LEED-designed university performing arts center, academic building completed

The $73 million project for Soka University in Orange County posed unique construction challenges and incorporated sustainable building methods to seek LEED Gold Certification

12/07/2010


McCarthy Building Companies, Inc. recently completed construction of Soka University of America’s new Performing Arts Center and Academic Building project, located on 1.9 acres of the Soka University campus. The new Performing Arts Center is designated to become a venue in South Orange County for concerts, theater productions, lectures and assemblies, enhancing Soka University’s role as a cultural center and community gathering place.

McCarthy served as general contractor for the $73 million project that began in December 2008. The project included construction of a three-level, 47,836-square-foot Performing Arts Center housing a reception lobby; various support spaces and a 1,200 seat auditorium. McCarthy also built a 48,974-sq-ft Academic Building located next to and providing support for the Performing Arts Center. The new four-level academic building houses 11 classrooms, 29 faculty offices, a 150-seat black box theater, four dressing rooms, a rehearsal/dance studio, musician warm-up spaces and other support areas. The project’s design and construction team is pursuing United States Green Building Council’s (USGBC) Leadership in Energy and Environmental Design (LEED) Gold Certification for the buildings.

Because of sloping terrain, both new structures presented design and construction challenges. The Performing Arts Center structure … is cast-in-place concrete with 65-foot tall radius shear walls. McCarthy performed all of the structural concrete work for the project, providing the formwork, planning and review process to ensure a successful completion on a very challenging structure.

It should be noted that the Performing Arts Center is designed with four massive roof trusses that span the width of the performance hall. At 16.5 feet tall and 114 feet wide, these trusses were so large that they had to be delivered at night with a special California Highway Patrol escort.

Designed by Zimmer Gunsul Frasca Architects LLP of Los Angeles, both structures were built with a combination of a structural concrete and structural steel frame. Building exteriors feature smooth plaster walls, travertine stone bands, aluminum curtain walls and clear glass glazing.  The Performing Arts Center features a green roof and solar panels, while the Academic Building has a clay tile roof to match the existing campus.

To successfully address the LEED aspects of the project, the design and construction team employed 15 LEED accredited professionals, and McCarthy used sustainable construction methods throughout the project. These included: recycling approximately 75 percent of construction waste; maintaining proper indoor air quality; utilizing local labor and ensuring that the subcontractors install the specified “green” materials.

Likewise, the design of these structures incorporates numerous sustainable and energy efficiency solutions. The academic building features operable windows and displacement ventilation. The Performing Arts Center’s “green roof” and sunshade structure surrounding the lobby uses photovoltaic (solar) panels, and a bioswale will help manage storm water runoff. McCarthy used building materials made from recycled content and that are locally extracted, processed and regionally manufactured. Additionally, Forest Stewardship Council (FSC) certified wood and low emitting adhesives, sealants, paints, carpets and composite wood products were incorporated in both structures.

The project team achieved 33 percent below Title 24 requirements for energy efficiency by utilizing the LEED Energy Cost Budget methodology. This energy efficiency rating was achieved by incorporating:

  1. displacement ventilation to reduce the amount of space being conditioned
  2. photovoltaic panels
  3. green roofs
  4. sensor lights
  5. operable windows for views/climate control
  6. white roofs
  7. instantaneous gas water heaters for the dressing room showers and theater support areas
  8. automatic daylight lighting controls in all classrooms and theater lobbies

Working in accordance with LEED 2.2, McCarthy is in the process of submitting the construction documentation needed for official certification.

Other project team members included Program Manager R.W. Buck and Associates of Rancho Santa Margarita; JAMA of Los Angeles, structural engineer; RBF of Irvine, civil engineer; Syska of Los Angeles, electrical and mechanical engineer; and SWA of Laguna Beach, landscape architect.



The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
Doubling down on digital manufacturing; Data driving predictive maintenance; Electric motors and generators; Rewarding operational improvement
2017 Lubrication Guide; Software tools; Microgrids and energy strategies; Use robots effectively
Prescriptive maintenance; Hannover Messe 2017 recap; Reduce welding errors
The cloud, mobility, and remote operations; SCADA and contextual mobility; Custom UPS empowering a secure pipeline
Infrastructure for natural gas expansion; Artificial lift methods; Disruptive technology and fugitive gas emissions
Mobility as the means to offshore innovation; Preventing another Deepwater Horizon; ROVs as subsea robots; SCADA and the radio spectrum
Research team developing Tesla coil designs; Implementing wireless process sensing
Commissioning electrical systems; Designing emergency and standby generator systems; Paralleling switchgear generator systems
Natural gas engines; New applications for fuel cells; Large engines become more efficient; Extending boiler life

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
The maintenance journey has been a long, slow trek for most manufacturers and has gone from preventive maintenance to predictive maintenance.
Featured articles highlight technologies that enable the Industrial Internet of Things, IIoT-related products and strategies to get data more easily to the user.
This digital report will explore several aspects of how IIoT will transform manufacturing in the coming years.
Maintenance Manager; California Oils Corp.
Associate, Electrical Engineering; Wood Harbinger
Control Systems Engineer; Robert Bosch Corp.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me