Power management system enhances emergency response

Case study: A super-tall building in the Middle East.

03/20/2014


A super-tall building in the Middle East contains three levels of enclosed underground parking, a hotel with multiple ballrooms and restaurants, several floors of offices, and multiple residential and observatory levels. Seven floors will host the building’s mechanical, electrical, plumbing (MEP), and fire protection equipment, which will use district-chilled water as a cooling source and feature three main chilled water pressure zones.

The building’s generator power systems will serve the following loads: fire pumps, fire transfer pumps, firefighter elevators, emergency evacuation elevators, emergency lighting system, safety and alarm systems, stair pressurization systems, lobby pressurization systems, public corridor exhaust systems, refuge floor pressurization systems, garage exhaust fans, partial building cooling load and associated equipment, and partial refuge floor cooling.

Three base building generators are located in each plant to support the life safety systems. Two plants are interconnected, providing reliable redundancy and backup for the building’s emergency power distribution system.

Like other super-tall buildings, there is a discrepancy between the code-required peak design demand and the building’s actual peak power usage. To take advantage of the additional power capacity already designed into the facility, the building’s power management system is programmed to accommodate a second and third tier of MEP systems that will enhance building response in the event of an emergency. This includes the building’s garage exhaust and corridor exhaust systems, life safety equipment supporting cooling devices, and refuge floor cooling.

During a power outage and after life safety Category 1 and legally required Category 2 systems were activated, then the third category is potentially energized. The power blocks in the third tier will be assessed based on each individual block’s power requirements and power availability. For example, the underground garage system was designed with 14 individual zones and allocated to the third tier. Upon receiving a signal simultaneously, all exhaust fans within this zone and adjacent zones will be activated. After necessary garage exhaust systems are online, the next power block in the third tier could also be activated if there is ample power capacity.

 

 


Suzan X. Sun-Yuan is a senior associate and lead mechanical engineer with Environmental Systems Design. She has experience with super-tall buildings, food labs, and central plant designs and upgrades. Mohsen Aghai is a senior associate and lead electrical engineer with Environmental Systems Design. He has experience with super-tall, mixed-used, commercial, and governmental buildings as well as hospitals and central plant designs and upgrades.

 



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.