Medium-voltage fused switchgear example

This example illustrates the results from an MV fused switchgear feeding a pad-mounted or dry-type transformer.

09/25/2013


Figure 1 illustrates medium-voltage (MV) fused switchgear feeding either a pad-mounted or a dry-type transformer. The NEC does not require the secondary overcurrent device to be close coupled. Where the primary and secondary overcurrent devices are located remotely, consideration must be given to protection of both feeder conductors between the transformer terminals and the terminals of the overcurrent devices.

Figure 1: The single line diagram and time-current curves illustrate a typical transformer protection scheme using primary MV fuses and low-voltage secondary breaker protection. Courtesy: JBA Consulting Engineers

Figure 1: The single line diagram and time-current curves illustrate a typical transformer protection scheme using primary MV fuses and low-voltage secondary breaker protection. Courtesy: JBA Consulting EngineersThe transformer circuit consists of:

  • Originating source: Customer-owned 12.47 kV metal fused switchgear
  • Primary fuse: 100E
  • Secondary circuit breaker: 2000 amp
  • Primary cable: #2-15 kV EPR MV 105 cables
  • Secondary cables: 9 sets of underground cables of 500 KCMIL per phase
  • Transformer rating: 1500 kVA, 12.47 kV D to 480 VU, Z=5.75% 

The following protective features are illustrated:

  • The 100E fuse curve is to the right of the transformer 12 times FLA inrush current point and to the left of the cable damage curve.
  • For a transformer of 6% impedance or less, the NEC requires both primary and secondary protection. The primary fuse must not be larger than 300% of primary FLA and the secondary 480 V overcurrent device must not be larger than 125% of secondary FLA.
    • Primary: The continuous rating of a 100E fuse is 130 amps; the FLA of a 1500 kVA transformer is 70 amps, which is 180%—well within the NEC requirements.
    • Secondary: A 2000 amp main breaker is 111% of the transformer FLA.
  • Both the primary and secondary cable damage curves are above the maximum fault current at 0.01 s.

Leslie Fernandez is senior project engineer, electrical at JBA Consulting Engineers. He has more than 28 years of engineering and design and field experience that includes MV distribution systems for military, mining, tunneling, food manufacturing, power production facilities, high-rise facilities, and casino resort complexes. 



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.