Sense and sustainability

Careful planning and continued effort were key to commissioning HSBC’s North American headquarters.

07/18/2008


The planning and effort put into the new 560,000-sq.-ft HSBC North American Headquarters to make it sustainable is a study in successful commissioning.

 

The building systems were designed with the purpose of reducing the carbon footprint of the building and minimizing energy costs. Lighting and HVAC occupancy sensors, an energy efficient envelope, rain-water reuse capabilities, and a reflective roof have made this possible.

 

Careful planning and continued effort were key to commissioning HSBC’s North American headquarters.
A large structured cabling system reduces the amount of cabling and enables the building to accommodate further systems integration. Audio visual displays, security cameras, and building automation systems (BAS) all can be set-up on the same infrastructure.

 

Natural light is maximized throughout the building with an automatic window blind system that harvests daylight by reflecting it deeper into the space. A light-sensing luminary control system regulates the lighting panels depending on the amount of natural light available to provide the desired level of illumination.

 

Coupled with months of expanded commissioning, these sustainable and integrated strategies help the suburban Chicago office building in Mettawa, Ill., exceed ASHRAE standard 90.1-1999 by as much as 50%, helping the building earn a USGBC LEED NC gold rating. The site received a credit apiece in both fundamental and enhanced commissioning.

Early challenges and testing
Beginning with the project’s design phase in early 2006 and continuing throughout construction and post-occupancy this spring, expanded commissioning of the building helped link the owner’s project requirements to systems performance.

 

Back-up power increases sustainability
With integrated systems playing such a crucial role in the building’s performance, HSBC wanted to make sure there was adequate back-up coverage. Deeming all systems critical, from personal computers to the HVAC equipment, owners required both BAS and BIS full-systems coverage. The generators, which currently are filled with diesel, are capable of providing the same performance with bio-diesel should HSBC decide to use it at a future date. The facility’s emergency power is set to kick in at 100% load if the need dictates. Run times will vary on the season and load shedding.

Reviewing test and balance reports generated by a third party, the commissioning team ran through test scripts for each system, opening valves and simulating each mode of operation, including device failures to eliminate malfunctions for first-time scenarios. Walking through each season, the team allowed the building to practice winter, spring, summer, and fall. With four to five commissioners over a period of six to eight weeks post-construction, each system was completely tested.

The facility’s integrated systems challenged commissioning as well. During one test of the HVAC equipment, temperatures were being maintained in air conditioning mode, yet the system was not performing as efficiently as designed. A quick look at the building information system (BIS) revealed a pressure imbalance; comparing cooling tons to the building’s electrical consumption didn’t match up. Site inspections and assistance from the general contractor led to the identification of a caulk and seal issue that repeated itself. The commissioning team now knew the irregularity was coming from an outside heat source; too much air was being introduced into the building.

Using the BIS as a tool, the imbalance was uncovered at the curtainwall: air was seeping in. The architect and contractor were brought in and the repair was made, with HVAC energy efficiency and consumption finally functioning as designed.

Without commissioning, HSBC building and design engineers wouldn’t have been able to make real-time measurements of the facility’s energy use and the problem may have gone undetected, resulting in a significant loss of energy over the 20- to 30-year life of the building. If left without a fix, this would have certainly caused the building to incur large costs due to unfiltered air and increased electricity use. However, using the BAS run times and the monthly and daily electric data from the local utility, the problem was identified and eliminated. This one find may have paid for the commissioning itself.

As the North American Headquarters for HSBC, the building also houses a corporate data center crucial to the company’s operations, which was to be occupied before to the rest of the building. This meant that mission critical systems needed to be intensely commissioned before building completion and prior to data center occupancy, only to be re-commissioned again with the rest of the facility after construction.

Personnel training and continued testing
Following design and testing, the commissioning team turned to training. Although engineer and operator education is often an afterthought, it is a vital part of maintaining an energy-efficient building. Attendees received more than 80 hours of equipment and system specific training in the classroom as well as at the BAS terminal and at the various equipment facilities themselves.

 

A challenge under the floor
As an additional challenge, the team had to commission an underfloor air distribution system. The biggest challenge was in educating the installing contractor that the flooring and underfloor area was going to be used as a duct and needed to be absolutely airtight. Observation and coaching during construction identified and corrected various leaks before they became too costly to repair.

 

Because of the sustainable and integrated properties of the building’s systems, site operators would need a thorough understanding of how to capitalize on operating efficiencies to save as much energy as possible going forward. For example, running two fans and two motors at a smaller load versus one on a higher load may be more efficient at times. The commissioning team trained building engineers on these issues and even brought in the air handler manufacturer to speak about appropriate compliance with design specifications.

 

Bringing the right teachers and students together in a sustainable environment can help establish a benchmark for future building efficiency and integration. The Environmental Systems Design team is currently still involved in seasonal commissioning at the facility throughout its first year in operation, maintaining the checks and balances at the company’s newest sustainable site.

Mike Kuppinger, PE, Senior Vice President, Mission Critical and Technology Group, Environmental Systems Design, Chicago, contributed to this article.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.