Saving time with SCADA

.

04/01/2009


View the full story, including all images and figures, in our monthly digital edition

 

In an effort to minimize the number of sustained power outages resulting from storm-triggered temporary faults, Jersey Central Power & Light (JCP&L) installed an adaptive-relay scheme. The scheme improved the utility's system average interruption duration index (SAIDI) reliability metric by reducing the number of time-consuming fuse replacements.

JCP&L was previously limited by installed electromechanical relays equipped with timing options that were selectable locally at substations. JCP&L engineers proposed a series of adaptive relays tied into the utility's supervisory control and data acquisition (SCADA) system. JCP&L needed to find an adaptive relay that had field-tested reliability, complied with the SCADA system and existing electromechanical and microprocessor-based relays, operated at 48 or 125 V direct current, and controlled more than one breaker installation

Electroswitch , Weymouth, Mass., provided JCP&L with a variation of its two-position, Series 31 tagging relay (TR). Electroswitch installed the TRs at 275 locations, comprising all 1,100 circuits in JCP&L's 13 districts. Each district now has one substation outfitted with SCADA-interfaced equipment that measures wind speed and detects lighting.

When the wind speed exceeds 25 mph, or lighting is detected, the pertinent regional dispatch office (RDO) can reset the protecting-timing scheme of its substations, either individually or by group. Actuation of the Electroswitch TR changes a substation's relay timing from fuse-sacrifice mode to fuse-saving mode.

In fuse-saving mode, a feeder circuit breaker is set to operate instantaneously—faster than lateral tap fuses. Since 70% of storm faults are temporary, opening the circuit first and then closing back on a time-delayed setting allows most of these faults to clear themselves. If the fault is still present after the breaker closes, the fuse on the affected lateral will blow, which requires a line crew to replace it.

At the selected substation, the TR latches in its red mode tag, which indicates that the facility is in fuse-saving mode. After the storm, the RDO sends another SCADA command to return the substation to fuse-sacrifice mode, and the TR's tag changes to green.

In 2008, JCP&L experienced 884 breaker operations in response to the line disturbances. The system's control of the instantaneous timing response of the electromechanical protective relays saved 22.4 SAIDI minutes, while maintaining the integrity of the installed line fuses.

Information provided by Jersey Central Power & Light.



AT A GLANCE

Jersey Central Power & Light (JCP&L) installed an adaptive-relay scheme to minimize the number of sustained power outages resulting from strom-triggered faults.

JCP&L needed to find an adaptive relay that featured field-tested reliability, compatibility with the SCADA system, controlled more than one breaker installation, and operated at 48 or 125-V direct current.

Electroswitch provided JCP&L with a solution by implementing:

  • A variation of its two-position, Series 31 tagging relay.

  • SCADA-integrated equipment on one substation at each JCP&L district.

  • An adaptive relay system, which saved 22.4 SAIDI minutes after 884 breaker operations in response to line disturbances.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.