You’ve see the equations, but have you thought about how those elements work together? Part 4: Feed forward

06/10/2014


In the first three blog posts (see Part 1, Part 2, and Part 3) we covered the basics of PID math. We started with the basic proportional-only controller and worked in the integral and derivative components. Well before get too far, let’s review the proportional-only controller:

u(t) = Kpe(t)

u(t)
is the output of the controller at the end of the scan. If the output of the controller is a valve, then the output is the valve position that the controller is requesting after it has seen the inputs.

Kpe(t) is the proportional component, the P in PID. e(t), usually called “error,” is simply the difference between the setpoint and the process variable. Kp gain is a factor that is multiplied by the error to give you the new output—the new valve position. It’s that simple. The error at that instant of the scan is calculated and the new output is calculated.

The pseudo code that we discussed was:

Error = Setpoint – ProcessValue
Output = K * Error

With this code the output changes immediately after the error changes. I like to use a cruise control on a car as an example. As soon as the car starts to slow down as it starts to climb a hill, the change in error (speed) immediately causes the output to change.

But what if you know that the speed is about to slow down? What if you can see the hill coming? That’s where feed forward comes in. The first step is detecting a condition that will affect the process value. This can be an upstream flow rate that affects a level controller, a pressure change that affects a flow controller or any number of variables. The important thing is that the feed forward signal has to have a predictable affect on the controlled variable.

The math behind it is conceptually pretty simple. The feed forward signal is multiplied by a gain and then added directly to the output:

Error = Setpoint – ProcessValue
Output = K * Error + FeedForward * Kf

That way as long as the feed forward signal doesn’t change, the controller is not affected. But, a change in the feed forward signal immediately makes a proportional type shift in the output.

The math does get more complicated when the time that it takes for the signal to affect the process value has to be considered. In that case a lead or lag calculation must be done to slow down or speed up the feed forward signal. But that’s a topic for the next post.

This post was written by Scott Hayes. Scott is a senior engineer at MAVERICK Technologies, a leading automation solutions provider offering industrial automation, strategic manufacturing, and enterprise integration services for the process industries. MAVERICK delivers expertise and consulting in a wide variety of areas including industrial automation controls, distributed control systems, manufacturing execution systems, operational strategy, business process optimization and more. 



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.