Green field oil seed processing facility

Integrated project delivery profile

02/18/2013


Project Team

Electrical Engineering, Instrumentation Engineering, Electrical Construction and Installation: Interstates Companies, Sioux Center, Iowa

Process Design and Mechanical Engineering: Karges-Faulconbridge Inc., St. Paul, Minn.

Construction Management: McGough, St. Paul, Minn.


Integrated project delivery (IPD) and collaboration brought a team of companies together to design and build a green field oil seed processing facility located in the upper Midwest. The facility, with capacity to process 1,000 tons of seed per day, produces food-grade oil. Along with the processing, the facility has capacity to store 830,000 bushels of grain. The site covers 390 acres including the grains receiving, preparation, extraction, refinery, and utilities areas.

To leverage market demand for its finished product, the owner had to commit to local growers that the facility would receive grain at the next harvest. The approaching winter season created additional pressure to begin construction of the foundation and underground electrical system. These factors required that the teams collaborate early to make design decisions and proceed with construction without a fully finished design.

Reflecting on what the team did to ensure the IPD method was successful for this project, Jim Faulconbridge, PE, president of Karges-Faulconbridge Inc., said, “The team stayed focused on the critical path schedule, making sure that the decisions were made in the right order. Also, the willingness to develop design ‘workarounds’ in the absence of complete information was key.”

For a team to successfully execute IPD methods, they must work toward key areas of early budgeting, scheduling, and a strong start-up. Early dependable pricing gives the client, and those financing it, the confidence to continue with a project. Early collaboration lends itself to significant schedule advantages. When team members are collaborating and providing just-in-time design, clients are able to respond to market conditions. In this case, the client and team were focused on completing the grains receiving area by the next harvest.

“To say that every single aspect of the project was smooth sailing due to integrated project delivery would be a stretch,” said Doug Post, PE, president of Interstates Engineering. “However, early agreement to proceed with construction when design was not 100% complete enabled the project to move forward according to the owner’s priorities.”

Start-up is the moment of truth for a project. When the team has worked well together in design and delivery of the project, the owner can feel confident as start-up approaches. “A strong start-up is important,” said Post. “It’s the most recent impression on the owner’s mind when all is said and done.”  

Ultimately, success circles back to the budget. The end result of IPD should be that the project finishes within budget and meets the owner’s business needs.

IPD methods allow team members to work together with the owner to provide value that includes not only the initial construction cost of a facility, but also the long-term cost of ownership. “If the design is calling for 16 valves that need regular maintenance to be situated in locations that can’t be accessed safely and easily, the owner will be reminded of this design decision forever,” said Post. “With early design collaboration, team members have input from many perspectives and can suggest value opportunities. While it may require more piping for the initial installation, the value of future ease of maintenance gained by repositioning those 16 valves to be grounded close to the floor clearly outweighs the added expense.”

 “Early specialty contractor involvement is only as good as the early detailed breakdown of costs and schedule they provide,” said Faulconbridge. “In this case, the team was better able to understand the impacts of proposed P&ID changes as design developed, and manage budget and schedule accordingly. This had the effect of protecting contingencies.”

IPD must capture the value of collaboration. The system must reward collaboration, and the designers must be incented to seek outside perspective on the constructability of the design. To successfully execute IPD, specialty contractors must be encouraged to suggest design alternatives. This project is an example of how early collaboration facilitates better decision making and value for the owner.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2015 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
2016 Engineering Leaders Under 40; Future vision: Where is manufacturing headed?; Electrical distribution, redefined
Strategic outsourcing delivers efficiency; Sleeve bearing clearance; Causes of water hammer; Improve air quality; Maintenance safety; GAMS preview
World-class maintenance: The three keys to success - Deploy people, process and technology; 2016 Lubrication Guide; Why hydraulic systems get hot
Flexible offshore fire protection; Big Data's impact on operations; Bridging the skills gap; Identifying security risks
The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Applying network redundancy; Overcoming loop tuning challenges; PID control and networks
Driving motor efficiency; Preventing arc flash in mission critical facilities; Integrating alternative power and existing electrical systems
Package boilers; Natural gas infrared heating; Thermal treasure; Standby generation; Natural gas supports green efforts

Annual Salary Survey

Before the calendar turned, 2016 already had the makings of a pivotal year for manufacturing, and for the world.

There were the big events for the year, including the United States as Partner Country at Hannover Messe in April and the 2016 International Manufacturing Technology Show in Chicago in September. There's also the matter of the U.S. presidential elections in November, which promise to shape policy in manufacturing for years to come.

But the year started with global economic turmoil, as a slowdown in Chinese manufacturing triggered a worldwide stock hiccup that sent values plummeting. The continued plunge in world oil prices has resulted in a slowdown in exploration and, by extension, the manufacture of exploration equipment.

Read more: 2015 Salary Survey

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.
This article collection contains several articles on the vital role that compressed air plays in manufacturing plants.
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
This article collection contains several articles on strategic maintenance and understanding all the parts of your plant.
click me