Real-time power management is a plant manager's secret weapon

12/05/2013


Sequence of event playback

The ability to recover from a system disturbance depends on the time it takes to establish the cause of problem and take remedial action. This requires a fast and complete review and analysis of the sequence of events prior to the disturbance. Power management software should assist your operation and engineering staff to quickly identify the cause of operating problems and determine where energy costs can be reduced. The software should also be able to reconstruct exact system conditions to check for operator actions and probe for alternative actions after-the-fact. This important tool serves as an on-going learning process for the operator.

Besides reducing losses and improving data gathering capability, such an application should assist in increase plant reliability and control costs. The event playback feature is especially useful for root cause and effect investigations, improvement of system operations, exploration of alternative actions, and replay of “What If” scenarios.

Event playback capability translates into savings. For example, a conservative estimate of 10% reduction in downtime for an outage that lasts an hour yields about $33,000 in savings. 

Online control

An advanced power management system should provide the options for full remote control to the system elements such as motors, generators, breakers, load tap changers, and other protection devices directly or through existing Supervisory Control and Data Acquisition (SCADA) system.

In addition, the software should provide user-definable actions that can be added or superimposed on the existing system for automating system control. This is similar to adding PC-based processors/controllers (kV, kW, kvar, PF, etc.) or simple breaker interlocks to any part of the system by means of the software.

Supervisory and advisory controls 

State-of-the-art supervisory and advisory control capabilities should be used to control and optimize in real-time various parameters throughout the system. Using optimization algorithms, the user could program the power management system (i.e., assist energy consumers by automatically operating their system to minimize system losses, reduce peak load consumption, or minimize control adjustment). For energy producers, this energy management system could be set up to minimize generation fuel costs, and optimize system operation.

Demand response or management

Another significant cost component of operations is demand charge of the energy bill. The demand charge is 40% to 60% of the bill for sites without peak shaving generation. A single unmanaged demand charge can produce a very large hike in the power bill each month and with “ratcheting” demand charges, the effect can linger for an entire year.

An intelligent power management system should provide the current and predicted demand for each day thus managing peak demands on a continuous basis. Loads can be shed manually or automatically, peak-shaving generators can be started, load startup can be postponed or sequenced, while maintaining and preserving vital processes.

A classic example is an industrial plant that purchases a new large motor and decides to perform a full-run test for 30 minutes. At the end of the month, the purchasing department notifies the operations manager because their operating bill is up by 7%, or nearly $20,000. Since their contract was a “ratcheting” contract, the peak demand charges they paid that month lingered for 10 months, making the motor test a $200,000 mistake, which could have been avoided if system demand had been monitored, simulated with system operating conditions and therefore fully understood.

In a study performed for a large industrial facility (150MVA), advanced optimization algorithms, native to the energy management system, were utilized to reduce real and reactive power losses. Assuming a conservative power loss reduction of only 0.1% at an average electrical energy cost of $0.13/kWh, an energy management system would yield savings of more than $135,000 per year and would pay for itself through the immediate realization of savings in operating and maintenance costs. 

Intelligent proactive load shedding

A major disturbance in an electrical power system may result in certain areas becoming isolated and experiencing low frequency and voltage, which can result in an unstable operation. A model based power management system can easily determine the electrical subsystems (areas of the network that are electrically isolated) including islanding detection. The system should then provide optimal “fast load shedding” based on the actual operating condition of the system including type and location of the disturbances.

Fast response time of less than 40ms (duration between disturbance to tripping non-essential load) is achievable. High-speed load shedding has become a necessity because the stability margins for today’s complex systems are razor thin. The longer it takes to shed load during a disturbance, the more load that must ultimately be shed.

By adding intelligence and proactive calculations, fast response times can be achieved. By speeding up the load shedding process, the actual amount of load that is shed is far less than that of using the conventional methods such as frequency relay and PLC-based schemes; both of which rely on fixed logic, lack logic validation using stability analysis and post process the disturbance adding to the response time delays.

The power management system should have the intelligence to initiate load shedding based on a user-defined Load Priority Table (LPT) and a pre-constructed Stability Knowledge Base (SKB) in response to electrical or mechanical disturbances in the system. Load shedding schemes by conventional frequency relays are generally a static control with fixed frequency settings. Based on Neural Networks, a power management system would be able to adapt to all real-time situations and provide a true dynamic load shedding control. This would allow the operator to optimize load preservation, reduce downtime for critical loads, and simulate/test the load shedding recommendations.

Figure 2: The load shedding model is also updated in the process and the entire system can be retested in a fraction of time it would take for conventional hardware based systems. Courtesy: ETAPThe Intelligent Load Shedding built into a model based solution offers yet another advantage; logic verification. Logic verification is a necessary step during Factory Acceptance Test (FAT) as well as Site Acceptance Test (SAT) performed during system commissioning. With an integrated model based solution, it is easy to capture operating data and evaluate results of Intelligent Load Shedding using dynamic stability.

This offers analytical and instantaneous visible confirmation that the load shedding logic will perform as expected without going through commissioning issues that are sometimes seen with hardware only based systems. Every scenario can be checked by using the live system data and a transient stability program. Since the model may be expanded to accommodate additional substations or manufacturing trains, the load shedding model is also updated in the process and the entire system can be retested in a fraction of time it would take for conventional hardware based systems (See Figure 2). 

Real-time power management

A standard power management system evaluates collected data in a non-electrical system environment without recognizing the interdependencies of equipment. Extending the power monitoring system by equipping it with an appropriate electrical system context, simulation modules, and playback routines will provide the system operator and engineer with a powerful new set of tools. Using these tools, the user can accurately predict the behavior of the electrical system in response to a variety of changes.

The playback of recorded message logs into the simulator-equipped monitoring system provides the operator with an invaluable means of exploring the effects of alternative actions during historical events. Simulation techniques readily extend into power system control and can be used to perform system automation and load shedding functions.

Finally, all of these capabilities should be included in one application with the flexibility and compatibility that allows plants to expand and upgrade as their needs grow. Real-time power management has become a plant manager’s secret weapon in assuring reliable plant operations 24/7. 

Shervin Shokooh, is Sr. Principal Electrical Engineer and Tanuj Khandelwal is Principal Electrical Engineer for ETAP.


<< First < Previous 1 2 Next > Last >>

VENTURA , Non-US/Not Applicable, Mexico, 12/12/13 07:37 PM:

It is a very useful information, thanks a lot
Congratulations.
SATYA , Non-US/Not Applicable, India, 12/22/13 10:49 AM:

Thanks for virtual metering information and its use. More details are welcome!
Can you provide more details on Lincoln Electric particularly the merits on which they have been selected.
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.