The 'HDC' transformer: A liquid-filled transformer designed specifically for application within large data centers

Let me to introduce to you a new liquid substation transformer that I believe solves all of the problems we've been discussing for so many weeks.

Joe Guentert

08/15/2012


If you've been following this series over the past five months, you'll know that there have been three major themes: 

Braided Flex Links Connect Transformer to Secondary Switchgear

1. Dry-type medium-voltage substation transformers have had a long history of catastrophic failures within data centers, due to switching-induced transient voltages when switched by upstream vacuum circuit breakers. I'm personally aware of dozens of such failures, and I'd have to believe there have been dozens more I'm not specifically aware of. Many of the failures have been well-publicized and thoroughly studied, and some solid research by IEEE committees has resulted in guidelines for mitigating techniques, published in IEEE Standard C57.142-2010.

2. Liquid-filled transformers, in contrast, seem far less susceptible to this problem. In fact, I'm unable to find a single documented case of a winding failure in a liquid transformer installed in a data center anywhere that could be attributed to this problem.

 

3. As data center loads have increased so dramatically over the years, and as 400 Y/230 V critical load distribution has gained popularity, the need to apply the "loadcenter substation" concept in data center power systems has become much more pronounced, in order to minimize the lengths of large cross-section secondary feeders and reduce the large tonnage of copper being presently installed in data centers (the title of this overall series of blogs is "Cut the Copper").

By and large, data center owners and their consulting engineers have been reluctant to use liquid-filled transformers inside their buildings. Many—perhaps even MOST—data centers used liquid-filled transformers, but generally installed outdoors. Relatively few liquid transformers have been used indoors, even though transformer manufacturers have offered very safe liquid transformers for that purpose for at least 10 years now. I'm surmising that this is due to a lingering distaste for liquids inside buildings after the production of PCBs was banned by the U.S. EPA more than 30 years ago, and companies were forced to spend billions of dollars in replacing and retrofitting Askerel-filled transformers.

3 MVA “HDC” Substation, 34.5 kV Primary, 200 kV BIL, Close-Coupled to Schneider Electric Secondary Switchgear. (Photo Courtesy Of Terremark Worldwide – A Verizon Company)

But now, let me to introduce to you a new liquid substation transformer that I believe solves all of the problems we've been discussing for so many weeks. I think that this new product is one of the most significant advancements in data center power infrastructure in the last 25 years.

A relatively new liquid transformer design, called HDC, for "Hardened Data Center Transformer," has been developed by Cooper Power Systems. I worked closely with Cooper for several years in refining this new design, in order to develop all of the features I wanted for my clients. It is the first liquid-filled substation transformer designed specifically for application inside data centers.

The secondary of the transformer is close-coupled directly to the secondary switchgear, and a set of very short braided flex links can replace literally 50 or more tons of copper in secondary feeder cables.

The HDC transformer is Envirotemp FR-3 fluid filled, with a compact footprint, and secondary flange/throat for coupling directly to secondary switchgear. Extra BIL (at least one level above ANSI/IEEE standard), is built into the primary windings as standard practice, and all primary leads within the tank are triple-insulated and carefully routed and securely spaced with correct isolation distances in between them.

In this design, it's easy to specify a higher BIL on the primary windings of, say 125 kV or 150 kV BIL, even on 15 kV-class units (more than double the IEEE standard of 60 kV for 15 kV dry-type transformers). I believe that his, in and of itself, would eliminate about 95% of the failures we've been discussing for so many weeks now.

2.5 MVA “HDC” Substation, 12.47 kV Primary, 125 kV BIL, Close-Coupled to IEM Secondary Switchgear (Photo Courtesy of Data Foundry Data Centers)

But beyond that, this design offers an optional feature that addresses switching-induced transients head-on—by preventing their very occurrence in the first place—by adding capacitance directly into the primary windings.

2.5 MVA “HDC” Substation, 24.9 kV Primary, 150 kV BIL, Close-Coupled to Schneider Electric Secondary Switchgear (Photo Courtesy of Sentinel Data Centers)

This feature operates very much like a "snubber," but without the need for any extraneous components like resistors or capacitors ... the capacitance actually becomes part of the primary winding itself. I believe that this technology has the potential to make the serious problem of switching-induced transformer failures a thing of the past, even if the transformer is fed by very short cable primary cables or by direct bus connection to the upstream vacuum breaker.

This new transformer is available with a full assortment of accessories, including internal liquid-submersed vacuum fault interrupter (VFI), 600 A load-break (under-liquid) incoming line switches or four-position loop switch, and viewing windows of the switches for visual confirmation that the transformer is isolated from primary voltage.

I've commissioned about 40 of these HDC transformers in indoor unit substation configurations at seven different data centers in the past three years, in ratings from 1000 kVA through 5000 kVA, with the majority of them in a 3000 kVA rating. No problems have been experienced in any of them so far, now at about 100 aggregate unit-years of operation.

The photos to the right show a typical 35 kV-, 25 kV-, and 15 kV-class unit, top to bottom.

The under-liquid VFI provides superior overcurrent protection, and the under-liqui

Under-Liquid Incoming Line Loadbreak Switches Replace Primary Load Interrupter Air Switches in Zero Footprint and Low Cost

d switches eliminate need for primary air switches generally used with dry-types, but without adding any size to the unit, because they are installed inside the tank.

These units have tested with very high efficiencies, typically in the range of 99.3% to 99.4% for most ratings at 100% of rated load, and around 99.7% at 50% loading.

With the new "voltage suppressor" feature in the design, this transformer seems virtually indestructible from any system problems it might encounter—from overloads, to secondary faults, to switching-induced transient voltages on its primary. It doesn't merely protect itself against switching induced transient voltages, but ELIMINATES them. 

 

And, these units are uniquely and extremely QUIET in their operation. In a typical installation inside an electrical room of a typical data center having typical ambient noise levels, they are virtually inaudible. More about this great new transformer next week.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. The 2012 Top Plant winners have been named.
In 2012, Plant Engineering's Product of the Year program will celebrated its 25th anniversary. Read about the 2012 winners and nominate for 2013.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2012 Leaders here.
Find the fake! Counterfeit electrical equipment a clear and present danger
Investment in excellence: One plant's improved productivity and quality was repaid when their company expanded the facility
Strategic uptime, Increased capacity goes right to the bottom line
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Alarm management tips, Power management, Building automation
Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Attacking Energy Costs: Strategies for showing financial return on energy management investments

2012 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results


Poll of the Week

What category most helps you select new products?
Recommendation from colleagues
Product of the Year winners
Supplier information
Trade show visit


Click Here for Poll Archives
Sponsored by:

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.