Tips and tricks for commissioning, balancing buildings

Building commissioning is one of the most important (and complex) types of projects an engineer can be tasked with. This overview provides insights for commissioning building systems.



Jerry Bauers, National director of commissioning, Sebesta Blomberg, Kansas City, Mo. Courtesy: Sebesta BlombergMichael P. Feyler, Co-director, building solutions group, RDK Engineers, Andover, Mass. Courtesy: RDK EngineersRobert J. Linder, PE, Senior project manager, Karges-Faulconbridge Inc., St. Paul, Minn. Courtesy: KFI EngineersJames Szel, Senior vice president, Syska Hennessy Group, New York City. Courtesy: Syska Hennessy GroupGeremy Wolff, Commissioning manager, McKinstry, Bellingham, Wash. Courtesy: McKinstryBarney York, Project manager, RMF Engineering, Baltimore. Courtesy: RMF Engineering



CSE: What challenges do building commissioning projects pose that are different from other projects? 

Jerry Bauers: As a provider of commissioning services, the biggest challenge we face is managing the schedule of commissioning project execution. At every phase of a project, our work is entirely dependent upon the logical and timely execution of the work of other members of the design and construction team. And, in many cases, the incentives that these team members have—both financial and emotional—are in conflict with the requirements appropriate to a disciplined and effective commissioning process. The challenge is to engage the project team members in the notion that an effective construction process and schedule adds value to the results of every member of the team.

James Szel: The biggest challenge to commissioning is to create the environment where everyone from the owner to the contractors to the vendors feels like they are a valued part of the commissioning team. Commissioning is only as important as the owner makes it. When the owner (or its representative) is engaged and actively participating in the process, it really makes for a cohesive, productive team. Another challenge is the timing of the involvement by the commissioning agent (CxA). The CxA should be engaged early in the project to be an integral part of the team, for tasks such as peer reviews. 

Geremy Wolff: Managing the relationships between the contractors, the architecture/engineering team, and the owner can be difficult at times. If everyone is on-board with collaborating to find solutions, it’s great, but there are times when it feels like all we hear is “that’s not in my scope.” This seems to be more prevalent on low-bid work versus design-build or projects with performance requirements. But it is a serious challenge for us.

Some project teams expect the commissioning provider to know everything about everything. This just isn’t the case, especially considering commissioning has expanded into disciplines other than mechanical, electrical, plumbing (MEP), and fire protection, such as building envelope. As the commissioning provider, you don’t have any authority. Through our commissioning process we identify issues and communicate them back to the team, but there is typically no contractual obligation for them to do anything about it. The design-bid-build process used today has not significantly changed in more than 100 years; however, commissioning was not introduced until the late 1980s, so we are still “the new kids on the block.” Integrating our process into the well-established design-build process has proven to be challenging. We still find ourselves educating design and construction professionals on what is commissioning (it’s not just “testing at the end”) and when it should be implemented (it’s never too early).

Barney York: Building commissioning projects are unique in the sense that another party is introduced and integrated into the overall design and construction process. This can create challenges because the CxA’s role has a natural tendency to become adversarial due to the additional oversight the commissioning process adds. In addition, the project schedule can become a challenge as the project completion now requires a contractor to demonstrate a building is not only substantially complete, but functionally complete as well. Commissioning tasks required to demonstrate functional completion must be integrated into the project schedule, and the team must work collaboratively to ensure the owner’s target date is met.

<< First < Previous 1 2 3 4 5 6 7 Next > Last >>

Gerry , Ontario, Canada, 08/29/13 06:33 AM:

Excellent comments we could not agree more
J.R. , TN, United States, 09/04/13 04:27 PM:

Good comments from some large users of the commissioning process.
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Safety for 18 years, warehouse maintenance tips, Ethernet and the IIoT, GAMS 2016 recap
2016 Engineering Leaders Under 40; Future vision: Where is manufacturing headed?; Electrical distribution, redefined
Strategic outsourcing delivers efficiency; Sleeve bearing clearance; Causes of water hammer; Improve air quality; Maintenance safety; GAMS preview
SCADA at the junction, Managing risk through maintenance, Moving at the speed of data
Safety at every angle, Big Data's impact on operations, bridging the skills gap
The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
Applying network redundancy; Overcoming loop tuning challenges; PID control and networks
Driving motor efficiency; Preventing arc flash in mission critical facilities; Integrating alternative power and existing electrical systems
Package boilers; Natural gas infrared heating; Thermal treasure; Standby generation; Natural gas supports green efforts

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
This article collection contains several articles on the vital role of plant safety and offers advice on best practices.
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
This article collection contains several articles on strategic maintenance and understanding all the parts of your plant.
click me