Build a maintenance schedule in six steps

Manufacturers should build a weekly maintenance schedule that addresses potential conflicts and address overdue preventive maintenance (PM) tasks.

04/05/2017


Image courtesy: CFE MediaStruggling to put together a complete weekly schedule? It may surprise you, but you're not alone. Although the processes of work execution (preventive and predictive programs, planning, scheduling, coordination, storeroom and production partnerships) are foundational, many groups struggle to put it all together well. Without this foundation, more advanced concepts fizzle out quickly. Frustration ensues.

There are many pieces that need to be aligned to complete the entire work execution puzzle. To start, let's focus on developing the weekly maintenance schedule. There are six basic steps that you should address to move things forward.

1. Quantify the maintenance backlog

The backlog represents a comprehensive list of all work yet to be completed. It may include overdue preventive maintenance (PM) tasks, corrective actions, safety items and so on. Overdue PM tasks in the backlog highlight problems in your work processes. Determine if the work is complete. If the tasks and frequencies are valid and not done, then we can expect failures as well as a reactive state with equipment availability.

Backlogged work orders should not have birthdays of the annual sort. If it's been on the list for a year, most likely it is not important. Remove unnecessary work orders from the backlog. Now, place labor estimates on the work in the backlog. You need these hours to determine the how many crew weeks of backlog exist. The backlog metric should be trended at least monthly based on the hours, not the number of work orders.

2. Determine your ability to accomplish maintenance work

At the end of the day, the goal is to schedule more work. To do this you need to understand the available crew size for each week. Personally, I prefer the maintenance supervisor to work with the maintenance planner scheduler to provide those estimated available hours at least two weeks out.

Things may change—people take a vacation, get sick, have family emergencies—but you need a starting place. Maybe you're too reactive and don't believe you have the resources to schedule 100% of the available hours. So start with 60%. Just start.

3. Find windows for maintenance work

The planner scheduler role knows the maintenance backlog. As such, those individuals should be looking for and negotiating for maintenance work windows. This effort requires working with production or operations and planning in partnership. Some organizations have a production gatekeeper to help move things along. There are lots of windows for work that are often overlooked.

4. Build the draft maintenance schedule

Now we should understand the PMs that are triggering each week at least two weeks in advance. Future work has received some level of maintenance planning. We've identified the maintenance backlog. We know our estimated hours available for work. We understand the production windows. Time to build the schedule for next week.

Assuming a Sunday to Saturday schedule, this should be completed by Tuesday of the week prior. Ultimately, we want to get at least two weeks ahead, but start somewhere. Knowing available equipment windows, we can place that work on those days or windows. Once built, email the draft to the stakeholders, including production managers and supervisors. Ask for people to come with changes before the weekly scheduling meeting so those changes can be integrated early.

5. The weekly maintenance scheduling meeting

This meeting should be on late Thursday or early Friday so that the meeting time is close to the start of the schedule period. Fewer changes occur that way. Keep in mind it's not a planning meeting but a scheduling meeting to confirm next week's work as a minimum, along with any special coordination activities.

The planning part should have happened long before this meeting to ensure parts and time to plan. There are two main components for this meeting: next week's schedule and a review of the previous week's metrics. Part of the metrics review must include schedule breakers that prevented you from accomplishing the schedule. Keep it short and sweet.

6. What gets measured, gets done

While the metrics discussion is a longer subject in itself, make sure you have a progression plan using measures for continuous improvement.

Jeff Shiver, CMRP, is a founder of People and Processes, a consulting and training group.



Top Plant
The Top Plant program honors outstanding manufacturing facilities in North America.
Product of the Year
The Product of the Year program recognizes products newly released in the manufacturing industries.
System Integrator of the Year
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
November 2018
2018 Product of the Year finalists, mild steel welding: finding the right filler, and new technique joins aluminum to steel.
October 2018
Tools vs. sensors, functional safety, compressor rental, an operational network of maintenance and safety
September 2018
2018 Engineering Leaders under 40, Women in Engineering, Six ways to reduce waste in manufacturing, and Four robot implementation challenges.
October 2018
2018 Product of the Year; Subsurface data methodologies; Digital twins; Well lifecycle data
August 2018
SCADA standardization, capital expenditures, data-driven drilling and execution
June 2018
Machine learning, produced water benefits, programming cavity pumps
Summer 2018
Microgrids and universities, Steam traps and energy efficiency, Finding help with energy projects
October 2018
Complex upgrades for system integrators; Process control safety and compliance
November 2018
Analytics quantify processes, Fieldbus networking and IIoT, Choosing the right accelerometer

Annual Salary Survey

After two years of economic concerns, manufacturing leaders once again have homed in on the single biggest issue facing their operations:

It's the workers—or more specifically, the lack of workers.

The 2017 Plant Engineering Salary Survey looks at not just what plant managers make, but what they think. As they look across their plants today, plant managers say they don’t have the operational depth to take on the new technologies and new challenges of global manufacturing.

Read more: 2017 Salary Survey

The Maintenance and Reliability Coach's blog
Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
One Voice for Manufacturing
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Maintenance and Reliability Professionals Blog
The Society for Maintenance and Reliability Professionals an organization devoted...
Machine Safety
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
Research Analyst Blog
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Marshall on Maintenance
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
Lachance on CMMS
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
Material Handling
This digital report explains how everything from conveyors and robots to automatic picking systems and digital orders have evolved to keep pace with the speed of change in the supply chain.
Electrical Safety Update
This digital report explains how plant engineers need to take greater care when it comes to electrical safety incidents on the plant floor.
IIoT: Machines, Equipment, & Asset Management
Articles in this digital report highlight technologies that enable Industrial Internet of Things, IIoT-related products and strategies.
Randy Steele
Maintenance Manager; California Oils Corp.
Matthew J. Woo, PE, RCDD, LEED AP BD+C
Associate, Electrical Engineering; Wood Harbinger
Randy Oliver
Control Systems Engineer; Robert Bosch Corp.
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Design of Safe and Reliable Hydraulic Systems for Subsea Applications
This eGuide explains how the operation of hydraulic systems for subsea applications requires the user to consider additional aspects because of the unique conditions that apply to the setting
click me