Power supply product reliability tests exceed 10 years
Miyachi Unitek tests power supply products, some of which reportedly have been running continuously in 105° temperatures for over a decade.
Miyachi Unitek Corp., a manufacturer of welding equipment and laser processing systems, for decades has allegedly been assessing its power supply technologies for effectiveness, reliability and durability by putting its power supply products to the test, running them continuously in an extreme 105° environment to prove the design’s merit.
The testing occurs in an area in the factory referred to as “the torture room” for its high temperatures and constant clatter of weld heads. The torture room holds a variety of Miyachi’s resistance welding power supply units, including advanced capacitive discharge welders and full-featured AC resistance weld controls. Many units have been run continuously for 10 to 15 years, for a total of 15 to 25 million cycles.
The objective of the torture room is to understand how the products perform over time. Miyachi Unitek’s engineers determine what works well and what breaks down after years of use, and they use that information to improve the next generation of equipment.
The torture room also allows Miyachi Unitek to make better guarantees about their technologies’ performance. “When your sales person praises a system’s reliability, we know it’s the truth because of our tests,” said Kevin Gunning, director of quality, service and support. “Our thorough assessments allow us to confidently say our equipment is robust enough for the long haul.”
Miyachi Uniteck
- Edited by Amanda McLeman, Control Engineering, www.controleng.com
Case Study Database
Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.
These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.
Click here to visit the Case Study Database and upload your case study.
2012 Salary Survey
In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.
Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.