Swedish nuclear power plant modernizes I&C infrastructure

Ringhals Unit 3 implements a new control system during 30-day shutdown, back on line for winter demand.

02/01/2011


Ringhals, the Swedish electric power utility, has upgraded the instrumentation and control (I&C) infrastructure for its Unit 3 in record time. Working with Alstom, the team has successfully completed the installation of a new control system in 30 days. The system has passed an exhaustive series of operational testing since it first synchronized to the grid in mid-October. This is the last important milestone of the integrated retrofit of the complete turbo group systems of Unit 3 which will boost generating efficiency. The commissioning of the new control system enabled the plant to deliver full power output in time for the increasing winter demand.

"I am very pleased with the good collaboration during the project execution” said Bertil Dihné, president, Ringhals AB. “Thanks to our joint efforts, all challenges within the project were met, and Ringhals 3 is now up and running in secure and stable commission.”

After a long period of engineering and mock-up tests, the actual installation work began in late August and was completed one month later, to meet the deadline for cold commissioning – a phase of preparation, installation, and testing, before turning the reactor steam on.

The next major step for Ringhals and Alstom is the completion of block 4 in 2011, which includes installation of the control system, erection of four new moisture separators, installation of two high-pressure turbines, and two low-pressure preheaters.

The Ringhals nuclear power plant is situated on the west coast of Sweden, 60 km south of Gothenburg, and at 3,690 MW, is the largest power plant in Scandinavia. The plant has four reactors - three pressurized water reactors and one boiling water reactor. In a normal year, Ringhals generates around 28 billion kWh – approximately 20% of Sweden’s total electrical energy consumption.

www.alstom.com

www.ringhals.se

Edited by Peter Welander, pwelander(at)cfemedia.com

Visit the Control Engineering Process Control Channel.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. The 2012 Top Plant winners have been named.
In 2012, Plant Engineering's Product of the Year program will celebrated its 25th anniversary. Read about the 2012 winners and nominate for 2013.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2012 Leaders here.
Find the fake! Counterfeit electrical equipment a clear and present danger
Investment in excellence: One plant's improved productivity and quality was repaid when their company expanded the facility
Strategic uptime, Increased capacity goes right to the bottom line
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Alarm management tips, Power management, Building automation
Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Attacking Energy Costs: Strategies for showing financial return on energy management investments

2012 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results


Poll of the Week

What category most helps you select new products?
Recommendation from colleagues
Product of the Year winners
Supplier information
Trade show visit


Click Here for Poll Archives
Sponsored by:

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.