Focus on data centers: Fire and life safety

Designing efficient and effective data centers and mission critical facilities is a top priority for consulting engineers. Engineers discuss fire and life safety, fire suppression, and the complexity of data centers.

01/21/2013


Participants

  • Cyrus Gerami, PE, LEED, CxA, Associate, Senior Project Engineer/Manager, exp Global Inc., Maitland, Fla.
  • Kerr Jonstone, IEng, MIET, Senior Electrical Engineer, CH2M Hill, Glasgow, Scotland 
  • Keith Lane, PE, RCDD/NTS, LC, LEED AP, President, Lane Coburn & Assocs., Bothell, Wash. 
  • James McEnteggart, PE, Vice President, Primary Integration Solutions Inc., Charlotte, N.C.
  • Robert M. Menuet, PE, Senior Principal, GHT Ltd., Arlington, Va. 
  • Brian Rener, PE LEED AP, Electrical Platform Leader and Quality Assurance Manager, M+W Group, Chicago, IL.

Fire/Life safety

CSE: What unique fire suppression systems have you specified or designed in mission critical facilities and data centers?

Johnstone: For different clients we have used various suppression systems, and while Terremark employed a water mist system within its data center, we have used other methodologies. A project in Budapest (Hungary) employed a nitrogen-based system, which for code compliance required a “live” test for the local authorities. In addition we also have experience with a CO2 suppression installation for generator containers, while an argonite gas suppression system was retrofitted into an existing live data center without any impact on its operation.

Rener: The usual suspects such as preaction, FM200, and inergen. However, we have occasionally worked with water mist systems in auxiliary areas like generator rooms.

CSE: How have the costs and complexity of fire protection systems changed in recent years?

Johnstone: In our experience there has been no unforeseen increase in fire suppression costs and they have typically remained in line with other costs. The information, however, that is available to site operations staff regarding the operation and performance of fire protection systems has improved dramatically. This increased performance and operation information enables maintenance staff to interrogate fire networks, thereby improving risk management and mitigation.

CSE: What are some important factors to consider when designing a fire and life safety system? What things often get overlooked?

Johnstone: With gaseous solutions, things that often get overlooked and require to be considered include:

· Overpressurization of the space and pressure relief

· “Asphyxiant” nature of gaseous systems for welfare of occupants

· Gaseous removal on accidental discharge. Accidental discharge would not be attended by fire authorities; therefore, removal of accidental discharge is by the client.

There are a number of important factors to consider when designing a fire and life safety system, and the fundamental and most important consideration is: Are we designing to protect life, or life and property? Once determined, we can design the fire and safety system to the required category. One thing that can often get overlooked is the probability of false alarms due the nature of the building and the sensitivity of the devices installed. This then introduces an additional complexity when commissioning the system in terms of introducing double-knock systems to mitigate against false alarms, which can result in loss of time and cost to the facility.



Gerardo , Non-US/Not Applicable, Mexico, 02/14/13 11:39 AM:

The application of double-interlocked pre-action systems in small data center computer rooms have proven both economic and practically maintenance free for over 18 years since the original installation. Periodic inspection and preventive maintanance have been key to continuous operation of the site.
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.