Machine Safety: For a safe machine, I’ll just install a small safety PLC

To mitigate a machine hazard, might it work to install one small safety PLC, then slave the other distributed standard PLCs to the safety PLC? Would that avoid the need for a risk assessment for the whole machine and create compliance? The answer is no. At least seven steps follow a risk assessment.

06/17/2013


ABB D45 Pluto Safety PLC, like all PLCs, must be appropriately applied. Safety PLCs are not a substitute for a risk assessment.“Have you heard the one about a manufacturing plant discussing options on how to modify an existing machine’s architecture and how to mitigate a hazard? They’re actually evaluating someone’s plan to install one small safety PLC for this hazard and to slave the other distributed standard PLCs to the safety PLC. Therefore, we won’t have to do a risk assessment of the whole machine and we’ll be in compliance”! 

This is not a joke! I’ve seen this story unfold multiple times over the past 10 years.

An applications approach as described above does not attempt to identify all hazards and mitigation plans on a machine. And, I would argue that the machine is completely unsafe. A complete solution following a risk assessment could involve:

  1. Redundant components, sensors, actuators, etc.
  2. Safety certified components to different Cat levels
  3. Redundant cabling
  4. Additional state monitoring
  5. Safety certified software
  6. Validation & documentation
  7. An updated risk assessment
  8. ... and more. 

It is commonly understood today that a risk assessment forms the foundation for design / modification. All hazards need to be identified and mitigated on a machine one by one to acceptable levels. Okay, there are some folks out there that simply require a machine (and all of its hazards) to be mitigated to meet one Category, such as Cat 2 or Cat 3. When this happens a risk assessment is still required and many of the hazard mitigation solutions could well be over-engineered with a costly investment. 

Is there any valid excuse for not performing a risk assessment today? No! Machine standards and regulations do not provide conditions on how to avoid completing the required risk assessment for each machine. And, simply slaving existing standard PLCs on a machine to a safety PLC does not meet the requirements for the safety related parts of a control system (SRP/CS). 

Or more simply said, it does not meet the requirements for the safety-related circuits! 

Has this presented you with any new perspectives? Add your comments or thoughts to the discussion by submitting your ideas, experiences, and challenges in the comments section below.

J.B. Titus, CFSE

Related articles:

Machine safety risk level assessment priority: Possibility, severity, or frequency?

Machine Safety: functional safety and the steps to be compliant in the US.           

Machine Safety – OSHA’s Top 10 Violations for 2012

Machine Safety: Is OSHA okay with my 'acceptable' risk mitigation? 

Contact: http://www.jbtitus.com for “Solutions for Machine Safety”.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.