SEARCH Archives
Loading
Sponsored by:

High on the energy hog

An example of a carefully planned successful energy and cost savings program was carried out by the Harley Davidson Motor Co. during the late 1990s.

By Peter D. Zak, PE, Graef-USA Inc., Milwaukee

11/19/2012


The system at the Harley Davidson Headquarters would ultimately be made up of three 250-ton chillers, variable speed chilled water, condenser water, and hot water pumping systems. Courtesy: Graef-USA Inc.An example of a carefully planned successful energy and cost savings program was carried out by the Harley Davidson Motor Co. during the late 1990s. At that time the corporate facilities occupied several floors on the original historic site. The site was comprised of several buildings with a total floor area of approximately 300,000 sq ft; offices and support areas occupied about 40,000 sq ft. These areas had been upgraded to a low-temperature variable air volume (VAV) system with partial ice storage for peak shaving. The remaining facilities were used for warehouse and storage areas. As the need for additional corporate space and training facilities was rapidly increasing, Harley realized the potential of the existing facilities and set about preparing a master plan to convert the facility to meet the future needs.

There were three fundamental requirements: the first was that the historical significance of the site had to be preserved. Second, the facilities had to be flexible with respect to function and operating schedules. Third, the HVAC system had to be designed to respond to a variety of operating conditions such as conference centers, corporate office, archival storage, and engine testing laboratories. Another requirement was that the HVAC system had to be designed in a manner such that it could be easily expanded to meet the new building loads throughout the multiyear project. Also, the firm wanted to maximize energy efficiency and minimize operating costs.

The plan built off the existing ice plant design, which served the current corporate facility. This allowed a majority of the main piping to be salvaged. The warehouse facility was converted to include a conference center, two floors of training facilities for dealers, a printing facility, and office space. The system selected would ultimately be made up of three 250-ton chillers, variable speed chilled water, condenser water, and hot water pumping systems. A water side economizer system was selected, which also allowed pre-cooling of the return chilled water during intermediate months. This was driven by limitations imposed on air side economizers, which prevented large louvers on the building face with respect to the historical significance. Changing the cooling tower fill surface area and increasing the fan size resulted in a net savings compared to air side economizers. Precooling the return chilled water temperature resulted in operating cost savings for some additional piping and valves.

The remaining floors of the original corporate facility were converted to office space with VAV systems. The ice storage system was upgraded to provide approximately 2200 tons/hr of cooling. Ice building was accomplished by a 250-ton air cooled chiller; this avoided the costs of additional chillers. The converted warehouse and office cooling plants were interconnected in the final phase. This allowed the ice to work with the water side economizers and the water cooled chillers, which have a higher operating efficiency. Minimum additional costs were incurred because piping was extended through a tunnel that connected both complexes during one of the earlier phases. The interconnection created an operational savings due to the diversity of the entire complex, which ultimately deferred the purchase of an additional 250-ton chiller. The initial added cost to install the pipe in the tunnel was a fraction of the cost of an additional chiller and tower; the end result provided an overall demand reduction of approximately 300 kW per month and an annual energy reduction of approximately 500,000 kWh per year.


Peter D. Zak is a principal with Graef-USA Inc., where he manages the MEP group. He is a member of NCEES and is on the editorial advisory board of Consulting-Specifying Engineer. He was an adjunct assistant professor at the Milwaukee School of Engineering for 20 years and is a registered professional engineer in 24 states.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. The 2012 Top Plant winners have been named.
In 2012, Plant Engineering's Product of the Year program will celebrated its 25th anniversary. Read about the 2012 winners and nominate for 2013.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2012 Leaders here.
Investment in excellence: One plant's improved productivity and quality was repaid when their company expanded the facility
Strategic uptime, Increased capacity goes right to the bottom line
2013 Forecast Issue: A shift in manufacturing
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Alarm management tips, Power management, Building automation
Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Attacking Energy Costs: Strategies for showing financial return on energy management investments

2012 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results


Poll of the Week

What category most helps you select new products?
Recommendation from colleagues
Product of the Year winners
Supplier information
Trade show visit


Click Here for Poll Archives
Sponsored by:

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.