Reliability considerations in simple paralleling applications

04/10/2013


Scalability

Paralleling systems are frequently expanded after they are put into service to accommodate increasing power demands. The ability to add a generator set and the associated switchgear in the future should always be considered. The system should have the flexibility to allow generator sets from a different manufacturer to be added in the future. Being locked in to a certain manufacturer limits the flexibility for future expansions. Additional question to ask concerning expansion include: 

  • Are the generators properly isolated so that new generators can be added without taking the facility off line?
  • What is involved in modifying the control for expansion? If a different manufacturer’s generators are used for the expansion, what will be required for the generators to parallel properly?
  • Does the manufacturer have experience in implementing field expansions, including expansions that include generators from other manufacturers?
  • How can the system be modified to support utility paralleling if that is required in the future? 

Conclusions

The decision on whether to provide backup power with a single generator set or with redundant paralleled generator sets will be based on reliability and cost. The key question is whether the redundancy coupled with the added complexity of a paralleling system increase the system reliability enough to justify the additional cost. When a decision has been made to parallel generator sets, the following should be addressed to maximize the reliability of the system:

  • The control system should be designed with critical functions distributed to the individual generator controls to minimize single points of failure.
  • The controls should have fault tolerance provisions such as load shed and manual operating modes.
  • The installation must meet code requirements for coordination, separation of circuits, and 10-second service to emergency loads and must allow proper isolation of the generator sets.
  • The system must be supported by an organization with a proven track record for servicing complete paralleling systems.  

Rich Scroggins is a technical specialist at Cummins Power Generation. Scroggins has been with Cummins for 20 years in a variety of engineering and product management roles and is active in IEEE 1547 and NEMA SC 16. He received his bachelor’s degree in electrical engineering from the University of Minnesota and an MBA from the University of St. Thomas.


<< First < Previous 1 2 3 4 5 6 Next > Last >>

Anonymous , 05/08/13 10:25 AM:

Excellent Article.
VISH , CA, United States, 05/08/13 12:53 PM:

Some of the increased cost of the parallel system can be off-set by Peak Load shaving technique. Illustration of Pros and cons of the system will greatly help the engineers to make the right decision.
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.