systems for Subsea Applications
This eGuide explains how the operation of hydraulic systems for subsea applications requires the user to consider additional aspects because of the unique conditions that apply to the setting
click me