Reliability considerations in simple paralleling applications

04/10/2013


Installation considerations

Installing and commissioning paralleled generator sets is not a simple process. A qualified manufacturer will have experience with protective relaying, system grounding, and other paralleling issues beyond the generator set functionality. Working with a manufacturer that has substantial paralleling experience over a wide range of applications and will assume responsibility for a correct installation is a key to a successful project even in the most basic paralleling application. There are several considerations that an experienced installer will address. 

Selective coordination. The National Electrical Code (NFPA 70) requires selective coordination for emergency and legally required loads (Sections 700.27 and 701.27). Any downstream breakers must coordinate with upstream overcurrent protection such as paralleling breakers or a genset mounted breaker. Coordinating with a generator set mounted molded case circuit breaker (MCCB) with an instantaneous trip will be very difficult and will require in most cases that the downstream breakers are supplied from the same breaker manufacturer as the genset mounted MCCB. It is much easier to coordinate with power breakers as are most often used in paralleling switchgear as they are typically equipped with a programmable trip unit specifically for the purpose of coordination. When the generator control includes integral, UL listed overcurrent protection, coordination between the genset and the paralleling breaker is simplified because the overcurrent trip curve is optimized to allow the maximum permissible time delay while still protecting the alternator.

Separation of circuits. The National Electrical Code (700.10(B)(5)) requires that emergency loads are separated from legally required and optional loads. NEC 700.10(B)(5)(d) allows the use of “single or multiple feeders to supply distribution equipment between the emergency source and the point where the combination of emergency, legally required or optional loads are separated.” In this context the “emergency source” can refer to either a single generator set or the bus in the case of paralleled generator sets. Emergency circuits must be separated from legally required and optional standby circuits with separate circuit breakers installed in separate switchboard sections or enclosures. Emergency loads must be switched using a dedicated transfer switch, separate from legally required and optional standby circuits.

There is some ambiguity in the code regarding whether legally required and optional standby circuits need to be separated from each other. The language in the code doesn’t explicitly require separation of legally required loads from optional standby loads, but all of the exhibits in the NEC handbook show them as separate. Some authorities having jurisdiction (AHJs) have enforced separation of legally required loads from emergency standby loads. 

Isolation of generators from the paralleling bus. To enable maximum reliability and safety, there must be means to individually disconnect each generator from the paralleling bus located at the paralleling switchboard. Without this disconnecting means, typically an incoming breaker, a fault on one generator can make all generators inoperable and all generators will have to be locked out to do maintenance work on any generator in compliance with NFPA 70E lockout-tagout requirements (see Figure 3). Without this disconnecting means, much of the value of having a redundant generator will be lost.

Figure 3: Distribution panel with no incoming breaker: Without the incoming breaker, a fault in one generator feed or maintenance on one generator will make the whole system inoperable. Courtesy: Cummins Power Generation

10-second start requirement. The National Electrical Code requires that emergency loads are served within 10 seconds of a utility failure. As 10 seconds typically isn’t enough time to start, synchronize, and close multiple generator sets, this requirement means that each of the generator sets in the system must be large enough to carry all of the emergency loads on its own. For example, a system of three paralleled 600 kW generator sets will not meet the NEC requirement if the emergency load exceeds 600 kW. To meet this requirement, the sequence of operations should not require any interaction with a master controller. All control functions should be carried out independently by the generator and the transfer switch controls with no communication required other than a genset start command. 

Supplier of distribution switchboard. Sourcing the generator and paralleling controls separately from the switchboard complicates a project. The contractor and consulting engineer must have a clear definition of what is included in the scope of supply for each part of the system. Dividing scope of supply won’t be limited to equipment but will also include assignment of responsibility for meeting code requirements like selective coordination and separation of circuits, system testing and start-up, and ongoing maintenance and service. Having the same entity responsible for supply, installation, and maintenance helps promote an efficient maintenance program. 



Anonymous , 05/08/13 10:25 AM:

Excellent Article.
VISH , CA, United States, 05/08/13 12:53 PM:

Some of the increased cost of the parallel system can be off-set by Peak Load shaving technique. Illustration of Pros and cons of the system will greatly help the engineers to make the right decision.
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
2016 Engineering Leaders Under 40; Future vision: Where is manufacturing headed?; Electrical distribution, redefined
Strategic outsourcing delivers efficiency; Sleeve bearing clearance; Causes of water hammer; Improve air quality; Maintenance safety; GAMS preview
World-class maintenance: The three keys to success - Deploy people, process and technology; 2016 Lubrication Guide; Why hydraulic systems get hot
Flexible offshore fire protection; Big Data's impact on operations; Bridging the skills gap; Identifying security risks
The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Applying network redundancy; Overcoming loop tuning challenges; PID control and networks
Driving motor efficiency; Preventing arc flash in mission critical facilities; Integrating alternative power and existing electrical systems
Package boilers; Natural gas infrared heating; Thermal treasure; Standby generation; Natural gas supports green efforts

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
This article collection contains several articles on the vital role that compressed air plays in manufacturing plants.
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
This article collection contains several articles on strategic maintenance and understanding all the parts of your plant.
click me