If you think nuclear plant construction here is slow, Iran’s pace is glacial but after 35 years has finally come full term.


Iran has finally entered the atomic age, publically at least, as its one and only more-or-less finished nuclear power plant connects to the grid. The Bushehr (strictly peaceful) nuclear power plant is about 750 miles south of Tehran on the Persian Gulf, and is a 1,000 MW, (presently) single unit facility. Originally the plan was to have four units on this site, but as of now the plan has been pulled back to three, which may still be wishful thinking. There have been many premature reports that it is just about ready to go online any minute now, but this time it looks like it’s legit, running at low power and ramping up to hit 40% of total output by next week.

   Construction on this plant began in 1975 led by Siemens and a group of other German companies back when the Shah was still in power. (Raise your hand if you’re old enough to remember the Shah.) Apparently he was looking ahead to the time when oil would be too expensive for use as a fuel, and had plans to build 23,000 MW of nuclear generating capacity. Things ground to a halt after the revolution in 1979. Siemens and its syndicate abandoned the project leaving two units under construction. Things sat quietly corroding in the hot salty air by the gulf, with occasional bombing damage during the Iran-Iraq war in the mid-1980s.

   The Iranians brought in a Russian group to start construction again in the mid-1990s, and work started slowly with the expectation of completion by 2001. The site quickly became a hodge-podge of equipment as Atomstroyexport decided to use its reactor design along with some of the remaining Siemens equipment. The international community in general wasn’t excited about the prospects, and Russia was having its own internal problems during that time, so it all got pretty complicated politically. Still, negotiations continued, and by 2005, the U.S. withdrew its official opposition to the project and things were stable enough with the Russians for things to begin again in earnest. Now it’s ready to go.

   While I think nuclear power is a pretty good idea in most situations, this one seems a little scary. Let’s accept for the sake of argument that this facility does not offer support for Iran’s desire to create weapons-grade nuclear material. We’ll also assume that Russian operators and trainers are on site to keep things on an even keel, running a Soviet-era reactor design. It still gives me the heebie geebies. This is just one more reason I’m glad I don’t live over there.

No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
A cool solution: Collaboration, chemistry leads to foundry coat product development; See the 2015 Product of the Year Finalists
Raising the standard: What's new with NFPA 70E; A global view of manufacturing; Maintenance data; Fit bearings properly
Sister act: Building on their father's legacy, a new generation moves Bales Metal Surface Solutions forward; Meet the 2015 Engineering Leaders Under 40
Cyber security cost-efficient for industrial control systems; Extracting full value from operational data; Managing cyber security risks
Drilling for Big Data: Managing the flow of information; Big data drilldown series: Challenge and opportunity; OT to IT: Creating a circle of improvement; Industry loses best workers, again
Pipeline vulnerabilities? Securing hydrocarbon transit; Predictive analytics hit the mainstream; Dirty pipelines decrease flow, production—pig your line; Ensuring pipeline physical and cyber security
Upgrading secondary control systems; Keeping enclosures conditioned; Diagnostics increase equipment uptime; Mechatronics simplifies machine design
Designing positive-energy buildings; Ensuring power quality; Complying with NFPA 110; Minimizing arc flash hazards
Building high availability into industrial computers; Of key metrics and myth busting; The truth about five common VFD myths

Annual Salary Survey

After almost a decade of uncertainty, the confidence of plant floor managers is soaring. Even with a number of challenges and while implementing new technologies, there is a renewed sense of optimism among plant managers about their business and their future.

The respondents to the 2014 Plant Engineering Salary Survey come from throughout the U.S. and serve a variety of industries, but they are uniform in their optimism about manufacturing. This year’s survey found 79% consider manufacturing a secure career. That’s up from 75% in 2013 and significantly higher than the 63% figure when Plant Engineering first started asking that question a decade ago.

Read more: 2014 Salary Survey: Confidence rises amid the challenges

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.