Sports, entertainment venues: Automation and controls

Sports arenas and entertainment facilities involve complex engineering solutions. Five consulting engineers offer advice on building automation and controls.

04/24/2013


Keith Cooper, PE, President, McClure Engineering, St. Louis. Courtesy: McClure EngineeringDouglas H. Evans, PE, FSFPE, Fire Protection Engineer, Clark County, Nevada. Courtesy: Clark County, NevadaBill Larwood, PE, LEED AP, Senior Vice President/Project Principal, Syska Hennessey Group, Los Angeles. Courtesy: Syska Hennessey GroupKevin Lewis, PE, LEED AP BD+C, Vice President, Henderson Engineers, Lenexa, Kansas. Courtesy: Henderson EngineersBruce McKinlay, Principal, Arup, Los Angeles. Courtesy: Arup

Participants (left to right):

 

Keith Cooper, PE, President, McClure Engineering, St. Louis

Douglas H. Evans, PE, FSFPE, Fire Protection Engineer, Clark County, Nevada

Bill Larwood, PE, LEED AP, Senior Vice President/Project Principal, Syska Hennessey Group, Los Angeles

Kevin Lewis, PE, LEED AP BD+C, Vice President, Henderson Engineers, Lenexa, Kansas

Bruce McKinlay, Principal, Arup, Los Angeles 


CSE: When designing monitoring and control systems, what factors do you consider?

Evans: From a fire protection standpoint, the initiating devices (primarily sprinkler water flow and smoke detection) must be taken into account and the associated output functions (primarily audible/visual alarms and activation of smoke management systems).

Cooper: Integration into a campus system (where applicable) is one of the major factors we must consider. In these cases, the equipment is often less of a factor than the way the existing systems are being operated and by whom. Significantly different operations philosophies can doom a project if not sorted out early and often. If you want to guarantee that a perfectly operating building system will not function correctly on its first birthday, hand it off to an operator who has not bought into the control schemes of the original design.

Larwood: Complexity is always a factor, as well as cost. The system should be matched with the sophistication of the operator.

McKinlay: Control and monitoring systems need to be seamless in operation and also be able to provide continuous feedback as to the operating characteristics of critical systems to minimize failure during the event. This includes major HVAC equipment, fire life safety systems, lighting, and electrical systems. The monitoring and control systems need to effectively switch between redundant systems to balance loads and prevent outages. In event of a power failure, the control systems need to automatically and quickly switch to backup systems to minimize downtime.

Lewis: When it comes to building controls, we want to provide a system that is robust and easy to integrate. After the contractor has installed the system and has left the job, we want to make sure the end user is trained in, and understands how to modify the designed system. Due to reduced maintenance staff and increased energy efficiency standards, automating as many controls as possible seems to be in the best interest of the end user.

CSE: What are some common problems you encounter when working on such systems?

Lewis: The typical issue with controls is usually the start-up process. The contractors do a great job integrating the building systems but are always under the gun to get all equipment up and running and programmed while construction is still happening. This makes it difficult to properly assess a project in a final punch and verify the equipment is working as designed.

McKinlay: That these systems are not properly commissioned and don’t have the flexibility for expansion for future needs of the venue, ensuring efficient use and predicting the future needs and flexibility.

CSE: When integrating systems, what challenges must you overcome?

Cooper: You have to ask who is responsible for the temperature control system operation and who is responsible for lighting controls scheduling. If it’s the same person or group, the challenges are minimal. If it’s not but they play well together, integration has a good chance. If it’s not and neither person/group wants the other touching their “stuff,” integration may not be the best solution.

Lewis: The integration of multiple disciplines is typically straightforward. The biggest challenge, or area to watch, is coordination. The design team needs to be cohesive and share information back and forth. The second big issue is to understand from the owner how the building will be operated. While most owners are very good at understanding revenue streams, the actual day-to-day operations of a building sometimes pose challenges. We have learned over the years how to ask the right questions to assist the owner team and really make the integration of systems work for the owner.

Larwood: One common concern is the security of routing data of the building automation system (BAS) and lighting over a backbone that serves the data network.

Evans: One of the primary areas fire protection engineers specialize in is coordinating fire protection aspects between differing disciplines. This includes the architectural aspects (fire-resistive construction and egress) as well as the engineering disciplines (secondary power supplies, smoke management systems, and structural fireproofing) and contractors (fire alarm and sprinklers).



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.