Tips and tricks for commissioning, balancing buildings

08/28/2013



CSE: ASHRAE Standard 202P, Commissioning Process for Buildings and Systems, identifies the minimum acceptable commissioning process for buildings and systems as described in ASHRAE’s Guideline 0-2005, The Commissioning Process. How have you applied this standard in a recent project, and what challenges did you overcome? 

Bauers: We are a NEBB-certified firm. As a member of the NEBB BSC Committee, we developed our procedural standards to comply with the ASHRAE guidelines on commissioning. Given that we have taken this approach, we apply the NEBB standard to commissioning. The challenge in the marketplace that we are finding is that our process and the NEBB standard seem to be more rigorous than many of the processes implemented by our competitors. Using a hands-on approach to commissioning, we are substantially more involved—particularly during construction—than many other firms against whom we price our services. 

Szel: Most of our commissioning projects are either for LEED certification or for critical facilities, which have their own specific requirements for commissioning that exceed the ASHRAE standard. With our critical facilities clients, we try to get engaged early in the process so we have input in the commissioning specifications for the vendors and contractors; we often write them entirely. 

Wolff: We have not applied 202P specifically to a project, though the principles contained within it align with our standard delivery. Another way to look at this is that McKinstry Commissioning has, in effect, already been providing 202P services, since our delivery method is already in accordance with this standard. 

York: I personally have not used the ASHRAE Standard 202P for a commissioning project. The standard was recently released by ASHRAE and most owners and CxAs are still learning the standard. The 202P standard does a great job specifying the minimum commissioning services required to ensure the owner extracts the most value from commissioning. The standard is very similar to the USGBC’s BD&C LEED EA Pre-requisite 1 requirements with the addition of submittal review, systems manual, and training, which we have applied on multiple projects. For systems manuals to be of long-term value, you need an engaged owner in the process—a owner that understands how the systems manual can support long-term operations and maintenance as well as potential system limitations as churn occurs.


<< First < Previous 1 2 3 4 5 6 7 Next > Last >>

Gerry , Ontario, Canada, 08/29/13 06:33 AM:

Excellent comments we could not agree more
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.