University of Texas Tower Air Handling Unit Replacement

System overhaul: University of Texas Tower Air Handling Unit Replacement; EEA Consulting Engineers

08/09/2012


The University of Texas at Austin main building (the U.T. Tower) is shown during installation of the new air-handling unit. Courtesy: Flintco, the general contractor on the project. (Click to enlarge)Project name: University of Texas Tower Air Handling Unit Replacement

Location: Austin, Texas

Firm name: EEA Consulting Engineers

Project type, building type: System overhaul, school (college, university)

Project duration: 1.5 years

Project completion date: April 30, 2007

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $77,000

Engineering challenges

Location and space constraints for the new equipment: The tower was occupied and existing equipment remained in use for duration of the project. There was limited access to the area where existing and new equipment were located. This area is near the top of the tower, behind the walls that support the clock facings.

Time constraint for the switch over to the new system: The two-week Christmas break between the fall and spring semesters provided the only period that the tower was not occupied. The transition from the old air handling unit to the new one was scheduled for that period, which meant that all aspects of the project absolutely had to be completed and become fully operational during the break.

Solutions

Location and space constraints for the new equipment: The solution was to remove a portion of the wall below the north clock facing to allow access. A new equipment platform and stair system was constructed to support and access the new equipment in the tall void space inside the top of the tower. A crane was used to lift the equipment and material into place as well as to remove and replace the 2,700-lb wall stones.

Time constraint for the switch over to the new system: This entailed close coordination between EEA, the owner, the subconsultants, and the contractor. All parties committed early in the project to meet deadlines and to quickly address any issues that might arise. As a result, the switch over proceeded smoothly and the tower reopened as scheduled. Following the switch, final installation was completed.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Strategic outsourcing delivers efficiency; Sleeve bearing clearance; Causes of water hammer; Improve air quality; Maintenance safety; GAMS preview
World-class maintenance: The three keys to success - Deploy people, process and technology; 2016 Lubrication Guide; Why hydraulic systems get hot
Your leaks start here: Take a disciplined approach with your hydraulic system; U.S. presence at Hannover Messe a rousing success
Flexible offshore fire protection; Big Data's impact on operations; Bridging the skills gap; Identifying security risks
The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Applying network redundancy; Overcoming loop tuning challenges; PID control and networks
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Package boilers; Natural gas infrared heating; Thermal treasure; Standby generation; Natural gas supports green efforts

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
This article collection contains several articles on the vital role that compressed air plays in manufacturing plants.
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
This article collection contains several articles on strategic maintenance and understanding all the parts of your plant.
click me