Using 3-D modeling keeps boiler project moving

When a Midwestern college took a look at its need for a system of four new boilers in a 100-year-old facility, it was more than an issue of just getting more efficient steam production through the system. "They needed to upgrade their boiler systems to meet EPA regulations, and the boiler replacement project was expected to meet their steam production needs for the next 20 years," said Tony Smi...

12/01/2005


When a Midwestern college took a look at its need for a system of four new boilers in a 100-year-old facility, it was more than an issue of just getting more efficient steam production through the system.

"They needed to upgrade their boiler systems to meet EPA regulations, and the boiler replacement project was expected to meet their steam production needs for the next 20 years," said Tony Smith, a senior mechanical engineer for Monsanto Enviro-Chem Systems, Inc., of St. Louis, which coordinated the design project for the new system. "We also had to maintain the architectural features of the brick powerhouse building. This was a historic building."

There was one other crucial consideration. "The utilities couldn't be turned off and couldn't be disturbed, for any length of time," said Mike Reim, piping designer with Monsanto Enviro-Chem. "There was university research that had been in place for 15 to 20 years. If we lost the utilities, that would all be for naught."

Little wonder Smith said, "Due to the large scale of this project, the mass of existing piping and equipment, and the need to keep the facility operating undisturbed, it was a very complicated project both in terms of engineering and construction planning."

One asset for the MECS, Inc., staff was the ability to work with 3-D models of the boiler system, giving them a clear view of how the existing pipe system would work with the new system. "3-D modeling is an enormously useful tool," said Smith. "When we had the new boiler and the new piping models completed, we were able to design to within 1/16th of an inch."

"We'd go to the field, take measurements, model those measurements, and put the new piping in. We didn't have to rely on what our gut feelings were on the clearances." Reim added.

The system also allowed designers to see the plant model in a CAD format so the entire design staff could see the existing boiler system piping. A laptop computer and design software allowed the field workers to input data on site and have that updated information available to everyone working on the project. Workers from the design team to the construction team saw real-time measurements and were able to make critical design decisions faster and more effectively.

The Monsanto team made the design data available to the project team. "We started with three engineers, and as the project progressed at any given time, we'd have from four to 12 people looking at the 3-D model," Jim Cope, CAD system administrator said. "Now we have it deployed across the building on 50 to 75 desktops."

The system also allowed for stress analysis to be done by computer, rather than by trial and error. "Once you cut into piping, the existing guides and supports act differently," Reim said. "We had to plan very carefully not to overload the system. There was potential for huge damage."

In the end, the 3-D CAD system made a tough project manageable because of its portability, flexibility and modeling capabilities. "When an issue would arise, we were easily able to go into the model and explore different solutions," said Reim.

The industry view

Mapping software is a common tool in new construction, but it's a big asset in retrofitting as well, said Dr. Jeffrey Hollings, senior vice president, Bentley Plant, Walnut Creek, CA. Bentley's AutoPLANT Plant Design solution is one of the tools utilized in the 3-D CAD scanning community. "It's very common, especially where downtime on existing systems needs to be minimized. This is where laser scanning can help.

"Upgrades, retrofits, and revamps are by far the most common capital projects being executed in North America these days. It has been highly publicized that not a single new refinery has been built since 1974," Hollings noted.

Hollings said many factors should be considered when looking at a retrofitting project:

  • Feasibility of mapping - access to information, any restrictions on the mapping process, and the time needed to effectively map the facility

  • The availability of legacy documents, such as scans or existing CAD documents

  • An assessment of a company's existing design base.

    • "Understanding what is currently in place will help the project engineers understand the tasks and tools required to execute the work," Hollings said. But there's also a big bonus at the end of that effort, as the Monsanto example illustrated. "The key advantage is that once mapped, the proposed changes can be planned off site, right down to construction simulation," said Hollings. "This gives a great deal of confidence in the planned revamp process."

      A need to build a new boiler piping system within a century-old college building was a challenge made easier with CAD technology. (Image courtesy of the 2005 BE Awards of Excellence)



The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
Doubling down on digital manufacturing; Data driving predictive maintenance; Electric motors and generators; Rewarding operational improvement
2017 Lubrication Guide; Software tools; Microgrids and energy strategies; Use robots effectively
Prescriptive maintenance; Hannover Messe 2017 recap; Reduce welding errors
The cloud, mobility, and remote operations; SCADA and contextual mobility; Custom UPS empowering a secure pipeline
Infrastructure for natural gas expansion; Artificial lift methods; Disruptive technology and fugitive gas emissions
Mobility as the means to offshore innovation; Preventing another Deepwater Horizon; ROVs as subsea robots; SCADA and the radio spectrum
Research team developing Tesla coil designs; Implementing wireless process sensing
Commissioning electrical systems; Designing emergency and standby generator systems; Paralleling switchgear generator systems
Natural gas engines; New applications for fuel cells; Large engines become more efficient; Extending boiler life

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
The maintenance journey has been a long, slow trek for most manufacturers and has gone from preventive maintenance to predictive maintenance.
Featured articles highlight technologies that enable the Industrial Internet of Things, IIoT-related products and strategies to get data more easily to the user.
This digital report will explore several aspects of how IIoT will transform manufacturing in the coming years.
Maintenance Manager; California Oils Corp.
Associate, Electrical Engineering; Wood Harbinger
Control Systems Engineer; Robert Bosch Corp.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me