Take a step-by-step approach to system troubleshooting

Troubleshooting is a step-by-step procedure whose purpose is to quickly and easily identify a problem in a system or process.

Hilton Hammond, Fluke Corporation

06/13/2012


Troubleshooting is a step-by-step procedure whose purpose is to quickly and easily identify a problem in a system or process. Proper test instruments make the process smoother and make it possible to more easily identify secondary problems where they exist.

To troubleshoot a system, process, or equipment, start by collecting technical records from relevant sources. These include the OEMs, suppliers, contractors, operators, and maintenance departments.

Choose suitable personal protective equipment and test instruments for the job, then isolate the portion of the system or equipment to be tested. Take readings on this portion to test for malfunction. Multiple readings may be necessary in order to either verify proper operation or to identify a problem.

Once located, repair and test the problem area to ensure proper function. The repair process may require technical service, parts replacement, or redemption of a warranty. Perform additional measurements after the initial repair is completed to determine whether any secondary problems still exist.

When all repairs are completed, document the processes performed. Include the original problem, all tests and measurements conducted, and the steps taken to repair the problem if one was found. Also include any secondary problems, if they exist, along with suggestions for solutions. Service and inventory all PPE and tools used while troubleshooting, and note anything that would have improved the process, such as additional tools or training.

When it comes to electrical problems, troubleshooting can range from as broad as a building or system to as specific as an individual component. Troubleshooting electrical equipment starts with basic tests first and moves toward more advanced testing as necessary. Voltage and current tests are the most common, and typically are first conducted at easily accessible points of measurement or access.

Voltage tests

Because all electrical systems and components require power, voltage testing is a logical first step in the troubleshooting process. For comparison, voltage should be measured both while the equipment is on and while it is off. When off, voltage delivered to the equipment in question should fall within -10% to +5% of the equipment nameplate rating,

When on, the operating voltage should not change by more than a maximum of ±3% of the voltage measured while the equipment is off. Ideally, in an appropriately sized power distribution system, the voltage measured should not change whether the equipment is on or off. A difference indicates a power distribution system that is overloaded, or conductors that are undersized or else delivering power for too long. High voltage drops typically require system testing.

When performing basic voltage tests, it is important to ensure correct grounding, as well as that measurements are taken between each phase-to-hot conductor, phase-to-neutral (underground) conductor, and phase-to-ground (grounded) conductor. These phase-to-phase measurements should not vary more than 1% to 3%. If fuses are present where taking voltage measurements, test them to ensure that they are operating correctly.

If the voltage into and out of the fuse is equal, and the voltage across the fuse is 0V, then the fuse is good (closed). If, on the other hand, no voltage is measured out of the fuse, then it is bad (open). This same measurement should also be taken at individual load points within the equipment, such as motors. The voltage delivered should fall within 110% to +5% of the motor’s nameplate rating when it is measured with the equipment on.

Current tests

Current tests are important because they can reveal things that voltage tests do not. A current test can detect whether a motor is delivering full power or half power, or is even inoperable, while the voltage measurement may be consistent at the motor and the load.

A current test will accurately indicate just how loaded a motor actually is. When at full power, the motor should match the listed current rating on the motor nameplate. Typically, though, most motors should draw less. It is also important to measure current over time; unlike voltage, which generally stays the same, current changes as the required load changes.

Current and voltage tests can detect basic problems including open fuses, power loss, and overloaded motors. In order to understand how a motor or system functions over time, however, more complex tests and measurements are necessary. These can include minimum, maximum, relative, and peak temperature measurements, which can be taken using a digital multimeter (DMM) or portable oscilloscope. Portable oscilloscopes, in addition to power quality meters, can test for waveform distortion problems. Portable oscilloscopes are ideal for taking advanced measurements because of their advanced test functions.

Should a test indicate a possible problem, a portable oscilloscope can isolate it. Common problems can be detected using these testing methods, and more serious and potentially damaging problems can be detected as well. Advanced measurements, taken over time and monitored closely, can provide crucial information about systems and equipment.

Excerpted from the book, “Motor and Drive Troubleshooting,” written by Glen A. Mazur and published by American Technical Publishers.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. The 2012 Top Plant winners have been named.
In 2012, Plant Engineering's Product of the Year program will celebrated its 25th anniversary. Read about the 2012 winners and nominate for 2013.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2012 Leaders here.
Investment in excellence: One plant's improved productivity and quality was repaid when their company expanded the facility
Strategic uptime, Increased capacity goes right to the bottom line
2013 Forecast Issue: A shift in manufacturing
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Alarm management tips, Power management, Building automation
Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Attacking Energy Costs: Strategies for showing financial return on energy management investments

2012 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results


Poll of the Week

What category most helps you select new products?
Recommendation from colleagues
Product of the Year winners
Supplier information
Trade show visit


Click Here for Poll Archives
Sponsored by:

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.