For a condition monitoring analyst, it’s just the facts

Don’t contribute to unnecessary maintenance costs

05/14/2012


A condition monitoring analyst encounters many challenges. One of the primary ones is to determine when to report a defect finding. Should it be reported now or should reporting wait until the severity of the defect increases? How near is the problem that has been found to actual failure? Each of these questions is difficult to answer.

A good analyst can use the condition monitoring data that has been collected to determine the severity of the problem found. However, it is impossible to determine the time or day the identified component will actually fail.

What happens if the replacement component (bearing, etc.) requires a very long lead time to obtain? What happens if a crane has to be scheduled to remove the equipment for repair? What happens if contractors have to be scheduled to support the repair effort? What if an outage is scheduled soon and the analyst waits until afterwards to report the problem?

These types of things may not be within the knowledge or control of the analyst. However, the way a condition monitoring analyst responds can greatly influence the ability of a facility to take action so that equipment health can be maintained and maintenance costs controlled.

What should the analyst do? It is always best to report any equipment defect as soon as it has been identified. Uptime, reliability, safety, etc. should not be put at risk to obtain a little extra life out of the failing component (bearing, etc.) that has been identified as having a problem.

The goal of any condition monitoring analyst should be to identify impending defects and provide as much time to correct them as possible. This allows proper planning and scheduling to be completed. This allows a facility the opportunity to keep equipment in the most reliable state, maintain uptime, maintain and increase capacity and avoid unnecessary cost.

If you are a condition monitoring analyst do not wait to report your findings. Do not contribute to the unnecessary maintenance costs that your skills and technology are supposed to help avoid. Generate a machine condition report, send an email, create a work order request, make a telephone call, or take those actions that are required to properly report the defect or impending failure. Make sure that you use the necessary communication method or a combination of methods to alert as quickly as possible those responsible for completing the required repairs. Once this is completed your responsibilities are not over. Monitor the equipment health and the status of your request for action on the equipment. Make sure that the equipment condition is not becoming worse and do not allow the health condition of the equipment to be forgotten or action to be delayed to the point of equipment failure. This may require follow-up communication with those responsible for completing the necessary repairs. You may have to become a pest to make sure that action is taken!

Additionally, make sure that the work order requires a follow-up evaluation from the appropriate condition monitoring technologies after the repair has been completed. This will allow verification that the repair was completed correctly and no additional equipment issues or defects have been introduced as a result of the repair actions taken.

These steps will help to make sure that the equipment is ready to perform its intended function. A machine that is properly monitored by the appropriate condition monitoring technologies, correctly evaluated and maintained leads to an efficiently producing, more reliable machine. This in turn ensures more reliable production, better quality, operating more safely and reduced cost to maintain and operate. It may be surprising how the actions of a dedicated condition monitoring analyst can contribute in a positive way toward the reliability and financial goals of the facility and company that employs him or her

Trent Phillips is the Condition Monitoring Manager for LUDECA, INC., leading provider of shaft alignment, vibration analysis and balancing equipment. He can be reached at 305-591-8935 or Trent.Phillips(at)ludeca.com or www.ludeca.com 



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
The true cost of lubrication: Three keys to consider when evaluating oils; Plant Engineering Lubrication Guide; 11 ways to protect bearing assets; Is lubrication part of your KPIs?
Contract maintenance: 5 ways to keep things humming while keeping an eye on costs; Pneumatic systems; Energy monitoring; The sixth 'S' is safety
Transport your data: Supply chain information critical to operational excellence; High-voltage faults; Portable cooling; Safety automation isn't automatic
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Synchronizing industrial Ethernet networks; Selecting protocol conversion gateways; Integrating HMIs with PLCs and PACs
Why manufacturers need to see energy in a different light: Current approaches to energy management yield quick savings, but leave plant managers searching for ways of improving on those early gains.

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.