Wisconsin Institutes for Discovery

Integrated project delivery profile

02/19/2013


Project Team

Owners: Wisconsin Alumni Research Foundation, University of Wisconsin

Architects: Ballinger, Uihlein/Wilson Architects

Construction Manager: A joint venture between J.H. Findorff & Son Inc. and M.A. Mortenson Company

Mechanical/Electrical: AEI/Affiliated Engineers Inc.

Piping: PSJ Engineering

Structural/Site/Civil: GRAEF

Telecommunications: Intelligent Network Solutions

Landscape: Olin Partnership, GRAEF


The Wisconsin Institutes for Discovery (“Discovery”), on the University of Wisconsin campus in Madison, has two owners and houses two major transdisciplinary research organizations. With a concentrated schedule, aggressive goals for sustainability, a paradigm-changing collaborative research model, and an urgent mission to accelerate new knowledge improving human health, the project compelled consideration of alternative modes of project delivery.

Recently honored as R&D Magazine’s 2012 Lab of the Year, Discovery fosters and supports fluid interdisciplinary teaming with social ergonomics strategies and laboratory flexibility. Research now being conducted at Discovery includes systems biology, epigenetics, BIONATES, regenerative medicine, virology, pharmaceutical informatics, and health care systems, environments, and treatment technologies optimization. Discovery systems performance targets a 50% reduction in CO2 emissions and a 50% reduction in water use in building operation, as compared to recently constructed research laboratory buildings elsewhere on the campus.

The lab spaces of the 300,000-sq-ft Discovery building are organized in a nonlinear concentric pod configuration, creating thermal buffers and optimizing daylighting. Highly reconfigurable plug-and-play utilities accommodate lab modification and support the sustainability-related objective of a 100-year building. Technologies and strategies to reduce energy consumption include exhaust heat recovery, chilled beam, LED task lighting, daylight harvesting, geosource heat exchange, hybrid natural ventilation, and solar generation of domestic hot water. An integrated system of building controls and automation monitors and records the energy- and water-efficiency of the facility, tracking the use of water and of energy for lighting, heating, cooling, ventilation, equipment, and plug load at the building and individual lab levels.

The owner briefly considered a fast-track approach given the project’s accelerated schedule but realized that fast-tracking alone wouldn’t require the extent of team collaboration needed to successfully execute the functionally intricate, large-scale, sustainability-focused design. With its basis of shared risk and reward, integrated project delivery (IPD) was seen as the best way to establish a collaborative culture among owners, designers, and builders for the duration of the project, and as most effectively translating the expenditure of resources into owner value.

In a conventional project delivery, the designer and builder contract individually with the owner, effectively creating jurisdictional boundaries. The Discovery project team developed its integrated project agreement (IPA) in negotiations including owners (a single owners’ representative/project manager), designers, and builders. The parties established and agreed to honor operational protocols optimizing coordination, transparency, and accountability. The team adopted a target value approach, agreeing to design to a set budget rather than pricing a developing design at a series of project milestones and eliminating elements exceeding the owner’s budget. This would require ongoing cost estimating, beginning with establishing the target value, thus including the CM/GC and subcontractors in very early design participation. A project contingency fund was established to cover unanticipated developments impacting project scope. This safety net provided change management and covered mistakes, failures of coordination, and workmanship issues.

The CM/GC joined six trades to their contract, replacing their hard bid contingencies with incentives distributed at three points in the project, with potential distribution down to the craft level. As the project timeline illustrates, the IPA wasn’t completed until well into design and at the outset of site preparation. It should be noted that many of the Discovery team members had worked together on previous projects; most had extensive experience with complex collaborative undertakings; they benefited from an experienced, highly effective, and significantly autonomous project manager; and they shared a sincere commitment to the project’s mission. Consequently, the protracted development of the IPA was simply another collaborative exercise, benefitting from an evolving culture of protocols, terminology, trust, and understanding.

The project’s broadly integrated concept development phase convened meetings of “cluster teams” that consisted of owner, designers, and construction representatives, addressing six critical components of the project: site, structure, enclosure, interior construction, lab casework, and MEP/IT. BIM was established as the central design and building tool (the CM/GC was given “right of reliance” on the BIM design models), enhancing collaboration, integrating the project team, and controlling waste by helping the team identify and resolve problems and conflicts early. The team established a “big room” design workshop strategy space in a building adjacent to the project site, to facilitate continuity in information flow.

The Discovery building was conservatively estimated to have been completed a year sooner than would have been possible using a conventional design-bid-build approach. Savings realized from unused “safety net” contingency, the removal of subcontractors’ hard bid contingency, and through the precision of target value design were reinvested in the project to additionally provide within the original target value: all lab fit-out in the facility; expansion in size and capacity of the server farm; the earth heat exchange system, solar generation of domestic hot water, LED task lighting, and systems integration; a TelePresence room; and the RFID system for research project asset management.

While the Discovery project stands as a landmark achievement for all the members of the project team, some lessons were learned. The MEP cluster would have benefited from supplemental subgroups. The prominence of the building’s complex engineered MEP systems (50% of overall project value) resulted in an unwieldy number of participants included in the MEP cluster (30); an ideal cluster team size is eight individuals. Supplementing the respective disciplines with subgroups would have focused and simplified management of these areas throughout the course of the project.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.