Taking A Systematic Approach To Planning Plant Moves

Conducting a plant move is an enormous undertaking from both a mental and financial point of view. Many factors and requirements must be considered. This article offers guidelines on how to plan, execute, and manage a facilities move via truck.

01/01/1998


Conducting a plant move is an enormous undertaking from both a mental and financial point of view. Many factors and requirements must be considered. This article offers guidelines on how to plan, execute, and manage a facilities move via truck.

Basic groundwork

"Before" and "after" drawings of plant areas or operations are essential. Deciding where or how everything should be placed into the new facility before the move begins saves time, money, and frustration. Seeing the items plotted on the layout helps ensure they can be found and moved to the correct location.

Before. Draw a scaled layout of each existing area to be moved. Show every piece of equipment, furniture, shelving, fixture, etc. Make sure it is up-to-date. Identify each item on the drawing with a unique designation.

After. Draw a scaled layout of the new area showing each piece of equipment in its new place. Check the before drawing to be sure nothing is omitted. Be sure to include any new equipment. Identify each item on the new drawing with the same unique designation used in the before layout.

Obtain a shop drawing and/or specification sheet for each piece of plant equipment. This information provides the type of unit, model number, size, weight, and utility needss. On the after drawing, identify the utility hookups for each piece of equipment, and know the mounting method.

Utility considerations include:

- Gas -- type, pressure, and Btuh

- Electric -- voltage, phase, and current or kW or kVA

- Compressed air -- pressure, flow rate, or pipe size

- Water -- type, flow rate, or pipe size; chilled or hot

- Drain -- sanitary or sewer; open or closed.

Onsite inspection

Check the new area near the move date. Take the utility checklist and a set of before and after drawings. There are several areas of concern.

Utilities. Are all the utilities roughed into the proper location? Is there sufficient supply for plant needs and future growth? Consider starting amperage, proper voltage, line conditioners, and gas, water, and airflows. Make sure there is sufficient access to the service panels and valves.

Floors. Will the floor construction support the equipment? Is it level and smooth enough? Consider drain locations and expansion cracks.

Inside environment. Is there proper lighting and ventilation? Air conditioning and heating may need adjustment if production processes give off heat. Consider the noise level in the new area, and whether it may require attention. Are emergency exits properly located and accessible?

Overhead obstructions. Check for clearance of ductwork, air handlers, piping, wiring, doorway heights, and moving hoists or cranes. Consider obstacles which may not be in the way for the move, but may present a safety hazard during normal operations.

Move management

The actual move plan should start with general considerations, and then move into the specifics. For example, general move requirements might include number of process lines, pieces of equipment, or pallets.

Organize the general requirements into more specific groups by:

- Sequence -- What moves first? What is easiest/hardest to move? What will take the longest?

- Due dates -- What has to be in by when?

- Similarities -- What packing or moving method can be applied to groups of equipment?

Ideally, department and product lines are moved as a group.

Develop a task list for each area or group to be moved.

1. List the details of each area's move. Brainstorm a list of tasks which must be completed.

2. Calculate the volume and weight to be moved.

3. Estimate the start and due dates or times. Place each task into a time frame.

4. Estimate the crew size and equipment needed. Receive feedback from crew leaders.

Assign coordinator

A knowledgeable, competent team leader should be chosen to coordinate all activities. This individual develops a general schedule, obtains feedback from key people on a timely basis, then assigns responsibilities, dates, and resources. The team leader should conduct meetings with key people to assess progress and make decisions, publish detailed schedules, and inform personnel well in advance of the scheduled date for the move.

Most important, this person must make plans which are realistic and flexible.

Assess needs

Determine what you need to make the move.

- Do you have enough vehicles in good condition: lift trucks, trailers, and carts?

- Do you have enough packing materials?

- Do you need an outside contractor to do some of the actual moving?

- Do you need any special moving equipment?

Be prepared for last-minute changes, and always have a contingency plan ready. A well-planned move has the greatest chance for success.

-- Edited by Ron Holzhauer,

Managing Editor, 847-390-2668, r.holzhauer@cahners.com

Key concepts

Six questions must be answered before beginning.

The plan should determine what you have to move, schedule for getting it to the new home, and where it goes.

Several specific considerations and suggestions help smooth the flow of equipment and material movement.

The all-important questions

1. What needs to be moved? Identify all items, no matter how small or insignificant they may appear. If it moves, identify it.

2. Where does it move from? All items must be shown on the before print.

3. Where does it move to? All items on the before print must be shown on the after print. Fill new areas from back to front.

4. Who moves what? Assign a person responsible for every item or group of items.

5. When does it have to be there? Timing may be critical for some items.

6. How will it be moved from here to there? Have some idea how the item will be packed and secured, and know how it will be transported (flatbed, trailer, contractor, rental van, personal vehicle, etc.).

Procedures for relocating equipment

Order of move

1. Shut down and purge

2. Tear down: disconnect, disassemble, and tag parts for identification, clean and inspect parts, and perform preventive maintenance

3. Secure for the move: palletize and add extra bracing if needed

4. Load onto vehicle: determine trailer type, size, and quantity

5. Move: deliver pieces of large equipment in the sequence of its rebuild

6. Unload

7. Position and level: mark machine location on floor

8. Utility hook-up: install valves and disconnects for servicing

9. Pilot run and debugging; safety checks first!

General considerations

- Determine crews and crafts needed: electrical, mechanical, plumbing, riggers, HVAC, welders, etc.; estimate time required for each

- Conduct PM while the equipment is torn down; if items are sent out for overhaul, have them delivered to the new location

- Consider adding features such as quick-disconnects to improve serviceability, productivity improvements, and safety items

- Contract manufacturer trained technicians to tear down, secure, and set up sophisticated equipment

- Move spare parts, PM records, tooling and fixtures, and test/calibration equipment with the machine

- Allow time for a pilot run, startup, and debugging; bring along test material and inspection equipment

- Always use every available safety precaution

Moving material to its new home

Don't underestimate the volume of stored material to be moved. Verify the computer report by counting the number of pallets to transport. What condition are they in? Will they survive the move? Is the product stacked neatly so it is easy to handle? Each pallet should be marked with its new location.

General considerations

- Determine how to pack items for the move. Remember that the objective is to protect the product.

-- Palletize: large boxes or large quantities of the same product

-- Gaylords: small boxes, loose, and bulky items

-- Totes: small pieces or quantities

- Have lift trucks move the big loads while the small stuff is being packed.

- Rent extra lift trucks for faster moving and back-up equipment.

- Take a physical count and update inventory records with quantity and location as each product is moved.

More info

The author will answer technical questions concerning this article. Mr. Cummins is available at 630-879-2696, x129.





No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.