There are many ways of setting PID strategy to make a controller respond the way you want it to. It all depends on what you think should happen.

04/01/2010


In an earlier life, I was overseeing commissioning of a control system that our company had manufactured as part of a larger flue gas conditioning package. I was on the site with the system integrator that we had used to configure the controller. The customer wanted us to tune the main control loop but the integrator said that part of the process fell outside of his scope of supply. He did not want to do any loop tuning, no way, no how. Given that the whole project was not going well, I pressed the request and he told me that loop behavior needs to be tailored to the process and he wasn't going to do it. Ultimately, after much haggling, the customer relented and did the tuning.

At that time I didn't fully appreciate the substance of the discussion. Either a loop works or it doesn't, right? Eventually I came to understand that the way a system responds has to be appropriate for the application. When we write articles on the topic of PID control for Control Engineering , we have to approach these subtleties as best we can. Usually when Vance VanDoren discusses loop tuning, he does it in the context of setpoint changes rather than compensating for upsets. This is deliberate, and Vance and I have discussed that how you tune for setpoint changes can be much different than how you want your controller to respond to an upset. This topic will most certainly be the basis for a feature article one of these months.

Until then, here is a brief discussion of the topic that may get you thinking. Farther down the page there are three pairs of diagrams with a process variable and setpoint. Each pair (left and right) illustrates how a particular tuning strategy responds to a set point change (left) compared to an upset (right) of similar magnitude. The upper half of the graph shows what the variable is doing, and the lower half shows the controller output. Each scenario illustrates the same magnitude change, but with a different approach to compensating for it.

Aggressive PI control set point tracking

Aggressive PI control, set point tracking

Aggressive PI control, load response

Aggressive PI control, load response

Moderate PI control, set point tracking

Moderate PI control, set point tracking

Moderate PI control, load response

Moderate PI control, load response

Aggressive I-PD, set point tracking

Aggressive I-PD control, set point tracking

Aggressive I-PD control, load response

Aggressive I-PD control, load response 

These charts were sent by Bob Rice, director of solutions engineering for Control Station. He includes the following explanation:

"The primary difference between a load (disturbance/upset) response and a set point response lies in the objective the end-user is typically trying to achieve. In most cases, users trying to get a good set point response are looking for a fast but smooth response which usually comes from the use of less aggressive tuning parameters. If the user is trying to reject a disturbance, then they are after a much faster response using more aggressive tunings. Therefore, they are at best conflicting control objectives. You cannot be both quick and responsive, while being smooth with little to no overshoot. There is always a trade-off when trying to tune for both set point tracking and load rejection using a typical PID-type controller. There is an‘I-PD' type controller, which is a ‘proportional on measurement' approach vs. ‘proportional on error,' which can improve the set-point tracking response under aggressive PI-control."

Also read:

Understanding PID control

Loop tuning fundamentals

The three faces of PID

Understanding derivative in PID control

-Peter Welander, process industries editor, PWelander@cfemedia.com
Control Engineering Process & Advanced Control Monthly eNewsletter
Register here to select your choice of free eNewsletters.



No comments
The Top Plant program honors outstanding manufacturing facilities in North America. View the 2013 Top Plant.
The Product of the Year program recognizes products newly released in the manufacturing industries.
The Leaders Under 40 program features outstanding young people who are making a difference in manufacturing. View the 2013 Leaders here.
The new control room: It's got all the bells and whistles - and alarms, too; Remote maintenance; Specifying VFDs
2014 forecast issue: To serve and to manufacture - Veterans will bring skill and discipline to the plant floor if we can find a way to get them there.
2013 Top Plant: Lincoln Electric Company, Cleveland, Ohio
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Plant Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Bring focus to PLC programming: 5 things to avoid in putting your system together; Managing the DCS upgrade; PLM upgrade: a step-by-step approach
Balancing the bagging triangle; PID tuning improves process efficiency; Standardizing control room HMIs
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software

Annual Salary Survey

Participate in the 2013 Salary Survey

In a year when manufacturing continued to lead the economic rebound, it makes sense that plant manager bonuses rebounded. Plant Engineering’s annual Salary Survey shows both wages and bonuses rose in 2012 after a retreat the year before.

Average salary across all job titles for plant floor management rose 3.5% to $95,446, and bonus compensation jumped to $15,162, a 4.2% increase from the 2010 level and double the 2011 total, which showed a sharp drop in bonus.

2012 Salary Survey Analysis

2012 Salary Survey Results

Maintenance and reliability tips and best practices from the maintenance and reliability coaches at Allied Reliability Group.
The One Voice for Manufacturing blog reports on federal public policy issues impacting the manufacturing sector. One Voice is a joint effort by the National Tooling and Machining...
The Society for Maintenance and Reliability Professionals an organization devoted...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
Maintenance is not optional in manufacturing. It’s a profit center, driving productivity and uptime while reducing overall repair costs.
The Lachance on CMMS blog is about current maintenance topics. Blogger Paul Lachance is president and chief technology officer for Smartware Group.