Take a step-by-step approach to system troubleshooting

Troubleshooting is a step-by-step procedure whose purpose is to quickly and easily identify a problem in a system or process.

06/13/2012


Troubleshooting is a step-by-step procedure whose purpose is to quickly and easily identify a problem in a system or process. Proper test instruments make the process smoother and make it possible to more easily identify secondary problems where they exist.

To troubleshoot a system, process, or equipment, start by collecting technical records from relevant sources. These include the OEMs, suppliers, contractors, operators, and maintenance departments.

Choose suitable personal protective equipment and test instruments for the job, then isolate the portion of the system or equipment to be tested. Take readings on this portion to test for malfunction. Multiple readings may be necessary in order to either verify proper operation or to identify a problem.

Once located, repair and test the problem area to ensure proper function. The repair process may require technical service, parts replacement, or redemption of a warranty. Perform additional measurements after the initial repair is completed to determine whether any secondary problems still exist.

When all repairs are completed, document the processes performed. Include the original problem, all tests and measurements conducted, and the steps taken to repair the problem if one was found. Also include any secondary problems, if they exist, along with suggestions for solutions. Service and inventory all PPE and tools used while troubleshooting, and note anything that would have improved the process, such as additional tools or training.

When it comes to electrical problems, troubleshooting can range from as broad as a building or system to as specific as an individual component. Troubleshooting electrical equipment starts with basic tests first and moves toward more advanced testing as necessary. Voltage and current tests are the most common, and typically are first conducted at easily accessible points of measurement or access.

Voltage tests

Because all electrical systems and components require power, voltage testing is a logical first step in the troubleshooting process. For comparison, voltage should be measured both while the equipment is on and while it is off. When off, voltage delivered to the equipment in question should fall within -10% to +5% of the equipment nameplate rating,

When on, the operating voltage should not change by more than a maximum of ±3% of the voltage measured while the equipment is off. Ideally, in an appropriately sized power distribution system, the voltage measured should not change whether the equipment is on or off. A difference indicates a power distribution system that is overloaded, or conductors that are undersized or else delivering power for too long. High voltage drops typically require system testing.

When performing basic voltage tests, it is important to ensure correct grounding, as well as that measurements are taken between each phase-to-hot conductor, phase-to-neutral (underground) conductor, and phase-to-ground (grounded) conductor. These phase-to-phase measurements should not vary more than 1% to 3%. If fuses are present where taking voltage measurements, test them to ensure that they are operating correctly.

If the voltage into and out of the fuse is equal, and the voltage across the fuse is 0V, then the fuse is good (closed). If, on the other hand, no voltage is measured out of the fuse, then it is bad (open). This same measurement should also be taken at individual load points within the equipment, such as motors. The voltage delivered should fall within 110% to +5% of the motor’s nameplate rating when it is measured with the equipment on.

Current tests

Current tests are important because they can reveal things that voltage tests do not. A current test can detect whether a motor is delivering full power or half power, or is even inoperable, while the voltage measurement may be consistent at the motor and the load.

A current test will accurately indicate just how loaded a motor actually is. When at full power, the motor should match the listed current rating on the motor nameplate. Typically, though, most motors should draw less. It is also important to measure current over time; unlike voltage, which generally stays the same, current changes as the required load changes.

Current and voltage tests can detect basic problems including open fuses, power loss, and overloaded motors. In order to understand how a motor or system functions over time, however, more complex tests and measurements are necessary. These can include minimum, maximum, relative, and peak temperature measurements, which can be taken using a digital multimeter (DMM) or portable oscilloscope. Portable oscilloscopes, in addition to power quality meters, can test for waveform distortion problems. Portable oscilloscopes are ideal for taking advanced measurements because of their advanced test functions.

Should a test indicate a possible problem, a portable oscilloscope can isolate it. Common problems can be detected using these testing methods, and more serious and potentially damaging problems can be detected as well. Advanced measurements, taken over time and monitored closely, can provide crucial information about systems and equipment.

Excerpted from the book, “Motor and Drive Troubleshooting,” written by Glen A. Mazur and published by American Technical Publishers.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.
Electric motor power measurement and analysis: Understand the basics to drive greater efficiency; Selecting the right control chart; Linear position sensors gain acceptance
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.