Using integrated design to achieve net-zero

Integrated design practices allow a middle school to achieve net-zero energy.

03/27/2014


Learning Objectives

  1. Know which metrics to use to establish baseline energy numbers for a building.
  2. Understand the four things needed to design a net-zero energy building (NZEB).
  3. Gain insight into the interdependency on multiple building systems in an integrated design.

Figure 1: This interior shot of the Hood River Middle School science classroom shows an abundance of natural daylight coming through clerestory and operable windows, which automatically dims electric lights. The radiantly heated and chilled slab providing thermal conditioning to the space is another example of an integrated design element. Courtesy: Interface EngineeringThe Hood River Middle School Music and Science Building (HRMS) building was designed by Opsis Architecture, Portland, Ore., with mechanical, electrical, plumbing (MEP), and energy consulting provided by Interface Engineering.


With the emergence of nationally established building performance targets and rising concerns over climate change, the push to design and construct net-zero energy buildings (NZEB) is stronger than ever. To achieve this ambitious goal, teams must eschew traditional design practices and use an integrated design process that seamlessly combines architectural elements, site features, and engineered systems as a cohesively operating whole.

This article aims to summarize some of the key components of the integrated design process and highlight the Hood River Middle School (HRMS) Music and Science Building that was designed using this concept. The building opened in the fall of 2010 and was constructed by Hood River (Ore.) County School District using funding from the May 2008 construction bond. The building houses a music classroom, music practice rooms, a new science lab with an attached greenhouse, and associated offices and support space. The building has been operational now for 3 years and has achieved net-zero energy.  

At the start of any project and particularly a net-zero energy project, it is critical to determine baseline energy numbers to establish a benchmark for simulation and design purposes. The most widely referenced database of energy metrics is the Commercial Buildings Energy Consumption Survey (CBECS), which is maintained by the Dept. of Energy. It is a national sample survey that collects energy usage and building characteristics on the stock of commercial buildings in the United States.

Energy consumption is available normalized as an energy use index (EUI) in units of kBtu/sq ft/year, which can be broken down into different end uses (heating, cooling, lighting, etc.). The Target Finder tool provided through the Energy Star website is a great tool for determining a building’s baseline energy rating. For the HRMS building, a baseline EUI of 52 kBtu/sq ft/year was determined with the major energy end uses being heating and lighting.

NZEB needs four things

There are four steps in the integrated design concept that are essential in yielding a NZEB: harnessing natural resources at the site, conservation through building elements, use of renewable energy resources, and measurement and verification (M&V) of intent.

Using site-available natural resources is essential and one of the most cost-effective strategies for achieving net-zero energy. Thus, it should be considered first in the design process. The HRMS project integrates multiple natural resources into the building and systems by using the earth, water, wind, and the sun in various forms to achieve its performance.

Figure 2: The exterior courtyard of the Hood River Middle School building highlights the interactive and educational aspect of the building with a fully functioning greenhouse and photovoltaic panels in clear view to the students and visitors. Courtesy: Opsis ArchitectureWind drives a natural ventilation system that combines low and high clearstory windows and rooftop ventilators to allow cross and stack ventilation. A red light/green light indicator informs building occupants when outside temperatures are favorable for natural ventilation, which engages students in the management of the building’s energy use. 

The earth provides one of the most efficient heat sources for the building’s main HVAC system, a geo-exchange system of tubing that is horizontally looped 10 ft under the school’s adjacent soccer field. The tubing is connected to two internal water-to-water heat pumps that feed radiantly heated and cooled slabs in the building.

An additional energy source for summer cooling comes from a portion of an adjacent stream. The district uses the stream’s snow melt runoff for irrigation during the region’s dry summers, which happens to coincide with the need for cooling during the summer months. Thus, the irrigation water is simply diverted through a heat exchanger when there is cooling demand. This cool water can be circulated through the building’s radiant floor slabs to provide cooling without using a refrigeration process.

Due to the proximity to the Columbia River Gorge, renowned for its windsurfing, it was assumed early on that wind-powered turbines could be an effective renewable energy source. However, an analysis of the micro climate of the site proved wind energy was not as cost-effective as solar. The sun provides renewable energy to the building in several different forms, which will be discussed below.

Energy efficiency

Figure 3: A cross-sectional schematic through the building highlights the multitude of natural resources and integrated design elements that are featured in the Hood River Middle School building. Courtesy: Opsis Architecture After analyzing the available site natural resources, the next step is to focus on conservation energy measures within and around the building. This step is where an integrated design process can provide the means to achieve net-zero energy and stay within budget. Combining architectural and engineered elements is the most cost-effective way to produce deep energy savings. Energy conservation measures can be broken into two separate categories: passive and active systems.

Arguably the most important passive system for any NZEB is the envelope. Careful attention was paid to this on HRMS, with R-38 rigid insulation (with lapped layers to avoid gaps) on the roof and R-15 insulation under the radiant slab on grade. The insulated concrete formwork (ICF) walls achieve an overall R-value of 25 and provide excellent thermal mass buffering against Hood River’s seasonal temperature swings. This type of wall uses polystyrene foam interlocking blocks to construct the form work for the walls. Concrete is then poured in stages into the formwork with rebar used for added structural stability. The forms are then left in place and provide the building’s thermal protection layer. Due to their monolithic nature, ICFs can drastically reduce air infiltration and thermal bridging with proper detailing. Last, triple glazing helps reduce heat gain and loss at the windows. The triple-glazed windows are set in wooden frames, which provide a higher level of thermal resistance than more common aluminum frames.

Daylighting is highly recommended for any net-zero energy project to reduce one of the highest energy end uses and is an example of a pseudo-passive strategy. While it takes an integrated control system to dim the electric lights in a space, the sun provides lighting passively through the windows or skylights. To achieve the optimum level of daylight in the HRMS classrooms, the project team performed multiple detailed daylighting studies, balancing the results with those of the energy model. The resulting design combines translucent skylights, clerestory windows, and traditional windows with deciduous vines for seasonal shading allowing views in multiple directions from most building locations. Light-colored acoustic panels help reflect natural light from the clearstory windows deep into the classroom space.


<< First < Previous 1 2 Next > Last >>

No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.