Student design team helps university save $2 million annually in utility costs

Students enrolled in the department of Mechanical Science and Engineering at the University of Illionis at Urbana-Champaign helped design a waterside economizer system wtih a cooling tower to keep the department's new supercomputer cool.

08/15/2008


A student design team in the Dept. of Mechanical Science and Engineering (MechSE) at the University of Illinois at Urbana-Champaign

The Blue Waters petascale supercomputer is expected to be the most powerful computer dedicated to scientific research when it comes online in 2011. It also will require lots of cooling power, as its many processors generate vast amounts of heat.

"We could have easily have spent $20,000 to hire a firm to validate the original design, but we thought it would be nice to get some of our own engineering students involved in helping us solve a real problem at their alma mater," said John Melchi, senior associate director, administration directorate at the National Center for Supercomputing Applications (NCSA). "It was a great chance for undergraduates to work on such a national scale, visible project."

Four seniors in the MechSE senior design program—Stanley Berent, Ross Ratajczak, Andrew Thacker, and Christopher Theis—answered the challenge to cool the supercomputer .

While most supercomputing systems are air-cooled, the heat from Blue Waters will be cooled by the university's central chilled water system. The students—working under the guidance of senior design project coordinator Emad Jassim, developed a computer model to simulate the operation of multiple economizer designs involving different tower and component sizes on an hourly basis for an entire year using local weather data. They predicted the total annual chilled water reduction and total annual cooling cost associated with each design.

The students' analysis provided valuable guidance in the design process. It indicated that the annual operating cost of the system initially proposed by a Chicago-based consulting firm could be reduced by an additional $1 million. In the end, the design the students proposed was similar to the one proposed by the consulting firm—giving everyone involved a high degree of confidence that they had arrived at the optimal system. Once implemented, the cooling system is expected to reduce the annual chilled water usage substantially, saving NCSA a predicted $2 million a year in operating costs. At an estimated initial cost of just over $3 million, it is expected to pay for itself in approximately one and a half years.

According to the system designers, the larger the economizer system, which mainly consists of cooling towers, heat exchangers, pumps and piping, the greater the energy savings, but also the greater the initial cost. The optimum design lies where the sum of the initial and operating cost over the predicted life of the data center is a minimum, or has the least lifecycle cost. The team determined that delivering chilled water directly to the processors will avoid the inefficiencies associated with the intermediate step of using chilled water to cool air, and is expected to reduce energy consumption by approximately 40%.

When it is finally in operation, Blue Waters will give scientists and engineers the capability to process








Enter CSE's ARC Awards ! Entries due Aug. 29.





No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.