Green field oil seed processing facility

Integrated project delivery profile

02/18/2013


Project Team

Electrical Engineering, Instrumentation Engineering, Electrical Construction and Installation: Interstates Companies, Sioux Center, Iowa

Process Design and Mechanical Engineering: Karges-Faulconbridge Inc., St. Paul, Minn.

Construction Management: McGough, St. Paul, Minn.


Integrated project delivery (IPD) and collaboration brought a team of companies together to design and build a green field oil seed processing facility located in the upper Midwest. The facility, with capacity to process 1,000 tons of seed per day, produces food-grade oil. Along with the processing, the facility has capacity to store 830,000 bushels of grain. The site covers 390 acres including the grains receiving, preparation, extraction, refinery, and utilities areas.

To leverage market demand for its finished product, the owner had to commit to local growers that the facility would receive grain at the next harvest. The approaching winter season created additional pressure to begin construction of the foundation and underground electrical system. These factors required that the teams collaborate early to make design decisions and proceed with construction without a fully finished design.

Reflecting on what the team did to ensure the IPD method was successful for this project, Jim Faulconbridge, PE, president of Karges-Faulconbridge Inc., said, “The team stayed focused on the critical path schedule, making sure that the decisions were made in the right order. Also, the willingness to develop design ‘workarounds’ in the absence of complete information was key.”

For a team to successfully execute IPD methods, they must work toward key areas of early budgeting, scheduling, and a strong start-up. Early dependable pricing gives the client, and those financing it, the confidence to continue with a project. Early collaboration lends itself to significant schedule advantages. When team members are collaborating and providing just-in-time design, clients are able to respond to market conditions. In this case, the client and team were focused on completing the grains receiving area by the next harvest.

“To say that every single aspect of the project was smooth sailing due to integrated project delivery would be a stretch,” said Doug Post, PE, president of Interstates Engineering. “However, early agreement to proceed with construction when design was not 100% complete enabled the project to move forward according to the owner’s priorities.”

Start-up is the moment of truth for a project. When the team has worked well together in design and delivery of the project, the owner can feel confident as start-up approaches. “A strong start-up is important,” said Post. “It’s the most recent impression on the owner’s mind when all is said and done.”  

Ultimately, success circles back to the budget. The end result of IPD should be that the project finishes within budget and meets the owner’s business needs.

IPD methods allow team members to work together with the owner to provide value that includes not only the initial construction cost of a facility, but also the long-term cost of ownership. “If the design is calling for 16 valves that need regular maintenance to be situated in locations that can’t be accessed safely and easily, the owner will be reminded of this design decision forever,” said Post. “With early design collaboration, team members have input from many perspectives and can suggest value opportunities. While it may require more piping for the initial installation, the value of future ease of maintenance gained by repositioning those 16 valves to be grounded close to the floor clearly outweighs the added expense.”

 “Early specialty contractor involvement is only as good as the early detailed breakdown of costs and schedule they provide,” said Faulconbridge. “In this case, the team was better able to understand the impacts of proposed P&ID changes as design developed, and manage budget and schedule accordingly. This had the effect of protecting contingencies.”

IPD must capture the value of collaboration. The system must reward collaboration, and the designers must be incented to seek outside perspective on the constructability of the design. To successfully execute IPD, specialty contractors must be encouraged to suggest design alternatives. This project is an example of how early collaboration facilitates better decision making and value for the owner.



The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
Pipe fabrication and IIoT; 2017 Product of the Year finalists
The future of electrical safety; Four keys to RPM success; Picking the right weld fume option
A new approach to the Skills Gap; Community colleges may hold the key for manufacturing; 2017 Engineering Leaders Under 40
Control room technology innovation; Practical approaches to corrosion protection; Pipeline regulator revises quality programs
The cloud, mobility, and remote operations; SCADA and contextual mobility; Custom UPS empowering a secure pipeline
Infrastructure for natural gas expansion; Artificial lift methods; Disruptive technology and fugitive gas emissions
Power system design for high-performance buildings; mitigating arc flash hazards
VFDs improving motion control applications; Powering automation and IIoT wirelessly; Connecting the dots
Natural gas engines; New applications for fuel cells; Large engines become more efficient; Extending boiler life

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
The maintenance journey has been a long, slow trek for most manufacturers and has gone from preventive maintenance to predictive maintenance.
This digital report explains how plant engineers and subject matter experts (SME) need support for time series data and its many challenges.
This digital report will explore several aspects of how IIoT will transform manufacturing in the coming years.
Maintenance Manager; California Oils Corp.
Associate, Electrical Engineering; Wood Harbinger
Control Systems Engineer; Robert Bosch Corp.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me