Kroger Data Center

Existing building retrofit: Kroger Data Center; PEDCO E+A Services Inc.

08/09/2012


The chiller plant installed.Project name: Kroger Data Center

Location: Cincinnati, Ohio

Firm name: PEDCO E+A Services Inc.

Project type, building type: Existing building retrofit, data center

Project duration: 1.3 years

Project completion date: May 29, 2007

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $288,000

Engineering challenges

The Kroger Company (Kroger), one of the nation’s largest retail grocery chains, operates data centers across the United States. One such data center, located in Cincinnati, Ohio, where Kroger is headquartered, was in need of an infrastructure upgrade. The existing facility houses two distinct data centers known as the North Data Room and South Data Room.

Half of the chiller plant being lifted into place.The original building, constructed in 1978, comprised the 7,500-sq-ft North Data Room and support areas such as offices, UPS and battery rooms, utility spaces, and a generator room. An expansion project in 2006 added the 6,400-sq-ft South Data Room and associated support spaces. That project also included a design for upgrading the North Data Room HVAC system, which was to be executed as a second phase. It mimicked the new South Data Room with a multiple glycol loop system with roof-mounted dry coolers, but the North Data Room system was never installed. As Kroger developed a new IT strategy, the strategy for the North Data Room’s utilization also changed.

Because the North Data Room was never renovated from the previous project, the design team was challenged to provide a robust design that was more energy efficient. Cooling capacity criteria for the North Data Room was 100W/sq ft, which converted to 215 tons. An allowance of 25 tons for future in-rack cooling in either Data Room brought desired capacity to 240 tons. Against the backdrop of reduced energy consumption, the redundancy requirements of a Tier III data center needed to be considered. Located in the Midwest, renown for summer humidity, this data center’s options did not include an airside economizer alternative. Space temperature and humidity criteria (75 F, 50% RH), however, did allow for warmer conditions than had previously been considered normal.

Solutions

Duke Energy awarded Kroger Company a $130,000 Smart $aver Incentive check. Pictured from left to right are Mark Smekrud (Kroger Senior Project Engineer), Tracy MacDonald (Kroger Corporate Facilities Engineer), Deanna Bowden (Duke Energy Account Manager),When comparing options for the cooling plant, the previously designed multiple glycol loop system was utilized as the baseline. Ultimately, a concept using modular chillers was developed for two main reasons. First, chilled water provides greater flexibility in terms of adding in-rack cooling, which Kroger anticipates in the future. Second, the renovated North Data Room was anticipated to be loaded over an extended period of time, so there would seem to be an inherent advantage to providing capacity on an incremental basis just ahead of its need.

As PEDCO looked further into the modular chiller approach, the prospect of placing free-cooling modules upstream of compressorized modules was immediately appealing. Depending on ambient conditions, this would enable the use of at least partial cooling of the return chilled water stream without compressors, therefore using less energy to cool the chilled water to the desired supply temperature. This contrasted to the more conventional approach of using either free cooling or compressorized cooling, but not a combination, at any given time. Based on available standard sizes, 30-ton modules were selected to be the design basis. An added advantage of this concept was the ability to achieve N+1 redundancy of chiller capacity with only one module. Thus, the desired redundancy was achieved with only an additional 30 tons of capacity. Had a more conventional approach of two 120-ton air-cooled chillers been used, N+1 redundancy would have required the addition of 120 tons of capacity.

The final design of the chiller assembly included nine 30-ton compressorized modules and eight 30-ton free cooling modules. The ninth compressorized module provided the desired N+1 redundancy. That redundancy was not required for the free coolers, since the compressorized modules served that function. Computer models were created for this concept and for one utilizing glycol computer room cooling equipment. The models predicted the chilled water/free cooling system would consume 92% as much energy as the glycol approach. A cost comparison of the two alternatives indicated first cost for the chilled water approach would be approximately 30% lower. Maintenance costs and system life expectancy were deemed to be roughly equivalent between the two alternatives. It thus became apparent that a modular chilled water system was the approach to pursue for this project. The potential for significant energy savings prompted Kroger and PEDCO to contact the energy rebate representative from Duke Energy. The project was submitted through Duke’s Smart$aver Custom Incentive program, which resulted in Kroger receiving a $130,000 rebate check. Further, Kroger measured a savings of over $100,000 in utility bills during the first year of operation.

Additional Information 

View a presentation from PEDCO on the project



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.