Leak detection: Technology catches up to theory

Making sure all the oil that goes in a pipeline comes out the other end is harder than it sounds.

10/01/2009


 

Comparing the schematics of the three systems, it is possible to see how the technology evolved over 40+ years of operation.

Comparing the schematics of the three systems, it is possible to see how the technology evolved over 40+ years of operation.

One of the world’s largest steam generating plants is located on an island in a major U.S. metro area. The plant distributes steam for heating and air conditioning throughout its local service area, but has to pull fuel for its oil-fired boilers from a tank farm approximately two miles away. To complicate matters, 85% of that distance is through a tunnel under a heavily traveled river. Given local environmental concerns, that fuel delivery system has to be closely monitored to make sure no oil is being lost in between.

The plant purchases No. 6 fuel oil from a tank farm across the river, so oil has to be pumped through a pressure-controlled pipeline that runs through a tunnel under the river, at a maximum flow rate of 300 gpm. Stringent requirements for the leak detection systems on the pipeline require that the system be able to detect any leak in excess of 60 gallons in 20 minutes, which effectively amounts to 1% of maximum flow.

Oil in = oil out?

The material balance method of leak detection is simple: quantity in– quantity out = size of leak. Simple, yes, but implementation is more complicated. The system must manage temperature and pressure differentials and time lag. If the system is based on volume, temperature compensation is especially challenging when different segments of the pipeline run at different temperatures. The oil temperature can change as it passes from the tank to underground to under water. Because multiple measurement devices are involved, measurement error accumulates, with negative consequences for overall accuracy.

In the early 1990s, the utility company assessed its leak-detection system and found it lacking. This prompted a 15-year effort to monitor, upgrade, and optimize the system so that it not only met but exceeded requirements.

The basic concept of the original system was straightforward and used paddlewheel sensors on each end of the pipeline. A comparator device developed in-house collected pulse data from the sensors via dedicated telephone lines, compared the inlet pulse rate to the outlet pulse rate, and calculated the difference in flow.

Unfortunately, the paddlewheels never were able to generate data with required accuracy. Variations in temperature and density made the errors worse, and the dedicated phone lines failed frequently. Although no significant leaks occurred over the 30 years the system operated, the company recognized the risk, and took steps to correct the problem.

Improved system, version 1

In the mid-1990s, the utility contracted system integrator Expert Systems Group to redesign and implement a system that would meet their specifications for sensitivity, accuracy, and reliability.

The sensing technology was changed from paddlewheels to Micro Motion D300 Coriolis mass flowmeters. Mass measurement is not affected by pressure and temperature variation, so an improvement in accuracy was realized immediately. Communications and processing were handled by two PCs connected by fiber optics. The PCs ran the Microsoft Windows 98 operating system, a custom data analysis program, and ProLink, a software tool from Emerson that retrieves process data from the sensors. As shown in the diagram, after local processing, the inlet PC sent data over TCP/IP to the outlet PC, where it performed comparison processing and leak detection analysis.

Although mass data is more stable, the leak rate is specified as a volume, so Al Shoop, proprietor of Expert Systems Group, had to make a conversion using mass and density readings measured by the D300 meters. By taking the direct density measurement from each end of the pipeline and assuming a straight-line temperature gradient from one end of the pipeline to the other, Shoop was able to generate temperature-corrected data that improved accuracy; other optimizations reduced the average system discrepancy to less than one gpm.

Even so, the enhanced system was still not ideal. The bulky D300 meters were hard to fit into the existing pipeline. Non-optimal positioning caused occasional bubbles in the line, which resulted in spikes and false alarms. The Windows operating system did not have real-time capability and its timer did not produce exact two-second data samples. Moreover, the PLCs of the time did not have sufficient computational and memory capacity to do the job. Still, the system ran flawlessly for 10 years.

Not only had PLC capabilities evolved during this time period, so too had the Coriolis sensor. The Elite Coriolis meter was five-times more accurate than the D300. Modbus-to-TCP/IP converters on each meter meant that no computers were needed because newer PLCs had no trouble processing and comparing the raw data.

The new equipment was installed beside the existing system, and immediate improvements were seen. “As a result of the increased accuracy and the preprocessing performed by the meter, for example, onboard data smoothing and noise reduction, the standard metering error dropped from 20–30 gallons in 20 minutes to less than 2 gallons in 20 minutes,” says Shoop. With decreased metering error, there is no danger of false alarms caused by spikes. The previous problem with bubble formation was addressed by adding S-bends to the pipeline, thus providing space to install the sensors in their optimal orientation.

Shoop knew the system was a success when one day he noticed a slight increase in the standard metering error. It was not reported because it was below the alarm limit, but a few days later, a technician saw sheen on the ground. The glint proved to be a small puddle of oil from a pinhole leak. Although no trip was initiated, the system had successfully detected the event.


Author Information

Marsha Yon is Micro Motion business development manager for liquid custody transfer. Richard Leonard is executive VP and CFO of Pro-Tech Solutions, Ltd. Alvin Shoop is president of Expert Systems Group.




No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.