Portland Community College Newberg Center

New construction: Portland Community College Newberg Center; Interface Engineering Inc.

08/09/2012


Combined Systems Infographic. Courtesy: Interface Engineering Inc. (Click to enlarge)Project name: Portland Community College Newberg Center

Location: Newberg, Ore.

Firm name: Interface Engineering Inc.

Project type, building type: New construction, school (college, university)

Project duration: 1.5 years

Project completion date: Aug. 31, 2007

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $194,000

Engineering challenges

The new Education Center at PCC Newberg will be the first higher education building in Oregon—and one of the first in the nation—to become net-zero and U.S. Green Building Council LEED Platinum certified. Achieving these lofty goals was the central challenge for the design team. Identifying the most cost-effective sustainable strategies suitable to the site while reducing energy use to 60%-70% less than a conventional code building without sacrificing comfort or building aesthetics was a daunting task.

Solutions

To achieve these lofty goals, Interface designed and implemented Structural insulated panels (SIPs) forming the exterior walls and roof provide a highly insulated building envelope, minimizing thermal breaks and helping to achieve more even temperatures throughout the Center. Courtesy: Interface Engineering Inc. (Click to enlarge)numerous sustainable features, including a highly insulated building envelope; passive heating/cooling systems; digital, addressable lighting control systems; and rooftop solar panels. The design team also improved insulation by incorporating structural insulations panels (SIP) for the roof and exterior walls. These provide less thermal breaks and more even temperatures throughout the facility, reducing heating and cooling loads. A majority of the building is cooled by natural ventilation only with a combination of exterior louvers that bring fresh air in, stacks along the building’s spine that push hot air out, and ceiling fans throughout the facility. When outside temperatures are below 55 F, a heat recovery ventilation (HRV) system kicks in. It brings in fresh outside air and warms it with heat recovery wheels that recover most of the building heat normally rejected to the outside. A radiant slab, with 90-F water running through it, heats the building to 68 F. Daylighting controls are in the classroom, administrative, multipurpose, and common spaces. Combined with the skylights and windows, the design effectively Skylights and daylighting controls maximize the use of natural daylight and reduce energy consumption by 15%. The skylights are equipped with motorized louvers that track the sun, allowing the appropriate amount of daylight into the classroom and can be closed to accommodate audiovisual presentations. Courtesy: Interface Engineering Inc. (Click to enlarge)maximizes the use of natural daylight while also reducing required electrical lighting and lowering the energy use by 15%. The skylights are equipped with motorized louvers that track the sun, allowing the appropriate amount of daylight into the room.

Automatic dampers and exterior louvers provide natural ventilation to cool the common area with assistance from large fans, drawing heat out through stacks along the building’s spine. When outside temperatures are below 55 F, the heat recovery system activates while 90-F water coursing through radiant floor slab heats the building to 68 F. Courtesy: Interface Engineering Inc. (Click to enlarge)Classrooms have manual controls to drive the louvers to a closed position to accommodate audiovisual presentations. Additional energy reduction features include: domestic hot water heat pump, a significant efficiency improvement over a standard electric hot water heater; solar preheating of ventilation air to reduce heating energy; low-flow bathroom fixtures and hand dryers that use one-tenth of the energy of paper towels; laptop computers in the computer lab space to reduce plug loads; high efficiency T5 bulbs for all interior light fixtures; improved glazing performance; and overall water use reduced by 49.2% through the use of low-flow faucets and toilets.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.