Sanford Consortium for Regenerative Medicine

New construction: Sanford Consortium for Regenerative Medicine; exp

08/09/2012


Project name: Sanford Consortium for Regenerative Medicine

Location: La Jolla, Calif.

Firm name: exp

Project type, building type: New construction, research/lab/high-tech

Project duration: 3 years

Project completion date: March 30, 2007

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $1.2 million

Engineering challenges

This project was run by a collaboration of four not-for-profit research entities: The Burnham Institute for Medical Research, The Salk Institute for Biological Studies, The Scripps Research Institute, and the University of California, San Diego (UCSD). This created challenges to meet varying program requirements. exp’s extensive experience with the lab environment was brought into play as we were asked to help develop mechanical, electrical, plumbing, and low-voltage infrastructure systems that designed flexible laboratory spaces that are adaptable to specific user group’s needs based on which one brings in the latest grant funding. exp provided input for design of overhead carriers for gases and electrical power to support the flexible lab spaces and worked closely with the architect on the specialty lighting design to deliver required lighting levels while being energy efficient and helping to articulate the high-end design features into this campus.

Solutions

exp was the LEED consultant for this project and as the project is targeting U.S. Green Building Council LEED Gold certification, we spent significant effort modeling the building and evaluating alternate air circulation and cooling methodologies. Some of the systems evaluated via IES modeling software were natural ventilation via automatically operated windows, displacement ventilation, variable refrigerant flow systems, and chilled beam cooling. Through extensive modeling, we were able to present various scenarios complete with initial system costs, anticipate annual energy savings, and predict payback periods for the various energy saving solutions. This resulted in the team’s decision to implement these energy-saving features into various areas of this research campus. We were also utilized to provide commissioning services for systems not required to be commissioned by others for third-party LEED commissioning point. On the plumbing scope we integrated the use of reclaimed water for makeup water at the cooling tower system, irrigation, and for water closets/urinals/drain trap priming inside the building. This proved to be exceptionally challenging, as this was one of the first projects in San Diego County that implemented the use of reclaimed water inside a building. We spent significant time developing the design and documentation for this system to meet the City of San Diego water requirements and the State of California regulatory commission requirements. This solution was ultimately implemented and is up and running with no issues after approximately 1 year of occupancy.

For exterior lighting, one of our challenges was to meet IES recommended foot-candle levels for outdoor lighting while also conforming to the local Dark Skies initiative in the greater San Diego area, LEED requirements for light pollution reduction point, and adjacent Glider Port flight pattern/landing requirements, while also having limitations respecting pole base areas on the site due to catch basin and bioswail requirements relayed by the civil engineers. Our solution, which required many iterations of modeling, implemented the use of 180 W low-pressure pole-mounted fixtures at 18 ft and 25 ft height along with pedestrian scale 14 metal halide pole-mounted fixtures and bollards strategically arranged to provide recommended foot candle levels with no spill light outside the project boundaries while also helping to create a safe and organized feel to the outdoor components of this research campus.

Additional Information 

View a presentation from exp on the project



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.