Project profile: Office building expansion

An addition to a customer training facility and employee office building included mechanical, electrical, and plumbing upgrades from exp.

04/25/2014


Project name: Learning Center Expansion

Project type: Addition to an existing building

Engineering Firm: exp

Building type: Office building; customer education center

Location: Verona, Wis.

Timeline: August 2010 – September 2011


Break room exterior. Courtesy: expBuilding details

This project was an addition to an existing customer training facility and employee office building.  The project included 2 floors of meeting rooms above a single floor of housing over 230 private offices.  Total project size was approximately 198,000 sq ft. Each private office received individual heating/cooling controls, occupancy sensors for lighting and variable air volume (VAV) operation reduction, and window monitors on all perimeter offices to disable mechanical supply to those rooms.  Fully integrated audio-visual (AV) controls were included in the training rooms to allow for interconnection of all lighting, projector operation, window shades and sky-fold room partitions.  Concourse lighting included fixtures designed by the lighting engineer to reflect and compliment concourse lighting in the existing portions of the building.

Project details

As the engineer of record on both this project, and the existing building, the engineering team was very familiar with the existing systems which allowed them to be instrumental in major revisions to the mechanical, electrical, and plumbing (MEP) systems. This included the following:

Electrical System: Two existing pad mounted transformers were in the way of the building expansion.  An existing 1250 kW building generator was also going to be encompassed in the center of the building with the new expansion.  Therefore, phased revision occurred by first locating a medium-voltage generator remotely on the site, and transferring down to 480 V within the building, allowing the generator to be removed while keeping the building fully backed up. The space made available from the removal of the generator allowed a dual transformer unit substation to be added as a replacement for the pad mounted transformers. This allowed the necessary space to be used for the building's construction. 

Meeting Level Concourse. Specialty fixtures were designed specifically for the expansion project. Courtesy: expMechanical: Four existing boilers providing hot water for perimeter radiation were removed and replaced as part of this project with high temperature multi-stack water-to-water heat pumps. Two 80,000 cfm Haakon custom rooftop units with economizers provide HVAC supply to the project. Three 200 hp geothermal pumps provided the means for connecting the building heating/cooling system to the vertical bore, closed loop, geothermal system. 

Plumbing: Relocated the domestic water supply due to the new building location with minimal downtime to keep building operational as close to 100% as possible.  Tied in emergency back up to the mechanical system in case of geothermal system failure. 

Fire Protection: Fully protected building. 

Lighting: High use of LED fixtures with a fully automated lighting control and dimming system.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.