Tips and tricks for commissioning, balancing buildings

Building commissioning is one of the most important (and complex) types of projects an engineer can be tasked with. This overview provides insights for commissioning building systems.

08/28/2013


 

Jerry Bauers, National director of commissioning, Sebesta Blomberg, Kansas City, Mo. Courtesy: Sebesta BlombergMichael P. Feyler, Co-director, building solutions group, RDK Engineers, Andover, Mass. Courtesy: RDK EngineersRobert J. Linder, PE, Senior project manager, Karges-Faulconbridge Inc., St. Paul, Minn. Courtesy: KFI EngineersJames Szel, Senior vice president, Syska Hennessy Group, New York City. Courtesy: Syska Hennessy GroupGeremy Wolff, Commissioning manager, McKinstry, Bellingham, Wash. Courtesy: McKinstryBarney York, Project manager, RMF Engineering, Baltimore. Courtesy: RMF Engineering

Participants


 

CSE: What challenges do building commissioning projects pose that are different from other projects? 

Jerry Bauers: As a provider of commissioning services, the biggest challenge we face is managing the schedule of commissioning project execution. At every phase of a project, our work is entirely dependent upon the logical and timely execution of the work of other members of the design and construction team. And, in many cases, the incentives that these team members have—both financial and emotional—are in conflict with the requirements appropriate to a disciplined and effective commissioning process. The challenge is to engage the project team members in the notion that an effective construction process and schedule adds value to the results of every member of the team.

James Szel: The biggest challenge to commissioning is to create the environment where everyone from the owner to the contractors to the vendors feels like they are a valued part of the commissioning team. Commissioning is only as important as the owner makes it. When the owner (or its representative) is engaged and actively participating in the process, it really makes for a cohesive, productive team. Another challenge is the timing of the involvement by the commissioning agent (CxA). The CxA should be engaged early in the project to be an integral part of the team, for tasks such as peer reviews. 

Geremy Wolff: Managing the relationships between the contractors, the architecture/engineering team, and the owner can be difficult at times. If everyone is on-board with collaborating to find solutions, it’s great, but there are times when it feels like all we hear is “that’s not in my scope.” This seems to be more prevalent on low-bid work versus design-build or projects with performance requirements. But it is a serious challenge for us.

Some project teams expect the commissioning provider to know everything about everything. This just isn’t the case, especially considering commissioning has expanded into disciplines other than mechanical, electrical, plumbing (MEP), and fire protection, such as building envelope. As the commissioning provider, you don’t have any authority. Through our commissioning process we identify issues and communicate them back to the team, but there is typically no contractual obligation for them to do anything about it. The design-bid-build process used today has not significantly changed in more than 100 years; however, commissioning was not introduced until the late 1980s, so we are still “the new kids on the block.” Integrating our process into the well-established design-build process has proven to be challenging. We still find ourselves educating design and construction professionals on what is commissioning (it’s not just “testing at the end”) and when it should be implemented (it’s never too early).

Barney York: Building commissioning projects are unique in the sense that another party is introduced and integrated into the overall design and construction process. This can create challenges because the CxA’s role has a natural tendency to become adversarial due to the additional oversight the commissioning process adds. In addition, the project schedule can become a challenge as the project completion now requires a contractor to demonstrate a building is not only substantially complete, but functionally complete as well. Commissioning tasks required to demonstrate functional completion must be integrated into the project schedule, and the team must work collaboratively to ensure the owner’s target date is met.


<< First < Previous 1 2 3 4 5 6 7 Next > Last >>

Gerry , Ontario, Canada, 08/29/13 06:33 AM:

Excellent comments we could not agree more
J.R. , TN, United States, 09/04/13 04:27 PM:

Good comments from some large users of the commissioning process.
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Prescriptive maintenance; Hannover Messe 2017 recap; Reduce welding errors
Safety standards and electrical test instruments; Product of the Year winners; Easy and safe electrical design
Safer human-robot collaboration; 2017 Maintenance Survey; Digital Training; Converting your lighting system
Mobility as the means to offshore innovation; Preventing another Deepwater Horizon; ROVs as subsea robots; SCADA and the radio spectrum
Future of oil and gas projects; Reservoir models; The importance of SCADA to oil and gas
Big Data and bigger solutions; Tablet technologies; SCADA developments
Automation modernization; Predictive analytics enable open connectivity; System integration success; Automation turns home brewer into brew house
Commissioning electrical systems; Designing emergency and standby generator systems; Paralleling switchgear generator systems
Natural gas for tomorrow's fleets; Colleges and universities moving to CHP; Power and steam and frozen foods

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
Featured articles highlight technologies that enable the Industrial Internet of Things, IIoT-related products and strategies to get data more easily to the user.
Compressed air plays a vital role in most manufacturing plants, and availability of compressed air is crucial to a wide variety of operations.
This digital report will explore several aspects of how IIoT will transform manufacturing in the coming years.
Maintenance Manager; California Oils Corp.
Associate, Electrical Engineering; Wood Harbinger
Control Systems Engineer; Robert Bosch Corp.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me