Waterhammer: How much do you know?

As soon as steam leaves the boiler, condensate takes place in the pipe due to heat loss. This situation is even more intense during the initial supply of steam and when the steam is cold.

10/30/2013


Figure 1: Tiny droplets of condensate can build up with increasing length of the pipe and eventually, it becomes a mass of liquid (solid slug) carried along at high speed. Courtesy: Spirax SarcoAs soon as steam leaves the boiler, condensate takes place in the pipe due to heat loss. This situation is even more intense during the initial supply of steam and when the steam is cold.

Figure 1 demonstrates how tiny droplets of condensate can build up with increasing length of the pipe and eventually, it becomes a mass of liquid (solid slug) carried along at high speed.

When the slug encounters any obstacle such as a change in the pipe direction, it will stop immediately. The kinetic energy of the high speed condensate is suddenly converted into pressure energy which has to be absorbed by the pipework. If the speed is very high or there is a lot of weight, the amount of energy output may be strong enough to crack pipes and rupture the fittings. Even if there is not much speed and weight, the noise created in the system by the impact can be a severe nuisance.

Figure 2: Common sources of trouble are sags in the pipework and incorrect use of concentric reducers. Courtesy: Spirax SarcoThe incidence of waterhammer will be encouraged if pockets of condensate are allowed to build up in low points of the steam system. Common sources of trouble are sags in the pipework and incorrect use of concentric reducers as shown in Figure 2. If the eccentric reducer is installed correctly as shown in Figure 3, collection of condensate will not be allowed. Even a strainer fitted as in Figure 4 is a potential cause of waterhammer. It is better to fit strainers on their sides in steam lines and will prevent the formation of condensate which can be picked up by fast moving steam.

To reduce the possibility of waterhammer, steam lines should be arranged with a gradual fall in the direction of flow and drain points installed at regular intervals and at all low points. Check valves should be fitted after any traps which would otherwise allow condensate to run back into the steam line or equipment during shut down.

Figure 3: If the eccentric reducer is installed correctly, collection of condensate will not be allowed. Courtesy: Spirax SarcoWaterhammer can occur in submerged steam heating coils commonly found in tanks and vats. Although the coils do not have the long uninterrupted lengths of steam mains or space heating pipes, incoming steam still can be condensed very quickly. This results in a large weight of water being carried forward by steam which has a fairly high speed due to the heavy condensate rate. If condensate is lifted to the trap, it is important that the coil falls continuously along its length and is fitted with a loop seal and small bore riser.

Difficulties arise when there is insufficient pressure available at the trap inlet if condensate has to be lifted after the steam trap. The equipment will then waterlog and waterhammer may happen when the steam pressure builds up again. This is especially the case with equipment fitted with automatic temperature controls. The best arrangement in such cases is to drain the condensate by gravity to a vented receiver and use a pump to lift to a higher level.

Figure 4: Even a strainer fitted it is a potential cause of waterhammer. Courtesy: Spirax SarcoIt is recommended to fit steam traps which have a strong resistance such as the thermodynamic or bucket types wherever there is a risk of waterhammer.

Content provided by Spirax Sarco, originally published in Steam News Magazine.



STEVE , MO, UNITED STATES, 11/20/13 03:37 PM:

"..This situation is even more intense during the initial supply of steam and when the steam is cold." If the steam were cold, then it wouldn't be steam. I believe they mean when the piping system is cold...
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.