        A building's life safety systems constantly stand ready to protect the structure and its occupants from catastrophe; their successful operation can mean the difference between a nuisance fire and a catastrophic event.

         

        A building's HVAC system generally penetrates every space of a building. Without effective life safety systems in place, these pathways can carry fire, smoke, and toxic gases throughout the building, causing property damage, injuries resulting from smoke inhalation, and even death.

         

        The smoke and fire components of the HVAC system, particularly the fire and smoke dampers, are therefore crucial components of the fire protection design.

         

        OPERATIONAL REQUIREMENTS

        To ensure that life safety systems serve their intended purpose, periodic inspection and testing are not only essential, they are mandatory.

         

        The International Codes and the NFPA 101 Life Safety Code are specific about the frequency and requirements of periodic inspection and testing. Virtually every jurisdiction in the country has adopted these requirements, or some variation of them. The Authority Having Jurisdiction (AHJ) typically requires the building owner to test all life safety dampers within 1 year of the acceptance test being conducted and/or the building being occupied. Figure 1 identifies standards and guidelines that specify periodic inspection and testing requirements and are adopted by reference in a code by a jurisdiction.

         

        Within 1 year after acceptance testing in new construction or after remodeling, a typical mandated periodic inspection and testing schedule can include the following:

         

        • Every 6 months—Cycle test (open and close) all motorized fire and smoke dampers, and test all dedicated smoke control systems

        • Every 12 months—Test all nondedicated smoke control systems

        • Every 2 years—Visually inspect all fire dampers, ceiling radiation dampers, smoke dampers, and combination fire/smoke dampers

        • Every 4 years—Manually operate (open and close) all fusible link-operated fire dampers and ceiling radiation dampers.

        (Note: Routine maintenance is not typically required by manufacturers unless a periodic inspection or test identifies the need for maintenance.)

         

        Inspection and testing should be performed by qualified personnel who have expertise in fire protection or mechanical engineering, or are certified to inspect life safety dampers or smoke control systems in accordance with an ANSI third-party accreditation program.

         

        INSPECTION PROCEDURES

        Inspectors typically observe components in operation to verify that the equipment or construction is installed properly and that it is appropriate for the system design. The specific tests, and the most efficient order of testing, depend on the:

         

        • Type of system

        • Number of systems

        • Progress of new construction or remodeling

        • Relationship between building systems and specific tenant work

        • Degree of interaction between other systems

        • Complexity of the controls sequence

        • Impact of system failures on fire or life safety and other factors.

        Determining the procedures for periodic inspection and testing is a critical component of the overall process. One option is to locate an existing inspection procedure that has already been approved by the AHJ. If an existing procedure exists, it must be followed implicitly. If a procedure cannot be located or does not exist, one must be developed by a qualified professional whose credentials are acceptable to the AHJ. Some AHJs provide the testing and inspection procedure.

         

        Establishing and approving an inspection procedure involves research, including:

         

        • Obtaining any existing inspection documents, including any previous inspections or testing reports

        • Locating relevant information from the overall building design, including design objectives and construction documents

        • Determining the specifications and location of every life safety damper that is installed in the building.

        Once the inspection and testing have been completed, meticulous records must be maintained. Records verify that the proper inspection and testing have been completed and that the building complies with local inspection requirements. These records should contain key information about each damper, such as make or model number, ratings, date installed, observations made during periodic inspection and testing, and any corrective actions taken. Whether handwritten or in electronic format, the records of all inspections and tests must be maintained on-site for at least 3 years, as stated in the codes.

         

        National Fire Protection Association (NFPA)

         

        Figure 1: Relevant standards and guidelines that specify periodic inspection and testing of life safety systems and their components.

        NFPA 90A

        Standard for the Installation of Air-Conditioning and Ventilating Systems

        NFPA 90B

        Standard for the Installation of Warm Air Heating and Air-Conditioning Systems

        NFPA 92A

        Standard for Smoke Control Systems Utilizing Barriers and Pressure Differences

        NFPA 92B

        Standard for Smoke Management Systems in Malls, Atria, and Large Spaces

        NFPA 80

        Standard for Fire Doors and Other Opening Protectives

        NFPA 105

        Standard for the Installation of Smoke Door Assemblies and Other Opening Protectives

        American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (ASHRAE)

        ASHRAE Guideline 5-1994

        Commissioning of Smoke Management Systems

        ASHRAE Guideline 1-1996

        The HVAC Commissioning Process

        Underwriters Laboratories Inc. (UL)

        UL 555

        Standard for Fire Dampers

        UL 555S

        Standard for Smoke Dampers

        UL 555C

        Standard for Ceiling Dampers

        Marking and

        Dampers for Fire Barrier and Smoke Applications & Ceiling Dampers Application Guide

        Air Movement and Control Association (AMCA) International, Inc.

        AMCA Publication 502

        Damper Application Manual for Heating, Ventilating, and Air Conditioning

        AMCA Publication 503

        Fire, Ceiling (Radiation), Smoke and Fire/Smoke Dampers Application Manual Inspection, Testing, and Maintenance Guidelines

        Other

        Individual manufacturers' Web sites and technical support hotlines

         

         

        CONCLUSION

        Life safety systems are in place to ensure that disastrous scenarios do not occur; however, these systems are worthless if they don't function as intended in an emergency. Therefore, conducting periodic inspections and testing of life safety dampers and other life safety systems is vital to protecting both property and human lives.

         



        No comments
        The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
        The Product of the Year program recognizes products newly released in the manufacturing industries.
        The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
        World-class maintenance: The three keys to success - Deploy people, process and technology; 2016 Lubrication Guide; Why hydraulic systems get hot
        Your leaks start here: Take a disciplined approach with your hydraulic system; U.S. presence at Hannover Messe a rousing success
        Hannover Messe 2016: Taking hold of the future - Partner Country status spotlights U.S. manufacturing; Honoring manufacturing excellence: The 2015 Product of the Year Winners
        The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
        Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
        Digital oilfields: Integrated HMI/SCADA systems enable smarter data acquisition; Real-world impact of simulation; Electric actuator technology prospers in production fields
        Improving flowmeter calibration; Selecting flowmeters for natural gas; Case study: Streamlining assembly systems using PC-based control; CLPM: Improving process efficiency, throughput
        Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
        Warehouse winter comfort: The HTHV solution; Cooling with natural gas; Plastics industry booming

        Annual Salary Survey

        Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

        There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

        But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

        Read more: 2015 Salary Survey

        Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
        The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
        The Society for Maintenance and Reliability Professionals an organization devoted...
        Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
        IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
        Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
        The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
        This article collection contains several articles on the vital role that compressed air plays in manufacturing plants.
        This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
        This article collection contains several articles on strategic maintenance and understanding all the parts of your plant.
        click me