Overall lead times beginning to ease
Lead times for three of the five products that we follow declined between the third and fourth quarters of 1998. Average lead times rose for pumps and special fasteners, but fell for gears, valves, and cylinders.
Lead times for three of the five products that we follow declined between the third and fourth quarters of 1998. Average lead times rose for pumps and special fasteners, but fell for gears, valves, and cylinders. Nevertheless, average 1998 lead times were much higher than in 1997, and shrinking manufacturing payrolls make it unlikely that average lead times will fall much if at all in 1999. LEAD TIMES
Weeks Change, %
November 1998 1997 1998 1999
Gears 5.1 -1.9 6.3 1.3
Pumps 5.1 -5.4 9.7 6.6
Special fasteners 7.2 -3.4 9.2 1.3
Valves 3.2 -6.9 8.1 2.8
Hydraulic cylinders 4.5 24.8 10.4 5.2
Source: Purchasing magazine and Cahners Economics
Do you have experience and expertise with the topics mentioned in this content? You should consider contributing to our WTWH Media editorial team and getting the recognition you and your company deserve. Click here to start this process.